BC Hydro Lawyer Says Stop-work Order Would Cause Expensive Delays On Site C Dam

Darpan News Desk The Canadian Press, 20 Aug, 2015 12:55 PM
    VANCOUVER — A stop-work order for the Site C dam will cause "extreme prejudice" to BC Hydro at a cost of hundreds of millions of dollars and a one-year delay in the construction schedule, the utility's lawyer says.
     
    Mark Andrews told a B.C. Supreme Court judge that critical milestones will not be met if an injunction is granted to a pair of First Nations.
     
    "This injunction is going to drive a truck into the schedule of the project at this stage in particular," Andrews said Wednesday.
     
    The West Moberly and Prophet River First Nations are challenging the nearly $9-billion project by arguing they were not properly consulted before permits were granted for Site C, the third dam on the Peace River.
     
    The Treaty 8 Tribal Alliance members say they will suffer "irreparable harm" if BC Hydro is allowed to start clearing thousands of hectares of old-growth forest.
     
    They've asked a judge to block work authorized by specific permits.
     
    The first of seven phases of construction is proceeding while the First Nations await decisions on two judicial reviews of environmental assessment certificates granted by the B.C. and federal governments.
     
    Andrews told court some work began in late July and that a year's delay would cost more than $300 million initially, plus another $200 million related to acquiring resources.
     
    He said it would also push back site preparation critical for the primary building contract, worth about $1 billion and slated to be awarded in December. 
     
     
    "If the applicants were seeking to stop this project, they should have moved earlier," Andrews said. 
     
    "The result of them not acting earlier is that prejudice — which I've characterized as extreme — is far worse."
     
    He also argued against the First Nations' assertions about the extent of damage the first stage of construction could cause to their traditional lands.
     
    Andrews said there's no evidence it would result in "serious harm" to heritage sites, describing their contents as stones, flakes, chips and tools.
     
    Established protocols for preserving artifacts could be used to adequately deal with those concerns, he said.
     
    "The clearing and other work that will be done on the south bank will not by any reasonable or objective measure cause serious or irreparable harm to the exercise of the applicant's treaty rights."
     
    The project is in the public interest because the dam's power will flow to British Columbians, he said.
     
    BC Hydro has said the dam is expected increase its energy supply by eight per cent, enough to generate electricity for about 450,000 homes annually.

    MORE National ARTICLES

    B.C. Company's Agile Robots Crawling Where Humans Can't

    B.C. Company's Agile Robots Crawling Where Humans Can't
    What started as a fun project for two techies on Vancouver Island more than 25 years ago has now become an industry leader in robotic crawlers.

    B.C. Company's Agile Robots Crawling Where Humans Can't

    Indian-Origin Journalist Adrienne Batra Honoured in Canada

    Indian-Origin Journalist Adrienne Batra Honoured in Canada
    Adrienne Batra, Toronto Sun newspaper's editor-in-chief, received the "Best Journalist Award" on Friday at 'Parvasi Awards' organised by the Parvasi Media Group.

    Indian-Origin Journalist Adrienne Batra Honoured in Canada

    2 Dead After Car Collides With Moose North Of Quebec City

    2 Dead After Car Collides With Moose North Of Quebec City
    The car jumped the median and crashed into a rock wall after striking the animal around midnight in the Laurentides Wildlife Reserve

    2 Dead After Car Collides With Moose North Of Quebec City

    Party Aims To Give People With Disabilities A Chance To Explore Sexuality

    Party Aims To Give People With Disabilities A Chance To Explore Sexuality
    TORONTO — A party meant to give people with disabilities a chance to explore and express their sexuality is shining a spotlight on an enduring and often ignored barrier for those with physical and mental limitations.

    Party Aims To Give People With Disabilities A Chance To Explore Sexuality

    Suspect In Montreal Double Homicide Turns Himself In To Police Saturday Night

    Suspect In Montreal Double Homicide Turns Himself In To Police Saturday Night
    Police released a video of the suspect entering a bar earlier this week, and had described him as dangerous and possibly armed.

    Suspect In Montreal Double Homicide Turns Himself In To Police Saturday Night

    Keystone Pipeline-Maker Braces For Obama Rejection, Already Planning Next Move

    WASHINGTON — The Canadian company involved in the controversy-plagued Keystone XL pipeline project has begun planning its response to an anticipated rejection of the project by U.S. President Barack Obama.

    Keystone Pipeline-Maker Braces For Obama Rejection, Already Planning Next Move