B.C. Government Approves Construction Projects For $9-Billion Site C Hydro Dam

The Canadian Press, 08 Jul, 2015 10:54 AM
    FORT ST. JOHN, B.C. — The British Columbia government has granted approval for the first phase of construction to start on the massive Site C hydroelectric dam project on the Peace River.
     
    Two dozen authorizations include conditions under the land, water, forest and wildlife acts and provide permits for timber removal, road building and site preparation.
     
    Forests, Lands and Natural Resources Minister Steve Thomson said there were initially 45 permit applications submitted, but several of them were deferred to allow more time for consultations with First Nations.
     
    Thomson said each application for the construction phase was reviewed for its potential impact on the environment and on aboriginal treaty rights.
     
    All the decisions makers are satisfied that the consultation process was adequate and upholds the duty to consult local First Nations, Thomson said Tuesday.
     
    "A number of the permits have conditions attached to them that were concerns raised during that process," he said in a interview.
     
    Concerns include seasonal timing restrictions, conditions for wildlife, and the sharing of plans with First Nations, Thomson said.
     
    Consultations with the local Treaty 8 First Nation began in August 2014 and concluded last month, but Thomson wouldn't say if the two sides had reached a resolution.
     
    "We have been through the appropriate consultation process. As you know, concerns have been expressed by First Nations. We will see what the response to the decision is," he said.
     
    Several lawsuits by environmental groups, citizens and First Nations have been launched to try to stop construction of the dam and are proceeding through the courts.
     
    But Thomson said the legal action won't stop the building process.
     
    "This is a very, very important project for British Columbia. It has been through an environmental assessment process with conditions. The permits that are needed to get the initial process started have been through an extensive process."
     
    No one from the Treaty 8 First Nation was available for an interview.
     
    Construction of the almost $9-billion project is touted to generate about 10,000 jobs while it floods 55 square kilometres of river valley.  
     
    Site C represents an eight per cent increase to Hydro's energy supply and is expected to generate enough electricity to power about 450,000 homes per year.

    MORE National ARTICLES

    Hydro One Fires Shawn Simoes, After Vulgar ‘FHRITP’ Rant Involving CityNews Reporter Shauna Hunt

    Hydro One Fires Shawn Simoes, After Vulgar ‘FHRITP’ Rant Involving CityNews Reporter Shauna Hunt
    Shawn Simoes, a assistant network management engineer with Hydro One — was fired by the company for violating its code of conduct.

    Hydro One Fires Shawn Simoes, After Vulgar ‘FHRITP’ Rant Involving CityNews Reporter Shauna Hunt

    Accused Retired Kamloops Teacher Contradicts Neighbour Who Found CDs Of Child Porn

    Accused Retired Kamloops Teacher Contradicts Neighbour Who Found CDs Of Child Porn
    Jerry Waselenkoff, 66, took the stand in his own defence Tuesday on a single count at his trial in B.C. Supreme Court in Kamloops.

    Accused Retired Kamloops Teacher Contradicts Neighbour Who Found CDs Of Child Porn

    Omar Khadr: Youth Or Adult? Question Goes To Canada's Top Court Thursday

    TORONTO — The case of former Guantanamo Bay prisoner Omar Khadr returns to Canada's top court for a third time on Thursday, as the federal government fights to have him declared an adult offender for crimes he committed as a 15-year-old.

    Omar Khadr: Youth Or Adult? Question Goes To Canada's Top Court Thursday

    Canadian Air Task Force In Iraq Gets Female Commander, Former Sea King Pilot

    Canadian Air Task Force In Iraq Gets Female Commander, Former Sea King Pilot
      Brig.-Gen. Lise Bourgon, has taken over responsibility for the country's air task force in a ceremony at the air base where Canadian aircraft conducting strikes against the Islamic State in Iraq and the Levant are based.

    Canadian Air Task Force In Iraq Gets Female Commander, Former Sea King Pilot

    Canadians Join Campaigners Calling For End To UN Peacekeeper Sex Abuse

    Canadians Join Campaigners Calling For End To UN Peacekeeper Sex Abuse
    The coalition, which calls itself Code Blue, wants UN Secretary Ban Ki-moon to lift the diplomatic immunity that protects UN employees from being held to account when abuse complaints arise.

    Canadians Join Campaigners Calling For End To UN Peacekeeper Sex Abuse

    Quebec Says School Officials Will No Longer Strip-Search Students

    Quebec Says School Officials Will No Longer Strip-Search Students
    QUEBEC — School officials in Quebec will no longer be permitted to strip search students as the provincial government moved to act on a report recommending that only police officers conduct such examinations.

    Quebec Says School Officials Will No Longer Strip-Search Students