B.C. First Nations Lawyer Says Crown Didn't Consult On Specific Site C Permits

The Canadian Press, 19 Aug, 2015 10:30 AM
    VANCOUVER — Two northeastern British Columbia First Nations will suffer "irreparable harm" if thousands of hectares of old-growth forest are cleared to build the Site C dam, their lawyer says.
     
    John Gailus told B.C. Supreme Court that a stop-work order should be issued to halt the first phase of the nearly $9-billion hydroelectric project from proceeding along the Peace River.
     
    He said the Crown granted permits for the preparatory phase of construction without consulting with the West Moberly and Prophet River First Nations, which are members of the Treaty 8 Tribal Alliance.
     
    "The Crown truncated their consultation and issued the permits to meet an arbitrary timeline imposed by BC Hydro, we say, contrary to both its contractual obligations and its constitutional obligations," Gailus said Tuesday.
     
    The injunction application comes as the First Nations wait for both B.C. Supreme Court and Federal Court to deliver decisions on a judicial review aimed at quashing the hydroelectric project entirely.
     
    The provincial government granted approval in July for the first of seven construction phases, although the work hasn't yet started.
     
    Court heard the permits authorize the clearing of more than 1,600 hectares of forest, equivalent to about 4,500 truckloads of timber, along the south bank of the Peace River.
     
    Construction of new access roads and bridges, expansion of quarries and removal of beaver dams, eagle nests and the alteration of 163 archeological sites — which may include burial sites — was also authorized, Gailus said.
     
     
    He told court there's no urgency for starting the project.
     
    "There are significant benefits to the B.C. taxpayers for a delay," he said, adding costs will be higher if the work is allowed to move ahead and then the project is overturned.
     
    Outside court, West Moberly Chief Roland Willson called the consultation process a "farce."
     
    He said the First Nations signed an agreement in April to consult with the province on the first phase, but BC Hydro's permits were approved before any meetings.
     
    Willson was particularly concerned that up to 28 eagle nests would be destroyed.
     
    "It doesn't mean anything to anybody if we don't even talk about it and they approve (the permits)," he said. "We actually have to sit down and work through them together."
     
    Last month, Forests Minister Steve Thomson said each of the two dozen approved permit applications was reviewed for its potential impact on the environment and on aboriginal treaty rights.
     
    Thomson said the province conducted an "appropriate consultation process."
     
    BC Hydro expects construction of Site C to take at least a decade. The utility has said the project will power the equivalent of 450,000 homes per year.

    MORE National ARTICLES

    Quebec's Newest Millionaires: Group Of 20 People From Montreal Area Shares $55-Million Jackpot

    Quebec's Newest Millionaires: Group Of 20 People From Montreal Area Shares $55-Million Jackpot
    The $55-million prize is the most money the provincial gaming authority has ever distributed. The Lotto Max prize is a Canada-wide lottery that is held every Friday.

    Quebec's Newest Millionaires: Group Of 20 People From Montreal Area Shares $55-Million Jackpot

    Most Canadian Toddlers Vaccinated Against Key Childhood Diseases: Statistics Canada

    Most Canadian Toddlers Vaccinated Against Key Childhood Diseases: Statistics Canada
    The 2013 Childhood National Immunization Coverage Survey found 89 per cent of two-year-old children had received the recommended number of immunizations against measles, mumps and rubella.

    Most Canadian Toddlers Vaccinated Against Key Childhood Diseases: Statistics Canada

    Provinces, Territories On Unsustainable Fiscal Path As Health Costs Rise: Report

    Provinces, Territories On Unsustainable Fiscal Path As Health Costs Rise: Report
    OTTAWA — A new report is warning that the net debt of the country's provinces, territories and municipalities is on an unsustainable path with health spending set to accelerate along with the aging population.

    Provinces, Territories On Unsustainable Fiscal Path As Health Costs Rise: Report

    Nothing Wrong With NDP Byelection Mailings, Elections Watchdog Says

    OTTAWA — The commissioner of elections has cleared the federal NDP of any wrongdoing related to mass mailings sent into four ridings in the midst of byelections in 2013.

    Nothing Wrong With NDP Byelection Mailings, Elections Watchdog Says

    Horse Racing Community Steps Up To Support Injured Winnipeg Jockey Alyssa Selman

    Horse Racing Community Steps Up To Support Injured Winnipeg Jockey Alyssa Selman
    Alyssa Selman, 29, told CTV Winnipeg on Monday that she is making "good progress" even though she has been told she has only a five per cent chance of ever walking again.

    Horse Racing Community Steps Up To Support Injured Winnipeg Jockey Alyssa Selman

    Pierre Poilievre Criticized For Announcing Child Tax Benefits Wearing Conservative Party Logo

    Pierre Poilievre Criticized For Announcing Child Tax Benefits Wearing Conservative Party Logo
    The employment minister donned the blue shirt with the party crest in Halifax as he kicked off a national effort to tout $3 billion in benefit payments being sent out to families.

    Pierre Poilievre Criticized For Announcing Child Tax Benefits Wearing Conservative Party Logo