B.C. Government Approves Construction Projects For $9-Billion Site C Hydro Dam

The Canadian Press, 08 Jul, 2015 10:54 AM
    FORT ST. JOHN, B.C. — The British Columbia government has granted approval for the first phase of construction to start on the massive Site C hydroelectric dam project on the Peace River.
     
    Two dozen authorizations include conditions under the land, water, forest and wildlife acts and provide permits for timber removal, road building and site preparation.
     
    Forests, Lands and Natural Resources Minister Steve Thomson said there were initially 45 permit applications submitted, but several of them were deferred to allow more time for consultations with First Nations.
     
    Thomson said each application for the construction phase was reviewed for its potential impact on the environment and on aboriginal treaty rights.
     
    All the decisions makers are satisfied that the consultation process was adequate and upholds the duty to consult local First Nations, Thomson said Tuesday.
     
    "A number of the permits have conditions attached to them that were concerns raised during that process," he said in a interview.
     
    Concerns include seasonal timing restrictions, conditions for wildlife, and the sharing of plans with First Nations, Thomson said.
     
    Consultations with the local Treaty 8 First Nation began in August 2014 and concluded last month, but Thomson wouldn't say if the two sides had reached a resolution.
     
    "We have been through the appropriate consultation process. As you know, concerns have been expressed by First Nations. We will see what the response to the decision is," he said.
     
    Several lawsuits by environmental groups, citizens and First Nations have been launched to try to stop construction of the dam and are proceeding through the courts.
     
    But Thomson said the legal action won't stop the building process.
     
    "This is a very, very important project for British Columbia. It has been through an environmental assessment process with conditions. The permits that are needed to get the initial process started have been through an extensive process."
     
    No one from the Treaty 8 First Nation was available for an interview.
     
    Construction of the almost $9-billion project is touted to generate about 10,000 jobs while it floods 55 square kilometres of river valley.  
     
    Site C represents an eight per cent increase to Hydro's energy supply and is expected to generate enough electricity to power about 450,000 homes per year.

    MORE National ARTICLES

    Yosef Gopaul Sentenced To 12 Years In Prison For Killing Surrey Hockey Mom; Says Sorry, Wants Rehab

    Yosef Gopaul Sentenced To 12 Years In Prison For Killing Surrey Hockey Mom; Says Sorry, Wants Rehab
     The family of a British Columbia woman whose motto was "money isn't worth dying for" wept as a 28-year-old man was sentenced for manslaughter after blindsiding her with a rock to the head outside a neighbourhood ice arena.

    Yosef Gopaul Sentenced To 12 Years In Prison For Killing Surrey Hockey Mom; Says Sorry, Wants Rehab

    Vancouver Aquarium Dolphin Hana In Critical Condition After Surgery

    One of two Pacific white-sided dolphins at the Vancouver Aquarium is in critical condition after groundbreaking emergency surgery for a gastrointestinal disorder.

    Vancouver Aquarium Dolphin Hana In Critical Condition After Surgery

    Shooting Outside Coquitlam Centre Mall Puts A Man In Hospital, Gunman On Loose

    Shooting Outside Coquitlam Centre Mall Puts A Man In Hospital, Gunman On Loose
    The shooting that put the unidentified man in hospital with non-life-threatening injuries took place Friday at about 2:45 p.m. in a parking lot at Coquitlam Centre

    Shooting Outside Coquitlam Centre Mall Puts A Man In Hospital, Gunman On Loose

    RCMP Say Man Known For Fleeing Police Arrested After Action-Packed Pursuit In Nanaimo

    RCMP Say Man Known For Fleeing Police Arrested After Action-Packed Pursuit In Nanaimo
    Police say the 31-year-old man was wanted for a number of property- and driving-related offences in Ladysmith and Duncan and was being monitored by RCMP.

    RCMP Say Man Known For Fleeing Police Arrested After Action-Packed Pursuit In Nanaimo

    Expo Line Halted: Bird's Nest Fire Shuts Down Skytrain During Rush Hour Between Burnaby & Vancouver

    Expo Line Halted: Bird's Nest Fire Shuts Down Skytrain During Rush Hour Between Burnaby & Vancouver
    The Expo Line has been halted between Burnaby and Vancouver after a spark from routine track maintenance ignited a bird's nest under a track.

    Expo Line Halted: Bird's Nest Fire Shuts Down Skytrain During Rush Hour Between Burnaby & Vancouver

    Major Oil Spill Could Cost Vancouver Economy $1.2 Billion: City Report

    Major Oil Spill Could Cost Vancouver Economy $1.2 Billion: City Report
    VANCOUVER — A major oil spill caused by Kinder Morgan's Trans Mountain pipeline expansion could cost Vancouver's economy up to $1.2 billion, according to a new report released by the city.

    Major Oil Spill Could Cost Vancouver Economy $1.2 Billion: City Report