    VANCOUVER — A stop-work order for the Site C dam will cause "extreme prejudice" to BC Hydro at a cost of hundreds of millions of dollars and a one-year delay in the construction schedule, the utility's lawyer says.
     
    Mark Andrews told a B.C. Supreme Court judge that critical milestones will not be met if an injunction is granted to a pair of First Nations.
     
    "This injunction is going to drive a truck into the schedule of the project at this stage in particular," Andrews said Wednesday.
     
    The West Moberly and Prophet River First Nations are challenging the nearly $9-billion project by arguing they were not properly consulted before permits were granted for Site C, the third dam on the Peace River.
     
    The Treaty 8 Tribal Alliance members say they will suffer "irreparable harm" if BC Hydro is allowed to start clearing thousands of hectares of old-growth forest.
     
    They've asked a judge to block work authorized by specific permits.
     
    The first of seven phases of construction is proceeding while the First Nations await decisions on two judicial reviews of environmental assessment certificates granted by the B.C. and federal governments.
     
    Andrews told court some work began in late July and that a year's delay would cost more than $300 million initially, plus another $200 million related to acquiring resources.
     
    He said it would also push back site preparation critical for the primary building contract, worth about $1 billion and slated to be awarded in December. 
     
     
    "If the applicants were seeking to stop this project, they should have moved earlier," Andrews said. 
     
    "The result of them not acting earlier is that prejudice — which I've characterized as extreme — is far worse."
     
    He also argued against the First Nations' assertions about the extent of damage the first stage of construction could cause to their traditional lands.
     
    Andrews said there's no evidence it would result in "serious harm" to heritage sites, describing their contents as stones, flakes, chips and tools.
     
    Established protocols for preserving artifacts could be used to adequately deal with those concerns, he said.
     
    "The clearing and other work that will be done on the south bank will not by any reasonable or objective measure cause serious or irreparable harm to the exercise of the applicant's treaty rights."
     
    The project is in the public interest because the dam's power will flow to British Columbians, he said.
     
    BC Hydro has said the dam is expected increase its energy supply by eight per cent, enough to generate electricity for about 450,000 homes annually.

    MORE National ARTICLES

    No Winning Ticket For $10.4-million Jackpot In Saturday's Lotto 6-49 Draw

    TORONTO — No one has the winning ticket for the $10.4-million jackpot in Saturday night's Lotto 6-49 draw.

    No Winning Ticket For $10.4-million Jackpot In Saturday's Lotto 6-49 Draw

    Peter Fassbender Eyes New Plan For Translink, Focuses On Public Confidence

    VANCOUVER — One of Premier Christy Clark's most respected ministers is vowing to restore confidence in Metro Vancouver's transit authority plagued by ongoing criticism and the recent defeat at the polls of a multibillion-dollar transportation plan. 

    Peter Fassbender Eyes New Plan For Translink, Focuses On Public Confidence

    Verdict In Canadian Journalist Mohamed Fahmy's Re-trial Postponed Until Aug. 29

    CAIRO — An Egyptian court postponed announcing a verdict in the much criticized case of Mohamed Fahmy once again on Sunday — a move the Canadian journalist described as "crippling."

    Verdict In Canadian Journalist Mohamed Fahmy's Re-trial Postponed Until Aug. 29

    Abbotsford Police Issue Public Warning About Sex Offender James Conway

    Abbotsford Police Issue Public Warning About Sex Offender James Conway
    Forty-year-old James Conway is six feet four inches tall, weighs 240 pounds and has brown hair and blue eyes

    Abbotsford Police Issue Public Warning About Sex Offender James Conway

    Man Attacked By A Group Of Men Outside Metrotown Shopping Centre In Burnaby

    Man Attacked By A Group Of Men Outside Metrotown Shopping Centre In Burnaby
    The victim suffered serious head injuries and was rushed to hospital after the attack just outside The Bay before 2 a.m.

    Man Attacked By A Group Of Men Outside Metrotown Shopping Centre In Burnaby

    Canadian Pacific Crews Dealing With Coal Train Derailment Near Sparwood, B.C.

    Canadian Pacific Crews Dealing With Coal Train Derailment Near Sparwood, B.C.
    SPARWOOD, B.C. — A Canadian Pacific Railway freight train carrying coal has derailed near the southeastern British Columbia community of Sparwood.

    Canadian Pacific Crews Dealing With Coal Train Derailment Near Sparwood, B.C.