A Chronology Of Events In The Site C Dam Project In British Columbia

The Canadian Press, 12 Dec, 2017 02:10 PM
    VICTORIA — A chronology of events in British Columbia's Site C hydroelectric dam project:
     
    Late 1950s: The location for a third dam on the Peace River is first looked at after the locations of WAC Bennett Dam and Peace Canyon Dam were identified.
     
    1970s: Engineering work is done to determine the feasibility of a third dam.
     
    1989: Plans for Site C are shelved because of local opposition to the project. 
     
    March 2001: The chairman of BC Hydro says he would like to see the project revived and get fast-track approval from the government.
     
    April 2004: BC Hydro includes Site C in a package of initiatives it is studying to boost the province's long-term supply of hydroelectricity.
     
    December 2007: Preliminary cost estimates for Site C show the project could cost between $5 billion and $6.6 billion, doubling previous estimates by the province.
     
    April 2010: The B.C. government announces plan to build Site C.
     
    December 2013: Public hearings begin on the project.
     
    May 2014: A joint review panel gives no clear yes or no answer but says B.C. will need new energy at some point. It says the project would cause significant adverse effects on the environment and wildlife, as well as Aboriginal communities and farmers in the area.
     
    October 2014: Provincial and federal environmental certificates are issued. 
     
    December 2014: The B.C. government makes the decision to go ahead with construction.
     
    July 2015: Construction begins on Site C.
     
    July 2015: The B.C. Supreme Court dismissed a petition by the Peace Valley Landowner Association challenging provincial environmental approval of Site C. An appeal was dismissed in September 2016.
     
    August 2015: The federal court dismissed an application by Prophet River First Nation and West Moberly First Nations challenging environmental approval of Site C by the federal government. An appeal was dismissed in January 2017. 
     
    February 2016: A judge orders protesters to leave their tent camp near the construction site after BC Hydro seeks an injunction.
     
    December 2016: The government says the project is on schedule and on budget.
     
    March 2017: The government says more than 2,000 workers are employed at Site C.
     
    Aug. 2, 2017: The province's newly sworn-in NDP government asks the B.C. Utilities Commission to review the project as it considers cancelling or delaying its construction.
     
    Aug. 28, 2017: A United Nations panel says construction of the dam should be stopped until there is a full review of how it would affect Indigenous land.
     
    Nov. 1, 2017: The B.C. Utilities Commission says the project is over budget and behind schedule in its report to the government, which promises a decision on Site C's future by the end of the year.
     
    Dec. 11, 2017: Premier John Horgan says the dam will be completed but the price tag is expected to rise from $8.3 billion to $10.7 billion.

    MORE National ARTICLES

    Pro-Nazi Posters Discovered At B.C. University On Remembrance Day

    Pro-Nazi Posters Discovered At B.C. University On Remembrance Day
    Philip Steenkamp, UBC's vice-president of external relations, says in a statement that the "disturbing" posters were discovered on War Memorial Gym on Saturday.

    Pro-Nazi Posters Discovered At B.C. University On Remembrance Day

    Drug Users, First Responders Share Stories From The Overdose Crisis' Front Lines

    Drug Users, First Responders Share Stories From The Overdose Crisis' Front Lines
    "Thank you so much for saving my life," Rea reads aloud to a crowd of 80 people packed into a community hall in the tony Vancouver neighbourhood of Kitsilano.

    Drug Users, First Responders Share Stories From The Overdose Crisis' Front Lines

    Home sales in B.C. rise in October despite higher prices, less choice

    Home sales in B.C. rise in October despite higher prices, less choice
    The British Columbia Real Estate Association says there were 8,677 residential sales across the province in October, a leap of 19.3 per cent over the same period last year.

    Home sales in B.C. rise in October despite higher prices, less choice

    Pender Island Beaver Battle: Parks Canada Asked To Reconsider Euthanasia

    Pender Island Beaver Battle: Parks Canada Asked To Reconsider Euthanasia
    PENDER ISLAND, B.C. — A battle over beavers is brewing on South Pender Island, B.C., where residents are vowing to save the animals from euthanasia.

    Pender Island Beaver Battle: Parks Canada Asked To Reconsider Euthanasia

    Ferry Service Resumes But No Power For Thousands Of Vancouver Island Customers

    Ferry Service Resumes But No Power For Thousands Of Vancouver Island Customers
     Ferry service has resumed on two routes between Tsawwassen and Vancouver Island after high winds cancelled sailings on Monday.

    Ferry Service Resumes But No Power For Thousands Of Vancouver Island Customers

    Amid Complaints, Quebec Town Forbids Nudity In Pool Locker Rooms

    Amid Complaints, Quebec Town Forbids Nudity In Pool Locker Rooms
    A Montreal-area town has decided to forbid all nudity in the locker rooms of its municipal pools — a level of discretion that has one man wondering if it doesn't go too far. 

    Amid Complaints, Quebec Town Forbids Nudity In Pool Locker Rooms