British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

How it started, how it ended: A chronology of Ontario's ad blitz against U.S. tariffs

How it started, how it ended: A chronology of Ontario's ad blitz against U.S. tariffs
Manitoba Premier Wab Kinew encourages Ford to keep the ad campaign going, saying Trump's tariffs betray Reagan's legacy.

How it started, how it ended: A chronology of Ontario's ad blitz against U.S. tariffs

Mark Carney's first budget plots a sharp departure from past fiscal plans

Mark Carney's first budget plots a sharp departure from past fiscal plans
Prime Minister Mark Carney's government is getting ready to table its first budget this week — one that will be markedly different from budgets of the past.

Mark Carney's first budget plots a sharp departure from past fiscal plans

Government expects fewer questions on foreign aid from weakened NDP: briefing note

Government expects fewer questions on foreign aid from weakened NDP: briefing note
A Global Affairs Canada briefing note suggests the department expects fewer questions going forward in the House of Commons about possible cuts to foreign aid from the much-reduced NDP caucus.

Government expects fewer questions on foreign aid from weakened NDP: briefing note

Canada bolsters Indo-Pacific presence with new defence pact with the Philippines

Canada bolsters Indo-Pacific presence with new defence pact with the Philippines
Defence Minister David McGuinty has signed a defence co-operation agreement with the Philippines, on the final day of a visit meant to strengthen defence relations.

Canada bolsters Indo-Pacific presence with new defence pact with the Philippines

B.C. First Nation members vote in favour of treaty, moving toward self-governance

B.C. First Nation members vote in favour of treaty, moving toward self-governance
A First Nation from the northwest coast of British Columbia has voted in favour of a constitution and a treaty that it says opens a path to a new era of self-government. 

B.C. First Nation members vote in favour of treaty, moving toward self-governance

Joly says Canada launching dispute process against Stellantis

Joly says Canada launching dispute process against Stellantis
Industry Minister Mélanie Joly says the federal government is launching a dispute resolution process against Stellantis for moving planned vehicle production from its Brampton, Ont. plant out of the country.

Joly says Canada launching dispute process against Stellantis