BC Hydro Lawyer Says Stop-work Order Would Cause Expensive Delays On Site C Dam

Darpan News Desk The Canadian Press, 20 Aug, 2015 12:55 PM
    VANCOUVER — A stop-work order for the Site C dam will cause "extreme prejudice" to BC Hydro at a cost of hundreds of millions of dollars and a one-year delay in the construction schedule, the utility's lawyer says.
     
    Mark Andrews told a B.C. Supreme Court judge that critical milestones will not be met if an injunction is granted to a pair of First Nations.
     
    "This injunction is going to drive a truck into the schedule of the project at this stage in particular," Andrews said Wednesday.
     
    The West Moberly and Prophet River First Nations are challenging the nearly $9-billion project by arguing they were not properly consulted before permits were granted for Site C, the third dam on the Peace River.
     
    The Treaty 8 Tribal Alliance members say they will suffer "irreparable harm" if BC Hydro is allowed to start clearing thousands of hectares of old-growth forest.
     
    They've asked a judge to block work authorized by specific permits.
     
    The first of seven phases of construction is proceeding while the First Nations await decisions on two judicial reviews of environmental assessment certificates granted by the B.C. and federal governments.
     
    Andrews told court some work began in late July and that a year's delay would cost more than $300 million initially, plus another $200 million related to acquiring resources.
     
    He said it would also push back site preparation critical for the primary building contract, worth about $1 billion and slated to be awarded in December. 
     
     
    "If the applicants were seeking to stop this project, they should have moved earlier," Andrews said. 
     
    "The result of them not acting earlier is that prejudice — which I've characterized as extreme — is far worse."
     
    He also argued against the First Nations' assertions about the extent of damage the first stage of construction could cause to their traditional lands.
     
    Andrews said there's no evidence it would result in "serious harm" to heritage sites, describing their contents as stones, flakes, chips and tools.
     
    Established protocols for preserving artifacts could be used to adequately deal with those concerns, he said.
     
    "The clearing and other work that will be done on the south bank will not by any reasonable or objective measure cause serious or irreparable harm to the exercise of the applicant's treaty rights."
     
    The project is in the public interest because the dam's power will flow to British Columbians, he said.
     
    BC Hydro has said the dam is expected increase its energy supply by eight per cent, enough to generate electricity for about 450,000 homes annually.

    MORE National ARTICLES

    Kinder Morgan Pipeline Opponents Furious About 'Chaotic' Review Process

    VANCOUVER — Opponents of Kinder Morgan's plan to boost capacity of its Trans Mountain pipeline across southern B.C., accuse the National Energy Board of once again changing key dates in the review process.

    Kinder Morgan Pipeline Opponents Furious About 'Chaotic' Review Process

    Pipeline Critics Await High Court's Green Light To Challenge Energy Board

    VANCOUVER — Opponents of Canada's big energy projects will soon learn if the country's highest court will consider an appeal that could drastically alter public participation in National Energy Board reviews.

    Pipeline Critics Await High Court's Green Light To Challenge Energy Board

    On A Scale Of Zero To Five, Manitoba Twister Bad But It Could Have Been Worse

    On A Scale Of Zero To Five, Manitoba Twister Bad But It Could Have Been Worse
    A massive tornado that struck western Manitoba this week has been given an preliminary rating which puts it in the category of large and violent, but not the worst that nature can serve up.

    On A Scale Of Zero To Five, Manitoba Twister Bad But It Could Have Been Worse

    Ontario Liberals Accuse Harper Of Abandoning Workers In The Province

    Ontario Liberals Accuse Harper Of Abandoning Workers In The Province
    TORONTO — Ontario's Liberals waded into the looming federal election Thursday, accusing Prime Minister Stephen Harper of abandoning workers in the province by refusing to co-operate on a new provincial pension plan.

    Ontario Liberals Accuse Harper Of Abandoning Workers In The Province

    Talk Budget To Me: Alberta Finance Minister Wants Ideas, Comments From Public

    Talk Budget To Me: Alberta Finance Minister Wants Ideas, Comments From Public
    EDMONTON — Alberta Finance Minister Joe Ceci is casting a wide net for input into the NDP government's first budget.

    Talk Budget To Me: Alberta Finance Minister Wants Ideas, Comments From Public

    Oilpatch Pain Persists As Cenovus To Cut 300 To 400 More Jobs This Year

    CALGARY — Cenovus Energy says 300 to 400 workers will be let go from its Calgary office by year end as hopes for a quick recovery in oil prices evaporate.

    Oilpatch Pain Persists As Cenovus To Cut 300 To 400 More Jobs This Year