Infrastructure bank won't spend fast enough: PBO

Darpan News Desk The Canadian Press, 28 Apr, 2021 08:52 PM
  • Infrastructure bank won't spend fast enough: PBO

A federal infrastructure financing agency might not meet its near-term plan to fund projects more quickly to foster economic recovery, says a new report by the parliamentary budget officer.

As it stands, the budget office estimates that the Canada Infrastructure Bank will spend $3.8 billion of the $10 billion it has been asked to invest over three years.

Budget officer Yves Giroux's report says the only way for the agency to meet the goals the government has set for it would be through a rapid increase in spending.

The agency's chief executive said a more important figure is the number of funding commitments the bank makes because it means financing is in place for a project to proceed, even if bank funding doesn't happen all at once.

"In our world, if I have signed a loan agreement with you to lend you money over the following four years as construction rolls out, that's a firm investment commitment and our goal is to rapidly increase the pace of those," Ehren Cory said in an interview.

"The moment we sign an investment commitment, the moment we finally reach financial close on a deal, the project is now happening. The private and institutional capital is now committed as well and the impact, we start to see it and the funds follow."

Cory added that short-term plans remain on track, pointing to six agreements over the last six months in projects that won't take years of development. One of those, a large irrigation project in Alberta, will see its first payment from the bank next week, he said.

The Liberals created the Canada Infrastructure Bank in 2017, seeing it as a vehicle to use public dollars to leverage private investment and finance new, revenue-producing projects like transit and water systems. Investors could earn a return, and federal dollars could be freed up for a greater number of projects.

The agency was given $20 billion to hand out in repayable loans, and a further $15 billion in financing that wouldn't be repaid.

It made an early splash, financing Montreal's electric-rail system, known by the acronym REM, alongside the province's public pension plan, but has been criticized since for moving too slowly.

Giroux's report estimates the infrastructure agency will spend less than half of the $35 billion given to it, or about $19 billion short of the 11-year funding goal.

Conservative infrastructure critic Andrew Scheer cited the findings in his call for the Liberals to scrap the infrastructure bank.

"It is a lemon of an institution," he said.

The PBO's analysis says nearly half of the projects reviewed by agency officials didn't meet marching orders from the government — for instance, not being big enough, or not having a private or institutional backer.

The other issue is the sheer size of the projects being reviewed. In straight dollars, the value of projects reviewed by the CIB was 13 times larger than the federal agency it replaced, known as PPP Canada.

"CIB has been spending much slower than planned, but funding delays are common for public-private infrastructure investment projects," Giroux said in a release.

Larger projects take more time to review and get shovels in the ground, which is why the Liberals shuffled the bank's funding deck in October and asked it to focus on smaller, short-term funding plans.

"The recognition for us was we needed to be working at both speeds, especially given the pandemic (and) the need to make sure that what we did was contributing to economic recovery," Cory said.

The PBO's report says the COVID-19 pandemic could cause some delays in spending as construction timelines get pushed back or organizations rethink spending plans. That could spill over post-pandemic into the timing of bank payments as projects see an impact in their value or revenue projections, the report says.

Cory said the pandemic hasn't had an impact on the overall outlook of potential investments.

MORE National ARTICLES

Canada joins allies for sanctions against China

Canada joins allies for sanctions against China
Foreign Affairs Minister Marc Garneau says in taking the dramatic step, Canada is joining its partners in calling on China to put an end to a systematic campaign of repression.

Canada joins allies for sanctions against China

Liberals sharpen climate change attack on Tories

Liberals sharpen climate change attack on Tories
The existing document does discuss curbing greenhouse gas emissions but does not specifically acknowledge the existence of climate change.

Liberals sharpen climate change attack on Tories

Probes found no wrongdoing by Vance: Harper aide

Probes found no wrongdoing by Vance: Harper aide
Ray Novak says those probes, largely led by senior public servants, did not turn up any evidence of wrongdoing before Vance took over as commander of the Canadian Armed Forces.

Probes found no wrongdoing by Vance: Harper aide

COVID-19 vaccine deliveries ramping up this week

COVID-19 vaccine deliveries ramping up this week
Shipments of both the AstraZeneca vaccine and the one-dose shot from Johnson & Johnson are widely expected to start arriving in Canada in April, though that timeline too has yet to be finalized.

COVID-19 vaccine deliveries ramping up this week

NDP motion calls on feds to end for-profit LTC

NDP motion calls on feds to end for-profit LTC
The NDP is tabling a motion Monday that calls on the government to transition existing for-profit homes to not-for-profit operations by 2030.

NDP motion calls on feds to end for-profit LTC

Canadian Michael Kovrig tried in Beijing

Canadian Michael Kovrig tried in Beijing
Canadian diplomats have been denied access to the trials with the explanation the hearings were being held behind closed doors because of alleged national security concerns.

Canadian Michael Kovrig tried in Beijing