Infrastructure bank won't spend fast enough: PBO

Darpan News Desk The Canadian Press, 28 Apr, 2021 08:52 PM
  • Infrastructure bank won't spend fast enough: PBO

A federal infrastructure financing agency might not meet its near-term plan to fund projects more quickly to foster economic recovery, says a new report by the parliamentary budget officer.

As it stands, the budget office estimates that the Canada Infrastructure Bank will spend $3.8 billion of the $10 billion it has been asked to invest over three years.

Budget officer Yves Giroux's report says the only way for the agency to meet the goals the government has set for it would be through a rapid increase in spending.

The agency's chief executive said a more important figure is the number of funding commitments the bank makes because it means financing is in place for a project to proceed, even if bank funding doesn't happen all at once.

"In our world, if I have signed a loan agreement with you to lend you money over the following four years as construction rolls out, that's a firm investment commitment and our goal is to rapidly increase the pace of those," Ehren Cory said in an interview.

"The moment we sign an investment commitment, the moment we finally reach financial close on a deal, the project is now happening. The private and institutional capital is now committed as well and the impact, we start to see it and the funds follow."

Cory added that short-term plans remain on track, pointing to six agreements over the last six months in projects that won't take years of development. One of those, a large irrigation project in Alberta, will see its first payment from the bank next week, he said.

The Liberals created the Canada Infrastructure Bank in 2017, seeing it as a vehicle to use public dollars to leverage private investment and finance new, revenue-producing projects like transit and water systems. Investors could earn a return, and federal dollars could be freed up for a greater number of projects.

The agency was given $20 billion to hand out in repayable loans, and a further $15 billion in financing that wouldn't be repaid.

It made an early splash, financing Montreal's electric-rail system, known by the acronym REM, alongside the province's public pension plan, but has been criticized since for moving too slowly.

Giroux's report estimates the infrastructure agency will spend less than half of the $35 billion given to it, or about $19 billion short of the 11-year funding goal.

Conservative infrastructure critic Andrew Scheer cited the findings in his call for the Liberals to scrap the infrastructure bank.

"It is a lemon of an institution," he said.

The PBO's analysis says nearly half of the projects reviewed by agency officials didn't meet marching orders from the government — for instance, not being big enough, or not having a private or institutional backer.

The other issue is the sheer size of the projects being reviewed. In straight dollars, the value of projects reviewed by the CIB was 13 times larger than the federal agency it replaced, known as PPP Canada.

"CIB has been spending much slower than planned, but funding delays are common for public-private infrastructure investment projects," Giroux said in a release.

Larger projects take more time to review and get shovels in the ground, which is why the Liberals shuffled the bank's funding deck in October and asked it to focus on smaller, short-term funding plans.

"The recognition for us was we needed to be working at both speeds, especially given the pandemic (and) the need to make sure that what we did was contributing to economic recovery," Cory said.

The PBO's report says the COVID-19 pandemic could cause some delays in spending as construction timelines get pushed back or organizations rethink spending plans. That could spill over post-pandemic into the timing of bank payments as projects see an impact in their value or revenue projections, the report says.

Cory said the pandemic hasn't had an impact on the overall outlook of potential investments.

MORE National ARTICLES

CRA locks 800K accounts after possible email 'Phishing' schemes

CRA locks 800K accounts after possible email 'Phishing' schemes
The statement comes less than a month after the tax agency said an unspecified number of user IDs and passwords may have been accessed by unauthorized individuals, "through a variety of means by sources external to the CRA."

CRA locks 800K accounts after possible email 'Phishing' schemes

Amazon workers to self isolate after COVID19 outbreak in Brampton

Amazon workers to self isolate after COVID19 outbreak in Brampton
The health unit says all shifts will be suspended as the workers self-isolate for two weeks starting tomorrow as everyone at the site might have had high-risk exposure to COVID-19.

Amazon workers to self isolate after COVID19 outbreak in Brampton

Abbotsford Police need public's help in finding missing person Chamkaur Singh Brar

Abbotsford Police need public's help in finding missing person Chamkaur Singh Brar
Brar is known to live a transient lifestyle in the Fraser Valley area, specifically between Abbotsford and Langley. Brar is a 47-year-old man, standing 5 ft 7, 132 lbs, thin build, brown eyes and black hair; there is no clothing description.

Abbotsford Police need public's help in finding missing person Chamkaur Singh Brar

Woman in wheelchair victimized

Woman in wheelchair victimized
The victim made her way to a nearby overdose prevention site, where she reported the assault to staff, who then called police. Police located the suspect and he was arrested. Charges related to the assault and the verbal comments have been recommended.

Woman in wheelchair victimized

Police watchdog investigates man's injuries

Police watchdog investigates man's injuries
RCMP say that when an officer arrived, a man allegedly pointed a firearm at her and threatened to shoot before escaping on foot to a nearby residence.    

Police watchdog investigates man's injuries

No need to lose sleep over shift to daylight saving time

No need to lose sleep over shift to daylight saving time
Don't forget to set your clocks an hour ahead, usually before bed Saturday night, to avoid being late for Sunday morning activities.    

No need to lose sleep over shift to daylight saving time