B.C. Government Approves Construction Projects For $9-Billion Site C Hydro Dam

The Canadian Press, 08 Jul, 2015 10:54 AM
    FORT ST. JOHN, B.C. — The British Columbia government has granted approval for the first phase of construction to start on the massive Site C hydroelectric dam project on the Peace River.
     
    Two dozen authorizations include conditions under the land, water, forest and wildlife acts and provide permits for timber removal, road building and site preparation.
     
    Forests, Lands and Natural Resources Minister Steve Thomson said there were initially 45 permit applications submitted, but several of them were deferred to allow more time for consultations with First Nations.
     
    Thomson said each application for the construction phase was reviewed for its potential impact on the environment and on aboriginal treaty rights.
     
    All the decisions makers are satisfied that the consultation process was adequate and upholds the duty to consult local First Nations, Thomson said Tuesday.
     
    "A number of the permits have conditions attached to them that were concerns raised during that process," he said in a interview.
     
    Concerns include seasonal timing restrictions, conditions for wildlife, and the sharing of plans with First Nations, Thomson said.
     
    Consultations with the local Treaty 8 First Nation began in August 2014 and concluded last month, but Thomson wouldn't say if the two sides had reached a resolution.
     
    "We have been through the appropriate consultation process. As you know, concerns have been expressed by First Nations. We will see what the response to the decision is," he said.
     
    Several lawsuits by environmental groups, citizens and First Nations have been launched to try to stop construction of the dam and are proceeding through the courts.
     
    But Thomson said the legal action won't stop the building process.
     
    "This is a very, very important project for British Columbia. It has been through an environmental assessment process with conditions. The permits that are needed to get the initial process started have been through an extensive process."
     
    No one from the Treaty 8 First Nation was available for an interview.
     
    Construction of the almost $9-billion project is touted to generate about 10,000 jobs while it floods 55 square kilometres of river valley.  
     
    Site C represents an eight per cent increase to Hydro's energy supply and is expected to generate enough electricity to power about 450,000 homes per year.

    MORE National ARTICLES

    Inquest Into Fatal Mill Blast Makes 33 Recommendations, Finds Deaths Accidental

    Inquest Into Fatal Mill Blast Makes 33 Recommendations, Finds Deaths Accidental
    A five-person jury made the recommendations after eight hours of deliberations on Thursday but ultimately concluded that the fatal 2012 blast at Lakeland Mills in Prince George, B.C., was accidental.

    Inquest Into Fatal Mill Blast Makes 33 Recommendations, Finds Deaths Accidental

    Employment Minister Pierre Poilievre Won't Apologize For Taxpayers' Dollars Spent On 'Vanity Videos'

    Employment Minister Pierre Poilievre Won't Apologize For Taxpayers' Dollars Spent On 'Vanity Videos'
    Poilievre is making no apologies for using taxpayer dollars to produce videos of himself promoting the universal child care benefit.

    Employment Minister Pierre Poilievre Won't Apologize For Taxpayers' Dollars Spent On 'Vanity Videos'

    Stephen Harper Touts Government's Economic Record In Campaign-Style Speech

    With a large Canadian flag as a backdrop, Harper told a packed high school gym in Truro, N.S., that the Conservatives are confident heading into this fall's election.

    Stephen Harper Touts Government's Economic Record In Campaign-Style Speech

    Rob Ford Speaks To Supporters At Fundraiser From Hospital Bed

    Rob Ford Speaks To Supporters At Fundraiser From Hospital Bed
    The former Toronto mayor also thanked those who attended a fundraiser Thursday night, as his brother Doug played the call from his cellphone.

    Rob Ford Speaks To Supporters At Fundraiser From Hospital Bed

    Harper Confident In RCMP Response To Fatal Shootings Last Year In Moncton, N.B.

    Harper Confident In RCMP Response To Fatal Shootings Last Year In Moncton, N.B.
    Harper wouldn't comment on the allegations Friday because they are part of a legal process, but said he was briefed by RCMP Commissioner Bob Paulson on what happened last June 4 in Moncton, N.B.

    Harper Confident In RCMP Response To Fatal Shootings Last Year In Moncton, N.B.

    Canada Sets New Target To Cut Greenhouse Gas Emissions

    Canada Sets New Target To Cut Greenhouse Gas Emissions
    Environment Minister Leona Aglukkaq (ah-GLOO'-kah) says the target is fair and ambitious and reflects Canada's growing economy.

    Canada Sets New Target To Cut Greenhouse Gas Emissions