B.C. Government Approves Construction Projects For $9-Billion Site C Hydro Dam

The Canadian Press, 08 Jul, 2015 10:54 AM
    FORT ST. JOHN, B.C. — The British Columbia government has granted approval for the first phase of construction to start on the massive Site C hydroelectric dam project on the Peace River.
     
    Two dozen authorizations include conditions under the land, water, forest and wildlife acts and provide permits for timber removal, road building and site preparation.
     
    Forests, Lands and Natural Resources Minister Steve Thomson said there were initially 45 permit applications submitted, but several of them were deferred to allow more time for consultations with First Nations.
     
    Thomson said each application for the construction phase was reviewed for its potential impact on the environment and on aboriginal treaty rights.
     
    All the decisions makers are satisfied that the consultation process was adequate and upholds the duty to consult local First Nations, Thomson said Tuesday.
     
    "A number of the permits have conditions attached to them that were concerns raised during that process," he said in a interview.
     
    Concerns include seasonal timing restrictions, conditions for wildlife, and the sharing of plans with First Nations, Thomson said.
     
    Consultations with the local Treaty 8 First Nation began in August 2014 and concluded last month, but Thomson wouldn't say if the two sides had reached a resolution.
     
    "We have been through the appropriate consultation process. As you know, concerns have been expressed by First Nations. We will see what the response to the decision is," he said.
     
    Several lawsuits by environmental groups, citizens and First Nations have been launched to try to stop construction of the dam and are proceeding through the courts.
     
    But Thomson said the legal action won't stop the building process.
     
    "This is a very, very important project for British Columbia. It has been through an environmental assessment process with conditions. The permits that are needed to get the initial process started have been through an extensive process."
     
    No one from the Treaty 8 First Nation was available for an interview.
     
    Construction of the almost $9-billion project is touted to generate about 10,000 jobs while it floods 55 square kilometres of river valley.  
     
    Site C represents an eight per cent increase to Hydro's energy supply and is expected to generate enough electricity to power about 450,000 homes per year.

    MORE National ARTICLES

    Realtors See Influx Of U.S. Buyers In Canada's Recreational Property Markets

    Realtors See Influx Of U.S. Buyers In Canada's Recreational Property Markets
    TORONTO — Real estate agent Priscilla Sookarow rang in the new year in a novel way, brokering the sale of a $3-million vacation property in B.C.'s Okanagan Valley to a family from Texas.

    Realtors See Influx Of U.S. Buyers In Canada's Recreational Property Markets

    Supreme Court Denies Murder Appeal Of New Brunswick Man In Girlfriend's Death

    Supreme Court Denies Murder Appeal Of New Brunswick Man In Girlfriend's Death
    OTTAWA — The Supreme Court of Canada has declined to hear the appeal of a New Brunswick man found guilty of first-degree murder in the death of his former girlfriend.

    Supreme Court Denies Murder Appeal Of New Brunswick Man In Girlfriend's Death

    Vancouver Pot Regulations Will Restrict Patient Access: Civil Liberties' Group

    Vancouver Pot Regulations Will Restrict Patient Access: Civil Liberties' Group
    VANCOUVER — The British Columbia Civil Liberties Association is applauding Vancouver city council for regulating medical marijuana dispensaries but is warning the new bylaws are too restrictive.

    Vancouver Pot Regulations Will Restrict Patient Access: Civil Liberties' Group

    HarperPac Much-needed Counterbalance: Former Adviser To PM Harper

    HarperPac Much-needed Counterbalance: Former Adviser To PM Harper
    OTTAWA — A former adviser to Prime Minister Stephen Harper says he's not surprised to see right-leaning political organizers fighting back against union-financed third-party groups on the left.

    HarperPac Much-needed Counterbalance: Former Adviser To PM Harper

    Police Seek Deadly Cafe Shooting Suspect North Of Toronto

    Police Seek Deadly Cafe Shooting Suspect North Of Toronto
    Police have released security video images of a suspect and vehicle in a cafe shooting north of Toronto that left two people dead and two others seriously injured.

    Police Seek Deadly Cafe Shooting Suspect North Of Toronto

    B.C. Gets Go-ahead To Pursue Polygamy Charge Against Bountiful Leader

    The leader of a fundamentalist Mormon sect in southeastern B.C. is accused of polygamy for having more than two dozen wives.

    B.C. Gets Go-ahead To Pursue Polygamy Charge Against Bountiful Leader