Extent of damage complicates B.C. highway repairs

Darpan News Desk The Canadian Press, 18 Nov, 2021 11:53 AM
  • Extent of damage complicates B.C. highway repairs

Repairing the British Columbia highways washed out by heavy rains and flooding will be complicated by the scale of the damage, the terrain and the coming winter, building experts say.

"It's unprecedented, the size and scope and the number of sites," said Joe Wrobel, the president of JPW Road and Bridge, a road-building company based in the north Okanagan area of B.C.

Despite the extent of the damage, Wrobel, whose company is not directly involved in the repairs related to the flooding, said there are processes in place for emergency repairs, adding that the B.C. government has already drawn up lists of available contractors and equipment.

Before work can begin, geotechnical assessments will have to be conducted, Wrobel said in an interview Wednesday. Protecting lives will be the first priority, followed by protecting infrastructure and restoring safe travel, he added.

Brenda McCabe, the president of the Canadian Society for Civil Engineering and a civil engineering professor emerita at the University of Toronto, said officials must first ensure repairs can be done safely. "We have to make sure that the slopes that are left are stable, that crews can get into there in a safe way," she said in an interview Wednesday.

In areas where roads have been washed away, engineers and officials will have to decide whether to rebuild the damaged infrastructure or use new designs — decisions that she said will likely be made on a case-by-case basis.

"Our parameters for design are evolving with our better understanding of the way that the climate is changing and the impacts that that will have on weather events," she said.

Every major route between the Lower Mainland and the Interior has been cut by washouts, flooding or landslides following record-breaking rainfall across southern B.C. between Saturday and Monday.

How long repairs will take will depend on the damage, said Ahmad Rteil, a professor of structural engineering at the University of British Columbia's Okanagan campus.

In places where whole sections of road have been washed away, just assessing the damage and the stability of the soil could take more than two weeks, he said in an interview Wednesday.

"You have to reassess the whole situation there in terms of the soil, stabilize the soil, and then once you figure that one out, you start building the new road, the new bridge," Rteil said.

Winter — and freezing weather — will make repairs more difficult, he added.

"As the temperature now starts to go below zero and starts to freeze, then it becomes very challenging to work with that upper layer of soil," he said, adding that it will also make bringing heavy equipment over mountain passes more difficult.

Rteil said he worries events like this will become more common in the future. He said the wildfires and high heat in B.C. earlier this summer killed trees and added to the risk of washouts. "When the vegetation on that slope is gone, then the slope becomes unstable," he said.

Repairing roads where debris has come down from above will likely be relatively straightforward, while in other places, temporary bridges and detours may need to be put in place while major work is done, Wrobel said. Areas where roads have been flooded and the water table has risen will likely be the most complicated, he added.

Wrobel, a former chairman of the Canadian Construction Association, said that the number of repairs required will add to the complexity, and he said provincial officials will have to decide which projects are given top priority. He said road builders from across the country are ready to do the work.

Over his career of more than 40 years, he has seen projects where the damage was as bad as what individual sites in B.C. are experiencing this week. "But I've never seen them all at the same time," he said.

 

MORE National ARTICLES

House of Commons breaks for summer today

House of Commons breaks for summer today
The House of Commons is poised to break today for the summer — and possibly for an election — after giving eleventh-hour approval to what the minority Liberal government considers its priority legislation.

House of Commons breaks for summer today

PBO: Seniors benefit boost could cost $10.7B

PBO: Seniors benefit boost could cost $10.7B
April's budget estimated that the overall cost of the measures would amount to just over $12 billion over five years before accounting for tax revenues that will offset a small part of the overall spend.

PBO: Seniors benefit boost could cost $10.7B

9 Punjabis involved in Project Brisa, largest , international drug takedown in Toronto Police Service’s history

9 Punjabis involved in Project Brisa, largest , international drug takedown in Toronto Police Service’s history
The Toronto Police Service have announced the takedown of a major international drug-smuggling ring, which saw more than 1,000 kilograms of cocaine, crystal meth, and marijuana being transported between Mexico, California, and Canada using modified tractor trailers. Out of the 9 arrested, 9 people are of Punjabi descent. 

9 Punjabis involved in Project Brisa, largest , international drug takedown in Toronto Police Service’s history

Charges stayed against parents in toddler's death

Charges stayed against parents in toddler's death
Crown prosecutors have stayed charges against parents who were facing a third trial in the death of their toddler in southern Alberta. Shawn Buckley, a lawyer for David and Collet Stephan, said Tuesday he received a letter from the Crown about the decision.

Charges stayed against parents in toddler's death

Regulator lifts Trans Mountain stop-work order

Regulator lifts Trans Mountain stop-work order
Trans Mountain has now submitted a satisfactory plan to correct deficiencies in the oversight of its contractors that could pose threats to nesting birds, the Canada Energy Regulator said Tuesday in a statement.

Regulator lifts Trans Mountain stop-work order

56 COVID19 cases for Tuesday

56 COVID19 cases for Tuesday
There are 1,150 active cases of COVID-19 in BC. This is the lowest number since of active cases since September 1. There There are 111 people in hospital, up 3, and 41 in ICU, down 6.

56 COVID19 cases for Tuesday