BC Hydro says pandemic delays Site C project

Darpan News Desk The Canadian Press, 31 Jul, 2020 08:13 PM
  • BC Hydro says pandemic delays Site C project

British Columbia's massive Site C hydroelectric dam project has been hit hard by the COVID-19 pandemic and now faces construction delays and rising costs.

BC Hydro president Chris O'Riley says in a quarterly update submitted to the B.C. Utilities Commission that the pandemic has had a material impact on safety, cost and schedule for the project in northeast B.C.

Site C's budget in April 2018 was estimated at $10.7 billion, including reserve and contingency funds amounting to about $1.5 billion for unexpected costs.

O'Riley's update to the utilities commission does not estimate the extent of increased costs but says reserve funds are being accessed.

Energy Minister Bruce Ralston says in a statement that he's concerned about the news and has appointed former deputy finance minister Peter Milburn as a special advisor to the project.

Site C will be the third dam and hydroelectric generating station on the Peace River and will provide enough energy to power the equivalent of about 450,000 homes per year in B.C.

MORE National ARTICLES

Closing Arguments Begin In Legal Case Over Private Health Care In B.C.

Closing Arguments Begin In Legal Case Over Private Health Care In B.C.
Peter Gall began his closing arguments Monday in a decade-long constitutional challenge of the Medicare Protection Act of B.C. as lead plaintiff Dr. Brian Day, CEO of Cambie Surgical Corp., looked on from the gallery.

Closing Arguments Begin In Legal Case Over Private Health Care In B.C.

Two Hurt, Four Others Rescued, As Flames Damage Vancouver Apartment Building

VANCOUVER - Firefighters had to work quickly to rescue six residents of a burning apartment building in south Vancouver.

Two Hurt, Four Others Rescued, As Flames Damage Vancouver Apartment Building

Trans Mountain Received $320M In Government Subsidies In First Half 2019: Report

The money included $135.8 million in direct subsidies and $183.8 million in indirect subsidies that were not clearly disclosed to taxpayers, says the report by the Institute for Energy Economics and Financial Analysis.    

Trans Mountain Received $320M In Government Subsidies In First Half 2019: Report

B.C. Introduces Gas Price Transparency Law Forcing Companies To Reveal Data

It's time to reveal to drivers in British Columbia how the price of gasoline is set, says provincial cabinet minister Bruce Ralston.

B.C. Introduces Gas Price Transparency Law Forcing Companies To Reveal Data

Police Release Sketch Of Suspect Wanted In Brampton Sex Assault

Investigators from the Peel Regional Police Special Victims Unit are continuing to seek the public’s assistance in relation to a sexual assault investigation in the City of Brampton.

Police Release Sketch Of Suspect Wanted In Brampton Sex Assault

Are You A Taxi Driver? If You Are, It’s Time To Start Buckling Up.

Taxi drivers used to be exempt from wearing seatbelts under Section 32.02 of the Motor Vehicle Act, as long as they remained under 70km/h. 

Are You A Taxi Driver? If You Are, It’s Time To Start Buckling Up.