B.C. Government Approves Construction Projects For $9-Billion Site C Hydro Dam

The Canadian Press, 08 Jul, 2015 10:54 AM
    FORT ST. JOHN, B.C. — The British Columbia government has granted approval for the first phase of construction to start on the massive Site C hydroelectric dam project on the Peace River.
     
    Two dozen authorizations include conditions under the land, water, forest and wildlife acts and provide permits for timber removal, road building and site preparation.
     
    Forests, Lands and Natural Resources Minister Steve Thomson said there were initially 45 permit applications submitted, but several of them were deferred to allow more time for consultations with First Nations.
     
    Thomson said each application for the construction phase was reviewed for its potential impact on the environment and on aboriginal treaty rights.
     
    All the decisions makers are satisfied that the consultation process was adequate and upholds the duty to consult local First Nations, Thomson said Tuesday.
     
    "A number of the permits have conditions attached to them that were concerns raised during that process," he said in a interview.
     
    Concerns include seasonal timing restrictions, conditions for wildlife, and the sharing of plans with First Nations, Thomson said.
     
    Consultations with the local Treaty 8 First Nation began in August 2014 and concluded last month, but Thomson wouldn't say if the two sides had reached a resolution.
     
    "We have been through the appropriate consultation process. As you know, concerns have been expressed by First Nations. We will see what the response to the decision is," he said.
     
    Several lawsuits by environmental groups, citizens and First Nations have been launched to try to stop construction of the dam and are proceeding through the courts.
     
    But Thomson said the legal action won't stop the building process.
     
    "This is a very, very important project for British Columbia. It has been through an environmental assessment process with conditions. The permits that are needed to get the initial process started have been through an extensive process."
     
    No one from the Treaty 8 First Nation was available for an interview.
     
    Construction of the almost $9-billion project is touted to generate about 10,000 jobs while it floods 55 square kilometres of river valley.  
     
    Site C represents an eight per cent increase to Hydro's energy supply and is expected to generate enough electricity to power about 450,000 homes per year.

    MORE National ARTICLES

    Stephen Harper Lands In Kyiv Amid Tension As Ukraine Pushes Canada To Push G7

    Stephen Harper Lands In Kyiv Amid Tension As Ukraine Pushes Canada To Push G7
    KYIV, Ukraine — Stephen Harper arrived in Kyiv early Saturday as Ukraine's envoy urged the prime minister to push his fellow G7 leaders into a strong political stand against the latest Russian aggression.

    Stephen Harper Lands In Kyiv Amid Tension As Ukraine Pushes Canada To Push G7

    Food Safety Agency Working With Game Farmers To Develop Rules Against Disease

    Food Safety Agency Working With Game Farmers To Develop Rules Against Disease
    EDMONTON — Canada's food safety watchdog says it is developing rules with people who raise elk and deer on commercial farms to guard against animal diseases.

    Food Safety Agency Working With Game Farmers To Develop Rules Against Disease

    Tim Hortons Controversy Shows The Pros, Cons Of Brand Association: Experts

    TORONTO — Tim Hortons is getting a crash course in brand association as the company tries to extinguish the fracas over its decision to pull ads for pipeline giant Enbridge.

    Tim Hortons Controversy Shows The Pros, Cons Of Brand Association: Experts

    Lying G20 Officer Who Choked, Arrested Compliant Man Demoted To Constable

    Lying G20 Officer Who Choked, Arrested Compliant Man Demoted To Constable
    TORONTO — A police sergeant who choked a compliant man he arrested illegally at the G20 summit five years ago and then lied about it was handed a two-month demotion to constable Friday.

    Lying G20 Officer Who Choked, Arrested Compliant Man Demoted To Constable

    Justin Levasseur Charged With Second-Degree Murder Of 79-Year-Old Charan Dhandwar In New Westminster

    Justin Levasseur Charged With Second-Degree Murder Of 79-Year-Old Charan Dhandwar In New Westminster
    A 23-year-old man has been charged with second-degree murder in the attack of an elderly woman while she was out for a walk in New Westminster, B.C.

    Justin Levasseur Charged With Second-Degree Murder Of 79-Year-Old Charan Dhandwar In New Westminster

    Police Call For Witnesses To Sea-to-Sky Highway Crash That Killed Cyclists, Passenger

    Police Call For Witnesses To Sea-to-Sky Highway Crash That Killed Cyclists, Passenger
    RCMP are appealing to the occupants of a dark or black SUV who may have witnessed an erratic driver on the Sea-to-Sky Highway near Lillooet, B.C., before three people were killed in a crash.

    Police Call For Witnesses To Sea-to-Sky Highway Crash That Killed Cyclists, Passenger