BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Another earthquake for B.C., less than four days after cities rattled

Another earthquake for B.C., less than four days after cities rattled
An earthquake has struck off the British Columbia coast, less than four days after major population centres were shaken by a similar-sized tremor. But Earthquakes Canada says the latest quake wasn't felt by anyone and it occurred in the Pacific, 182 kilometres west of Port Alice in northwest Vancouver Island.

Another earthquake for B.C., less than four days after cities rattled

Windstorm knocks out power to thousands of BC Hydro customers along south coast

Windstorm knocks out power to thousands of BC Hydro customers along south coast
An overnight windstorm along British Columbia's south coast has knocked out power for thousands. BC Hydro is reporting more 7,000 people along southern Vancouver Island woke up to outages on Tuesday.

Windstorm knocks out power to thousands of BC Hydro customers along south coast

B.C. plans 'substantive changes' for interprovincial trade

B.C. plans 'substantive changes' for interprovincial trade
British Columbia plans to enter a meeting with other provinces next week prepared to make "substantive changes" to its interprovincial trade barriers as the threat of hefty U.S. tariffs looms, Economic Development Minister Diana Gibson said. Gibson met virtually Friday with her provincial counterparts on the Committee on Internal Trade and said they were committed to reducing trade barriers within the country.

B.C. plans 'substantive changes' for interprovincial trade

Rain and possible snow melt set off high-water warnings for parts of B.C.

Rain and possible snow melt set off high-water warnings for parts of B.C.
A series of wet weather systems bringing rain and a warming trend has prompted high streamflow advisories for waterways on B.C.'s south coast and the lower half of Vancouver Island.  Environment Canada has issued rainfall warnings for Howe Sound and communities in north and eastern Metro Vancouver, saying as much as 100 millimetres of rain could fall by the end of the weekend. 

Rain and possible snow melt set off high-water warnings for parts of B.C.

Liberal party kicks Ruby Dhalla out of leadership race

Liberal party kicks Ruby Dhalla out of leadership race
The Liberal party has kicked Ruby Dhalla out of the leadership race just days before the contestants were to face off in two debates in Montreal. Party national director Azam Ishmael says in a statement published late Friday that the decision was made unanimously by the Liberal Leadership Vote Committee.

Liberal party kicks Ruby Dhalla out of leadership race

Earthquake shakes Vancouver and other B.C. cities

Earthquake shakes Vancouver and other B.C. cities
An earthquake with a preliminary magnitude of 5.1 has shaken Vancouver, Victoria and other B.C. cities. Natural Resources Canada says the quake was centred 24 kilometres north-northeast of Sechelt on the Sunshine Coast.

Earthquake shakes Vancouver and other B.C. cities