B.C. First Nations Lawyer Says Crown Didn't Consult On Specific Site C Permits

The Canadian Press, 19 Aug, 2015 10:30 AM
    VANCOUVER — Two northeastern British Columbia First Nations will suffer "irreparable harm" if thousands of hectares of old-growth forest are cleared to build the Site C dam, their lawyer says.
     
    John Gailus told B.C. Supreme Court that a stop-work order should be issued to halt the first phase of the nearly $9-billion hydroelectric project from proceeding along the Peace River.
     
    He said the Crown granted permits for the preparatory phase of construction without consulting with the West Moberly and Prophet River First Nations, which are members of the Treaty 8 Tribal Alliance.
     
    "The Crown truncated their consultation and issued the permits to meet an arbitrary timeline imposed by BC Hydro, we say, contrary to both its contractual obligations and its constitutional obligations," Gailus said Tuesday.
     
    The injunction application comes as the First Nations wait for both B.C. Supreme Court and Federal Court to deliver decisions on a judicial review aimed at quashing the hydroelectric project entirely.
     
    The provincial government granted approval in July for the first of seven construction phases, although the work hasn't yet started.
     
    Court heard the permits authorize the clearing of more than 1,600 hectares of forest, equivalent to about 4,500 truckloads of timber, along the south bank of the Peace River.
     
    Construction of new access roads and bridges, expansion of quarries and removal of beaver dams, eagle nests and the alteration of 163 archeological sites — which may include burial sites — was also authorized, Gailus said.
     
     
    He told court there's no urgency for starting the project.
     
    "There are significant benefits to the B.C. taxpayers for a delay," he said, adding costs will be higher if the work is allowed to move ahead and then the project is overturned.
     
    Outside court, West Moberly Chief Roland Willson called the consultation process a "farce."
     
    He said the First Nations signed an agreement in April to consult with the province on the first phase, but BC Hydro's permits were approved before any meetings.
     
    Willson was particularly concerned that up to 28 eagle nests would be destroyed.
     
    "It doesn't mean anything to anybody if we don't even talk about it and they approve (the permits)," he said. "We actually have to sit down and work through them together."
     
    Last month, Forests Minister Steve Thomson said each of the two dozen approved permit applications was reviewed for its potential impact on the environment and on aboriginal treaty rights.
     
    Thomson said the province conducted an "appropriate consultation process."
     
    BC Hydro expects construction of Site C to take at least a decade. The utility has said the project will power the equivalent of 450,000 homes per year.

    MORE National ARTICLES

    CTV Says Reporter Charged A Year After Arrest While Covering Ferguson Protests

    CTV Says Reporter Charged A Year After Arrest While Covering Ferguson Protests
    CTV says its Los Angeles bureau chief has been charged nearly a year after his arrest while covering the protests in Ferguson, Mo.

    CTV Says Reporter Charged A Year After Arrest While Covering Ferguson Protests

    Toronto Mayor Meets With Olympic Committee As City Weighs Bid For 2024 Games

    Toronto's mayor is one step closer to deciding whether the city will bid to host the 2024 Summer Olympics.

    Toronto Mayor Meets With Olympic Committee As City Weighs Bid For 2024 Games

    Investigators Unable To Determine Cause Of Fire That Killed Four Manitoba Boys

    Investigators Unable To Determine Cause Of Fire That Killed Four Manitoba Boys
    WINNIPEG — Investigators say they are unable to determine the cause of a house fire in rural Manitoba that killed four boys who were between nine and 15 years old.

    Investigators Unable To Determine Cause Of Fire That Killed Four Manitoba Boys

    Sask. Gov Wraps Up Public Consultations On Farmland Ownership Restrictions

    Sask. Gov Wraps Up Public Consultations On Farmland Ownership Restrictions
    Saskatchewan's agriculture minister says almost all options are on the table as the government considers the future of farmland ownership restrictions in the province.

    Sask. Gov Wraps Up Public Consultations On Farmland Ownership Restrictions

    Man Who Found Knife Blade In Back Three Years After Stabbing Files Lawsuit

    Man Who Found Knife Blade In Back Three Years After Stabbing Files Lawsuit
    YELLOWKNIFE — A man from the Northwest Territories has filed a lawsuit against health officials claiming they failed to find a knife blade buried in his back for three years.

    Man Who Found Knife Blade In Back Three Years After Stabbing Files Lawsuit

    Judge allows sailors charged in sex assault to return to U.K. until trial

    Judge allows sailors charged in sex assault to return to U.K. until trial
    HALIFAX — A Nova Scotia Supreme Court judge has ruled three British sailors charged with a sexual assault in Halifax can return to the United Kingdom while on bail.

    Judge allows sailors charged in sex assault to return to U.K. until trial