Darpan News Desk The Canadian Press, 08 Mar, 2022 01:02 PM
  • B.C. adds conditions for Trans Mountain expansion

VANCOUVER - British Columbia has amended the conditions of its environmental assessment certificate for the Trans Mountain pipeline expansionand told the federal government it still has concerns about its response to potential marine oil spills.

The changes announced in late February focus on the impacts of marine shipping and potential oil spills from ships related to the pipeline project.

The expansion is set to nearly triple the capacity of the existing 1,150-kilometre pipeline that carries 300,000 barrels per day of petroleum products from Alberta to B.C., which will significantly increase the number of tankers carrying oil for export.

In a letter relaying B.C.'s updated conditions, Environment Minister George Heyman and Energy Minister Bruce Ralston urged federal Natural Resources Minister Jonathan Wilkinson to adopt a series of recommendations that would address the province's concernsafter it consulted with Indigenous nations, municipalities, government agencies and the public.

Those concerns would be most effectively addressed by Ottawa as part of the regulations and measures that fall under federal jurisdiction, Heyman and Ralston wrote in the letter, dated Feb. 24.

B.C. has made changes that are under its jurisdiction and sought to avoid duplicating existing federal regulations, the province said in a news release.

One of B.C.'s recommendations encourages Transport Canada to "expand the scope of its oversight" to include work done by the Western Canada Marine Response Corp., which responds to spills. In particular, it says Transport Canada's oversight should include shoreline cleanup, planning for sunken and submerged oil, co-ordinating volunteers, and managing wildlife and waste in the event of a spill.

"We strongly urge you to carefully consider these important recommendations, and to take action on them ... as soon as possible, so that the (Trans Mountain expansion) is operated in as safe a manner as possible," the ministers wrote.

Among B.C.'s new conditions is a requirement that Trans Mountain, a federal Crown corporation, provide a report on health risks in the event of a marine oil spill. It must identify measures to reduce human exposure and negative health effects and outline which authorities would be responsible.

Another condition requires Trans Mountain to provide a report with baseline data on B.C.'s shoreline in areas that could be affected by an oil spill, including Vancouver's English Bay and the Strait of Georgia. The report should include information on land use, infrastructure, flora and fauna, the order says.

The province has also amended a condition to require updates every five years on research Trans Mountain is involved with related to diluted bitumen and how the heavier, unrefined oil product could be cleaned up if spilled in water.

A Trans Mountain spokesperson said it is reviewing the changes to determine next steps.

Neither Wilkinson nor anyone from his Department of Natural Resources was available to comment on the provincial government's request.

Andrew Radzik, an energy campaigner with the Georgia Strait Alliance, said the province's changes are welcome, but gaps remain.

"If a spill happens, we've got better baseline data. So that's great, that's important. That's information that will inform spill response plans," he said in an interview.

"But they're not requiring shoreline spill response plans of a particular standard."

Instead, the province is relying on federal regulations on marine shipping and spill response that it has criticized for being too vague, Radzik said.

Transport Canada requires certified marine response organizations to treat 500 metres of shoreline per day and the Western Canada Marine Response Corp. has indicated it's working to increase its capacity to 3,000 metres.

But the existing regulations and emergency plans for the pipeline expansion lack some key detail, Radzik said, like what exactly it means to fully "treat" a shoreline.

The province shares jurisdiction along its shoreline and it could have amended the project's certificate to require more specific information or standards, he said.

On human health risks, Radzik said it's a step forwardfor B.C. to require an outline of the roles and responsibilities of different levels of government and the pipeline operator in reducing exposure after a potential spill.

However, it's not clear who would foot the bill for those health measures and what portion the province would have to pay, he said.

Asked why B.C.'s new conditions didn't include more specific requirements for marine spill preparedness and response, the Environment Ministry said the changes reflect certain criteria it had to follow in its review.

The opportunity for B.C. to change its environmental assessment certificate stemmed from a 2018 decision by the Federal Court of Appeal.It found the National Energy Board, since renamed the Canada Energy Regulator, had incorrectly excluded marine shipping from its assessment.

The regulator reconsidered the potential impacts, and the federal government used the subsequent report in 2019 to approve the pipeline expansion for a second time.

The B.C. Court of Appeal later decided that because the provincial ministers who issued the environmental assessment certificate had relied on the regulator's original assessment, they should have the opportunity to consider the later report and make changes, provided the issues related to differences between the two reports and fell under provincial jurisdiction.

MORE National ARTICLES

More than 1M COVID-19 doses wasted: survey

More than 1M COVID-19 doses wasted: survey
The survey suggests at least 1,016,669 doses have been rejected since vaccines first arrived last December. That's about 2.6 per cent of the entire supply delivered to the provinces and territories that provided their numbers.    

More than 1M COVID-19 doses wasted: survey

B.C. restaurants struggle with supply after floods

B.C. restaurants struggle with supply after floods
Restaurant operators in British Columbia's southern Interior are scrambling after flooding and landslides closed highways and rail lines, cutting businesses off from the supply chains they rely on. It's the latest hurdle after 20 months of struggles through the COVID-19 pandemic and a summer of smoky skies from wildfires that wiped out tourism.

B.C. restaurants struggle with supply after floods

Health Canada approves first COVID-19 vaccine for kids aged 5 to 11

Health Canada approves first COVID-19 vaccine for kids aged 5 to 11
Health Canada has approved the first COVID-19 vaccine for children aged five to 11 in Canada, and the first shipment of doses is expected to arrive in the country by Sunday. Pfizer and its partner BioNTech submitted a request for approval of a child-sized dose of its mRNA vaccine for COVID-19 on Oct. 18.

Health Canada approves first COVID-19 vaccine for kids aged 5 to 11

Merritt, B.C., evacuees seeking help in Kamloops

Merritt, B.C., evacuees seeking help in Kamloops
Barkad Khan wiped away tears Thursday as he made another "frustrating" visit to one of the emergency reception centres set up to help residents from Merritt, B.C., who have been forced from their homes due to unprecedented flooding. Khan said he and his family, wife Afreen and daughters Mahveen and Mahira, were given just 10 minutes to get out before their home was flooded.

Merritt, B.C., evacuees seeking help in Kamloops

Military helps ramp up flood relief efforts

Military helps ramp up flood relief efforts
Public Safety Minister Mike Farnworth has indicated that measures could include an order preventing passage for all but essential travellers as limited access is slowly restored along some highways.

Military helps ramp up flood relief efforts

Domtar mill in Kamloops to be sold with takeover

Domtar mill in Kamloops to be sold with takeover
The companies say the facility will be sold to resolve the Competition Commissioner of Canada's concerns about the implication on the purchase of wood fibre from the Thompson/Okanagan region in British Columbia.

Domtar mill in Kamloops to be sold with takeover