B.C. First Nations Lawyer Says Crown Didn't Consult On Specific Site C Permits

The Canadian Press, 19 Aug, 2015 10:30 AM
    VANCOUVER — Two northeastern British Columbia First Nations will suffer "irreparable harm" if thousands of hectares of old-growth forest are cleared to build the Site C dam, their lawyer says.
     
    John Gailus told B.C. Supreme Court that a stop-work order should be issued to halt the first phase of the nearly $9-billion hydroelectric project from proceeding along the Peace River.
     
    He said the Crown granted permits for the preparatory phase of construction without consulting with the West Moberly and Prophet River First Nations, which are members of the Treaty 8 Tribal Alliance.
     
    "The Crown truncated their consultation and issued the permits to meet an arbitrary timeline imposed by BC Hydro, we say, contrary to both its contractual obligations and its constitutional obligations," Gailus said Tuesday.
     
    The injunction application comes as the First Nations wait for both B.C. Supreme Court and Federal Court to deliver decisions on a judicial review aimed at quashing the hydroelectric project entirely.
     
    The provincial government granted approval in July for the first of seven construction phases, although the work hasn't yet started.
     
    Court heard the permits authorize the clearing of more than 1,600 hectares of forest, equivalent to about 4,500 truckloads of timber, along the south bank of the Peace River.
     
    Construction of new access roads and bridges, expansion of quarries and removal of beaver dams, eagle nests and the alteration of 163 archeological sites — which may include burial sites — was also authorized, Gailus said.
     
     
    He told court there's no urgency for starting the project.
     
    "There are significant benefits to the B.C. taxpayers for a delay," he said, adding costs will be higher if the work is allowed to move ahead and then the project is overturned.
     
    Outside court, West Moberly Chief Roland Willson called the consultation process a "farce."
     
    He said the First Nations signed an agreement in April to consult with the province on the first phase, but BC Hydro's permits were approved before any meetings.
     
    Willson was particularly concerned that up to 28 eagle nests would be destroyed.
     
    "It doesn't mean anything to anybody if we don't even talk about it and they approve (the permits)," he said. "We actually have to sit down and work through them together."
     
    Last month, Forests Minister Steve Thomson said each of the two dozen approved permit applications was reviewed for its potential impact on the environment and on aboriginal treaty rights.
     
    Thomson said the province conducted an "appropriate consultation process."
     
    BC Hydro expects construction of Site C to take at least a decade. The utility has said the project will power the equivalent of 450,000 homes per year.

    MORE National ARTICLES

    Tekmira Abandons Ebola Drug Development, Changing Focus To Hepatitis B Cure

    Tekmira Abandons Ebola Drug Development, Changing Focus To Hepatitis B Cure
    TORONTO — One month after clinical trials for a once-promising Ebola drug were suspended, the company behind the treatment has suspended all research on the compound.

    Tekmira Abandons Ebola Drug Development, Changing Focus To Hepatitis B Cure

    James Daniel McIntyre Identified As Man Shot By Dawson Creek Police, Anonymous Vows Revenge

    James Daniel McIntyre Identified As Man Shot By Dawson Creek Police, Anonymous Vows Revenge
    The global activist hackers' group Anonymous has claimed through social media that the man was one of its comrades and has vowed revenge against the RCMP.

    James Daniel McIntyre Identified As Man Shot By Dawson Creek Police, Anonymous Vows Revenge

    Winnipeg Man Suspected Of Planning To Aid Terrorism Awaits Court Date

    Winnipeg Man Suspected Of Planning To Aid Terrorism Awaits Court Date
    WINNIPEG — A Winnipeg man suspected of planning terrorist activities is still waiting to find out when his case will go to court.

    Winnipeg Man Suspected Of Planning To Aid Terrorism Awaits Court Date

    Former Vermont Transportation Chief To Push For Resumption Of Train Service To Montreal

    Former Vermont Transportation Chief To Push For Resumption Of Train Service To Montreal
    MONTPELIER, Vt. — A former Vermont transportation secretary is coming out of retirement to help plan resumption of passenger train service between the northeastern United States and Montreal.

    Former Vermont Transportation Chief To Push For Resumption Of Train Service To Montreal

    RCMP National Website Goes Offline, Anonymous Claims Responsibility

    RCMP National Website Goes Offline, Anonymous Claims Responsibility
    Anonymous has no identifiable leadership but online posters who say they're members have claimed responsibility in the past for hacking incidents including the shutdown of the city of Cleveland's website last fall.

    RCMP National Website Goes Offline, Anonymous Claims Responsibility

    Canadian Techs Train Ukrainian Soldiers In The Art Of Bomb Disposal

    Canadian Techs Train Ukrainian Soldiers In The Art Of Bomb Disposal
    The soldiers, from the 4th Engineering Support Regiment, based in Gagetown, N.B., are in Yavoriv, Ukraine to impart skills hard-won in the over decade-long Afghan war.

    Canadian Techs Train Ukrainian Soldiers In The Art Of Bomb Disposal