BC Hydro Sets Contract For Controversial Site C Dam At $1.75 Billion

Darpan News Desk The Canadian Press, 22 Dec, 2015 11:53 AM
  • BC Hydro Sets Contract For Controversial Site C Dam At $1.75 Billion
VANCOUVER — British Columbia's power utility will pay a consortium of three companies about $1.75 billion to build the largest components of the controversial Site C hydroelectric dam in the province's northeast.
 
The contract agreement announced on Monday by BC Hydro will see the Peace River Hydro Partners build the earthen dam, foundation, two diversion tunnels and spillways in the province's northeast.
 
Initial estimates pegged the work at about $1.5 billion when the Crown corporation announced last month that ACCIONA Infrastructure Canada Inc., Petrowest Corporation and Samsung C&T Canada Ltd. were the "preferred proponents."
 
"We said on Nov. 25 that the cost would be 'more than $1.5 billion' and that a final value would be known once we had concluded a contract," said BC Hydro spokesman Craig Fitzsimmons in an email.
 
"With a contract in place, we now have a confirmed value."
 
The contract's duration is eight years, and at the peak of construction, about 1,500 people will be working on the main projects, BC hydro said in its news release.
 
BC Hydro said the work will create about "8,000 person-years of employment," and it is planning a series of job fairs and "business to business networking sessions" in the new year.
 
"The sessions will provide an opportunity for local, regional and aboriginal businesses and job seekers to meet the main civil works team and other project contractors."
 
Legal challenges against the dam have been launched by several groups and First Nations over concerns about flooding and the impact a new lake created by the dam will have on the Peace River area.
 
 
Opposition New Democrat Leader John Horgan criticized the announcement, noting the contract is a $250-million increase over last month's estimate and there's no guarantee how many jobs will go to British Columbians.
 
"When you're spending billions of dollars of the public's money, I believe any responsible premier of B.C. should ask how many jobs can be guaranteed for British Columbians," he said in a release.
 
Horgan has said that he wouldn't rule out cancelling the $9-billion Site C hydro-electric project if he wins the 2017 election.
 
The BC Building Trades Council said in a news release that it was shocked by the announcement, claiming as many as 1,500 jobs may go to workers from Alberta and Saskatchewan.
 
Council president Lee Loftus said hundreds of Alberta workers are already working on the dam.
 
"Only when every qualified B.C. construction worker who wants a job on this project has been hired should BC Hydro even consider looking outside the province for workers — and that's simply not the case today at all."

MORE National ARTICLES

Feds, Junior League, Tribes Fight Sex Traffickers In SD: 'Catching Awful Lot Of Them'

Feds, Junior League, Tribes Fight Sex Traffickers In SD: 'Catching Awful Lot Of Them'
It was an anonymous two-story house with an outdoor side staircase, nothing that looked ominous to Kevin Koliner when he passed by going to and from work

Feds, Junior League, Tribes Fight Sex Traffickers In SD: 'Catching Awful Lot Of Them'

The New Brunswick Government Has Formed A Committee To Handle Incoming Refugees

The New Brunswick government has formed a committee aimed at facilitating a smooth transition of the Syrian refugees to the province.

The New Brunswick Government Has Formed A Committee To Handle Incoming Refugees

Government Says Assisted-Death Panel Won't Give Advice For Legislation

Government Says Assisted-Death Panel Won't Give Advice For Legislation
A federal panel created in the wake of the Supreme Court ruling on assisted death will no longer be asked to make recommendations to the government and will now simply report on its consultations on the issue.

Government Says Assisted-Death Panel Won't Give Advice For Legislation

Speed A Factor In Crash That Killed 68-Year-Old Man On Oak Street: Vancouver Police

Speed A Factor In Crash That Killed 68-Year-Old Man On Oak Street: Vancouver Police
Vancouver police say speed is likely a factor in a crash that killed one man and sent another to hospital on Saturday.

Speed A Factor In Crash That Killed 68-Year-Old Man On Oak Street: Vancouver Police

Suspicious Package Prompts Evacuation Of Airport In Northern Alberta

Suspicious Package Prompts Evacuation Of Airport In Northern Alberta
The airport in Fort McMurray, Alta., has resumed normal operations after being evacuated Friday night because of a suspicious package.

Suspicious Package Prompts Evacuation Of Airport In Northern Alberta

Canadian Entrepreneurs Turning To Equity Crowdfunding As Provinces Loosen Rules

Canadian Entrepreneurs Turning To Equity Crowdfunding As Provinces Loosen Rules
When long-time ad agency executive Jillian Bowman needed capital to start a small business, she didn't find an angel investor — she found a crowd.

Canadian Entrepreneurs Turning To Equity Crowdfunding As Provinces Loosen Rules