Three contractors were rescued late Thursday after more than 60 hours trapped underground at the Red Chris gold and copper mine in northern B.C.

Here is a timeline of how the situation unfolded (all times Pacific):

July 22, 2025, 6 a.m. Three contractors working for Hy-Tech Drilling begin work for the day at the mine.

7:47 a.m. The mine experiences the first of what officials call a "localized" ground fall. The three workers go to a refuge station and Newmont says the workers radio that they are safe.

10:30 a.m. 

A second, larger, fall takes place, cutting off communication with the workers. 

July 23, 2025, 10 a.m.

B.C. Premier David Eby, speaking at a news conference in Ontario to mark the end of a premiers' meeting, announces the three workers are trapped.

11 a.m.

Newmont Corp., the operator and majority owner of the mine, says the contractors were working more than 500 metres beyond the area affected by the first fall. It says the workers have enough air, water and food for an "extended stay."

July 24, 2025, 6 a.m. 

Newmont says it has deployed drones to assess the conditions underground, and a pile of debris 20 to 30 metres long and seven to eight metres high is blocking access to the workers. It says a remote-controlled scoop is removing the debris.

2:30 p.m.

Newmont CEO Tom Palmer says the company will conduct a "thorough and independent investigation" into what happened and share details with the rest of the industry.

4:40 p.m.

Newmont holds a news conference where global safety chief Bernard Wessels says there is a "natural flow of air" to the area where the workers are trapped. He says drones have flown over the debris and have found a stable route to the refuge behind it.

6 p.m.

Hy-Tech Drilling releases the names of the workers with permission from their families. They are Kevin Coumbs, Darien Maduke and Jesse Chubaty.

10:50 p.m.

The men are safely brought to the surface after what Newmont calls a "carefully planned and meticulously executed rescue."

July 25, 2025, 7:45 a.m. 

Newmont says open-pit operations at the mine have resumed since that is unrelated to the project the men were working on. The company says the underground area where the rockfall occurred has been secured and no work will resume there "until a full investigation is completed and safety is reassessed."

Picture Courtesy: THE CANADIAN PRESS/Dave Middleton

MORE National ARTICLES

Sea otter pup livestream on now

Sea otter pup livestream on now
The Vancouver Aquarium says its sea otter pup online stream is now live. Canadians can see the progress of rescued sea otter pup Tofino as she settles into her permanent home. 

Sea otter pup livestream on now

2 million bathtubs: Calgarians urged to conserve as new water restrictions kick in

2 million bathtubs: Calgarians urged to conserve as new water restrictions kick in
A city official was conjuring images of bathtubs, swimming pools and jugs to drive home just how much water Calgarians need to save every day as they endure yet another round of rationing while a troubled pipe is repaired. 

2 million bathtubs: Calgarians urged to conserve as new water restrictions kick in

Mountain biker seriously injured

Mountain biker seriously injured
A 71-year-old mountain biker is in hospital with serious injuries after falling while riding trails in Castlegar.  R-C-M-P say the man was riding the mountain bike trails in the Merry Creek recreational area yesterday when he reportedly fell off a log bridge and became unconscious.

Mountain biker seriously injured

Highway 99 overnight closure in Delta

Highway 99 overnight closure in Delta
The provincial government is warning drivers about lane closures overnight on Highway 99 in Delta. Crews will be moving a large industrial crane across the highway for the 78th-Street-Interchange construction project.

Highway 99 overnight closure in Delta

BC Hydro begins filling reservoir as Site C dam megaproject nears completion

BC Hydro begins filling reservoir as Site C dam megaproject nears completion
BC Hydro says it has begun filling the reservoir created by the massive Site C dam project in northeastern British Columbia. The provincial electric utility says in a statement that the filling of the reservoir is one of the last steps toward starting operations for the controversial dam project, located about 14 kilometres southwest of Fort St. John, B.C.

BC Hydro begins filling reservoir as Site C dam megaproject nears completion

West Coast Express commuter trains resume Monday as rail staff ordered back to work

West Coast Express commuter trains resume Monday as rail staff ordered back to work
Metro Vancouver's transit authority says the West Coast Express commuter train service shut down last week due to the Canada-wide rail stoppage will resume operations this week. TransLink issued a statement saying services will resume their normal schedules starting Monday, although there may be some delays "due to freight traffic backlog."

West Coast Express commuter trains resume Monday as rail staff ordered back to work