B.C. Asks Utilities Commission To Review $8.8-Billion Site C Dam Megaproject

The Canadian Press, 03 Aug, 2017 02:06 PM
    VANCOUVER — British Columbia's New Democrat government has requested an independent review of the $8.8-billion Site C dam, threatening thousands of construction jobs on what was a signature megaproject for former premier Christy Clark.
     
    The government has asked the B.C. Utilities Commission to determine the economic viability of the massive hydroelectric dam on the Peace River. The review will begin Aug. 9, with interim findings six weeks later and a final report by Nov. 1.
     
    The NDP campaigned on having the project reviewed by the commission, a practice that was once standard in B.C., before the previous Liberal government's clean-energy laws allowed some projects to bypass the regulatory agency.
     
    "The previous government refused to allow our independent energy watchdog to examine the project to determine if it was in the public interest," Energy Minister Michelle Mungall said Wednesday.
     
    "That was wrong. We're sending this project to the BCUC to ensure we make the right decision for B.C. families."
     
    Mungall said the commission has been asked to confirm whether BC Hydro is on target to complete Site C on budget and by 2024.
     
     
     
     
    It has also been asked to provide advice on three possible outcomes: proceeding with the project, suspending construction and keeping the option open to resume until 2024, or terminating the project and proceeding with other energy options.
     
    Mungall said the utilities commission will be required to consult with interested parties, including First Nations, and it may consider expert advice and public input as well.
     
    The dam is two years into construction and employs more than 2,000 people in northeastern B.C. It would be the third dam on the Peace River, flooding an 83-kilometre stretch of valley, and has faced fierce opposition from local First Nations, landowners and farmers.
     
    Former BC Hydro CEO Jessica McDonald warned in June that delaying the evictions of two homes would result in a one-year delay of a road and bridge construction project at a cost $630 million.
     
    However, Mungall said that rerouting a highway to save one of the homes was an option.
     
    BC Hydro confirmed Wednesday that while some highway realignment work will be delayed, mitigation options have been identified so that river diversion can remain on track and the overall project schedule and budget can be maintained, should the project proceed.
     
    The Green party, led by Andrew Weaver, has agreed to support the NDP in a minority government. The Liberals, now in Opposition, questioned the New Democrats' motivations for requesting a review.
     
     
    "Is this fake review being done in the best interest of the British Columbia taxpayer or is this simply another way of appeasing Andrew Weaver to prop up their partisan alliance?" asked Liberal member of the legislature Mike Bernier in a statement.
     
    "It is clear this review is designed to meet the NDP's political needs and not the province's electricity needs."
     
    Weaver said in a statement that the Greens were consulted early on the terms of reference for the review, but the final draft was the responsibility of cabinet.
     
    Construction will continue while the review is underway, but that provides little solace to the 2,400 people working on the project, said Chris Gardner, president of the Independent Contractors and Business Association.
     
    "They've got to be thinking that six months from now they may not have a job," he said.
     
    "Site C was reviewed for three years by an independent panel. BC Hydro spent a decade planning for the project. The provincial and federal levels of government both approved the project. It's now 20 per cent complete."
     
     
     
    However, environmental group Sierra Club BC applauded the government's decision, saying it was good news for ratepayers.
     
    "The reality is that we don't need Site C power, it's hideously expensive and inevitable cost overruns would be paid for by B.C. ratepayers, and more environmentally and economically viable alternatives are available today."

    MORE National ARTICLES

    Vancouver Police Use DNA To Crack Decade-Old Break-And-Enter Cases

    Vancouver Police Use DNA To Crack Decade-Old Break-And-Enter Cases
      Police say they have linked at least 11 residential break-and-enters on the city's west side between 2005 and 2016.

    Vancouver Police Use DNA To Crack Decade-Old Break-And-Enter Cases

    Aerospace Giants Boeing, JetBlue Invest In Indian-Origin's Startup

    Aerospace Giants Boeing, JetBlue Invest In Indian-Origin's Startup
    A hybrid electric aircraft startup founded by an Indian-origin entrepreneur has received investments from aerospace giants Boeing and JetBlue owing to its goal to develop alternative propulsion aircraft.

    Aerospace Giants Boeing, JetBlue Invest In Indian-Origin's Startup

    Vancouver, Get Set For Another Exciting Season of Bard on the Beach!

    Vancouver, Get Set For Another Exciting Season of Bard on the Beach!
    The stages are set for another terrific summer, featuring four classic Shakespeare plays plus a short-run contemporary drama. Together they transport audiences from a mythical past to modern-day Venice and contemporary Vancouver.

    Vancouver, Get Set For Another Exciting Season of Bard on the Beach!

    Police Issue Warning After Carfentanil Found In Drugs Seized North Of Toronto

    Police Issue Warning After Carfentanil Found In Drugs Seized North Of Toronto
    RICHMOND HILL, Ont. — Police are warning the public after the deadly opioid carfentanil was found north of Toronto in York Region.

    Police Issue Warning After Carfentanil Found In Drugs Seized North Of Toronto

    Ten Arrested For Duping People In US, India Of Diamonds Worth $9 Million

    Ten people have been arrested and two others charged for allegedly duping persons in New York, Las Vegas and Mumbai to the tune of over US $9 million through fraudulent diamond trade.

    Ten Arrested For Duping People In US, India Of Diamonds Worth $9 Million

    Company A No-Show In B.C. Provincial Court On English Bay Fuel Spill Charges

    Company A No-Show In B.C. Provincial Court On English Bay Fuel Spill Charges
    The MV Marathassa and Alassia NewShips Management Inc., a firm based in Greece, were due in court Wednesday on 10 charges, including discharge of a pollutant, but only a lawyer for the ship appeared.

    Company A No-Show In B.C. Provincial Court On English Bay Fuel Spill Charges