Fast-track approval no guarantee of success for B.C. mines, researcher suggests

Darpan News Desk The Canadian Press, 06 Feb, 2025 04:59 PM
  • Fast-track approval no guarantee of success for B.C. mines, researcher suggests

The mining industry is applauding the British Columbia government's decision to fast-track permits for several projects amid the ongoing U.S. tariff threat, but research suggests economic factors have been behind long delays for many other proposals.

Simon Fraser University associate professor Rosemary Collard says research shows that regulatory fast-tracking of mining projects is no guarantee that they will all materialize.

She's the co-lead author of a recent study of 27 B.C. mining projects granted environmental assessment certificates since 1995 and projected to open by 2022, showing that most failed to open on time.

The study says that of the 20 that failed to do so, regulation was a factor in only three, with economic factors and viability instead being the most common cause. 

The B.C. government on Tuesday released a list of 18 critical mineral and energy projects, including four mines, that it said would be expedited to diversify the economy during what Premier David Eby called the "on-and-off tariff threats" from the United States.

Tim McEwan, a senior vice-president at the Mining Association of British Columbia, says in a statement that the association is pleased the government recognizes the need to speed up permitting and calls the initial list released earlier this week as "a good first step."

McEwan said there were 17 critical mineral projects currently "on the books" in B.C. and several are poised to enter permitting processes within the year.

He said it was imperative that the provincial government work to expedite approvals for other critical mineral, precious metal and steelmaking opportunities.

About half of the mines in Collard's study, which was published in December, never opened.

Collard, a geographer, said there's a big question mark around whether certainty can be delivered by doubling down on resource extraction in sectors like mining, which she calls "notoriously volatile and uncertain" with swinging commodity prices.

“One of the main surprising things about the study that we did that's relevant to this fast-tracking, I think, is that almost half of the mines that were approved through environmental assessment in B.C. since 1995 haven't been built,” Collard said.

“So, there are 12 fully approved, permitted mines in the province that are sitting waiting for the right economic conditions to be built.”

She said another main finding of the study is that mines that did become operational "have underperformed economically compared to what their forecast said in their environmental assessment."

“When you look back in the past, you see that the track record is of significant underperformance of mining projects on employment and tax revenue,” she said.

Among the handful of mines that the study says were held up by regulation is the Red Chris copper and gold mine which opened in 2015, six years after originally hoped.

Expansion of the Red Chris project in B.C.'s north is among four mining projects slated for fast-tracking this week.

Another is the Highland Valley Copper mine southwest of Kamloops. Owner Teck Resources is seeking an extension of operations beyond 2028 and into the mid-2040s.

The project has received support from First Nations Groups, including the Citxw Nlaka’pamux Assembly, the Lower Nicola Indian Band and the Kanaka Bar Indian Band, although it has been opposed by the Stk’emlupsemc te Secwepemc Nation.

“We value building strong relationships with local Indigenous and non-Indigenous communities who may be affected by our operations and are actively engaging with those communities,” Teck's director of stakeholder relations Dale Steeves said in an emailed statement.

Asked at a news briefing Thursday whether the process of fast-tracking mining and energy projects would mean compromising consultation with First Nations or environmental assessments, Energy Minister Adrian Dix did not respond directly but said the projects would still need to get "through the needed tests of standards in B.C. that are critical."

Dix announced that the province would introduce legislation this spring allowing the regulation of renewable energy projects like wind and solar to move under the single authority of the B.C. Energy Regulator. 

Among the 18 projects identified for fast-tracking this week was a series of BC Hydro clean energy ventures that mostly involve wind power.

Dix said that moving clean energy projects to a single authority will enable it to act as a “one window regulator” for the permitting process and the legislation is about “advancing growth and diversity” within the sector.

A statement from Dix's ministry said the province "is committed to working in co-operation with First Nations partners, and is engaging with Nations across the province on the approach to the proposed legislation."

MORE National ARTICLES

One dead after a single-vehicle rollover crash in Delta

One dead after a single-vehicle rollover crash in Delta
One person is dead after a single-vehicle rollover crash in Metro Vancouver. Police in Delta say it happened last night along Highway 99, near the exit for Highway 17, where a pick-up truck crashed into a barrier before rolling onto its roof.

One dead after a single-vehicle rollover crash in Delta

Ford's decision to speed up alcohol sales expansion will cost province $612M: report

Ford's decision to speed up alcohol sales expansion will cost province $612M: report
Premier Doug Ford's decision to speed up the rollout of alcohol sales in corner stores — which first sparked early election speculation last spring — will cost the province more than $600 million, Ontario's budget watchdog said Monday. That's nearly three times the amount the Progressive Conservative government said it would cost to accelerate the timeline.

Ford's decision to speed up alcohol sales expansion will cost province $612M: report

Canada stops letting cross-border hikers enter B.C. via Pacific Crest Trail

Canada stops letting cross-border hikers enter B.C. via Pacific Crest Trail
The agency has announced it will stop issuing permits for people to enter Canada on the Pacific Crest Trail, saying the move helps enhance border security and allows for compliance monitoring of those using the hiking and horse-riding trail.

Canada stops letting cross-border hikers enter B.C. via Pacific Crest Trail

B.C. firm seeks injunction stopping capital gains hike proposed by federal Liberals

B.C. firm seeks injunction stopping capital gains hike proposed by federal Liberals
A law firm acting on behalf of a B.C. company is seeking an injunction stopping the Canada Revenue Agency from enforcing a proposed capital gains tax hike that has yet to pass in Parliament. Thorsteinssons LLP says the challenge it filed in Federal Court last week on behalf of Pelco Holdings Inc. aims to stop the government agency from administering the change as if it is law.

B.C. firm seeks injunction stopping capital gains hike proposed by federal Liberals

Who's in and who's out of the Liberal leadership race

Who's in and who's out of the Liberal leadership race
The deadline for registering to vote in the leadership contest passed on Jan. 27 and candidates have until Feb. 17 to submit their full entry fee of $350,000. The winner will be named on March 9. Here's a quick look at who's in and who's out.

Who's in and who's out of the Liberal leadership race

More child care spaces in Powell River

More child care spaces in Powell River
Another 28 child care spaces have opened up for children in Powell River. A statement from B-C's Education Ministry says the spaces at Kelly Creek Community school include a dozen for children younger than three years of age, as well as 16 spots for children aged three to five.

More child care spaces in Powell River