BC Premier gives green light to Site C with a price tag of $16B

Darpan News Desk The Canadian Press, 26 Feb, 2021 07:10 PM
  • BC Premier gives green light to Site C with a price tag of $16B

The cost of British Columbia's Site C hydroelectric dam has grown by $6 billion, bringing the price tag of the megaproject to $16 billion and stretching the completion date to 2025.

The provincial government says the skyrocketing expenses are due to construction setbacks, geotechnical issues, COVID-19 and other cost and schedule pressures.

Premier John Horgan's announcement comes weeks after a former deputy finance minister completed his report on the status of the northeastern B.C. dam and submitted the study for cabinet consideration.

The review was ordered last July after Crown-owned BC Hydro reported concerns about risks and delays, and the province says it has accepted all 17 of Peter Milburn's recommendations, including a strengthened project assurance board.

The government also released a review by two independent experts that found changes to the foundation to address geotechnical issues on the project's right bank will ensure Site C meets safety standards.

The province says terminating Site C now would mean an immediate writedown of about $10 billion, which would result in an average 26 per cent increase in BC Hydro rates over the next 10 years if covered by ratepayers.

It says continuing with the project means the costs will be recovered through rates over the 70-year lifespan of the dam.

Horgan also announced new leadership at BC Hydro as Doug Allen — who has held top positions at the Insurance Corporation of British Columbia and TransLink — replaces Ken Peterson as chairman of the board.

The premier said in December 2017 that the NDP government would reluctantly support completion of the dam across the Peace River just west of Fort St. John, but he would never have started the project commissioned by the previous B.C. Liberal government.

MORE National ARTICLES

Canada's spy chief points finger at China

Canada's spy chief points finger at China
Vigneault says ill-intentioned countries will aim to "take advantage" of Canada as it works to get back on its economic feet once the COVID-19 pandemic subsides.

Canada's spy chief points finger at China

Anti-harassment program for B.C. port workers

Anti-harassment program for B.C. port workers
Federal Labour Minister Filomena Tassi says the BC Maritime Employers Association, International Longshore and Warehouse Union and Ending Violence Association of BC have created a program to benefit 10,000 employees in ports along the B.C. coast.

Anti-harassment program for B.C. port workers

VPD arrests shoplifter after worker threatened with baton

VPD arrests shoplifter after worker threatened with baton
The victim, 20, was working inside the Robson Street grocery store around 5 p.m. on Friday when he saw a shopper walking around without a mask.

VPD arrests shoplifter after worker threatened with baton

CERB repayment demand scrapped for some

CERB repayment demand scrapped for some
They'd been told that to qualify for the CERB they had to have earned at least $5,000 in 2019 or in the 12 months before they applied.

CERB repayment demand scrapped for some

China shouldn't host 2022 Olympics: Annamie Paul

China shouldn't host 2022 Olympics: Annamie Paul
Paul says the International Olympic Committee, along with Canada and other countries that condemn human rights violations in China, should find another venue.

China shouldn't host 2022 Olympics: Annamie Paul

Training PSWs to cost $38.5M over two years: PBO

Training PSWs to cost $38.5M over two years: PBO
Parts of the country have faced dire staffing shortages in long-term care homes, where COVID-19 outbreaks have strained resources and caused thousands of deaths.

Training PSWs to cost $38.5M over two years: PBO