Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Goods train wagons run over eight workers in Odisha, six killed

Goods train wagons run over eight workers in Odisha, six killed
The railway officials present at the spot have taken them to hospital. So far, six of them have died while two critically injured workers have been admitted in the SCB Medical College and Hospital, Cuttack, he said.

Goods train wagons run over eight workers in Odisha, six killed

NCB busts pan-India darknet LSD trafficking network, students among 6 arrested

NCB busts pan-India darknet LSD trafficking network, students among 6 arrested
The NCB seized 15,000 blots of LSD worth several crore rupees from them. This is a pan-India drug trafficking network connected to an international chain that primarily operates on the darknet, said officials.

NCB busts pan-India darknet LSD trafficking network, students among 6 arrested

Fake policeman held for extorting Rs 50,000

Fake policeman held for extorting Rs 50,000
The victim remained in the car, meanwhile another person who introduced himself as a senior police officer, demanded Rs 1 lakh, the victim then transferred Rs 50,000 from his brother's account to the account mentioned by the suspects.

Fake policeman held for extorting Rs 50,000

Talks of Pilot floating new party mere speculation, says Randhawa

Talks of Pilot floating new party mere speculation, says Randhawa
Stating that Pilot will not float a new party, Randhawa said, "Pilot and (Ashok) Gehlot will work together. Both of them know that the formula for reconciliation was reached on the day of the meeting in Delhi. But I cannot disclose the formula."

Talks of Pilot floating new party mere speculation, says Randhawa

Modi thanks US Speaker for inviting him to address joint meeting of Congress

Modi thanks US Speaker for inviting him to address joint meeting of Congress
The Prime Minister was responding to McCarthy's tweet of June 2, when he had said, "It is my honor to invite @PMOIndia @narendramodi to address a Joint Meeting of Congress on Thursday, June 22nd."

Modi thanks US Speaker for inviting him to address joint meeting of Congress

Man held at IGI airport for smuggling gold in shoes

Man held at IGI airport for smuggling gold in shoes
The gold concealed in a pair of shoes that the accused was carrying. A senior official said that the man was detained at the airport due to his suspicious activities. Further investigation into the matter is currently underway.

Man held at IGI airport for smuggling gold in shoes