Investigators Review Why Girders Buckled In Edmonton Bridge Construction

Darpan News Desk, 17 Mar, 2015 02:51 PM
    EDMONTON — It's become Edmonton's bridge of sighs.
     
    A $32-million project to replace a key bridge in the Alberta capital could be delayed up to one year after four 40-tonne steel girders mysteriously buckled.
     
    The safety hazard posed by the twisted metal means a major commuter route underneath the 102 Avenue Bridge must remain closed until further notice, perhaps for a few weeks, in addition to part of the avenue which has been shut down since July.
     
    "Under the city’s oversight, several engineering teams are investigating the situation to determine exactly what went wrong here,” Barry Belcourt, manager of Edmonton's road design and construction branch, said Monday.
     
    "Right now nothing is going to fall down because it is all bolted in place and cranes are still holding pieces in place."
     
    No one was injured.
     
    Belcourt said investigators are reviewing the bridge design, materials used, the construction process and environmental conditions for clues.
     
    Crews started installing the girders Friday night, bolting them in place after they were put in position with cranes, but work was temporarily suspended Saturday night due to what Belcourt called extreme winds.
     
    Crews were working on the girders Monday morning when some of them buckled without warning, he said.
     
    "All of a sudden four of them bent simultaneously."
     
    How long it will take to get the project back on track will depend on what is learned from the review into why the girders buckled, Belcourt said.
     
    The city needs to determine if more cranes are needed, if the girders can be repaired on site or if crews have to take the bridge apart and start over.
     
    "In the worst-case scenario, if the steel can't be repaired, it could delay the overall project by a year."
     
    Belcourt said the delay is likely to add to the project's cost. 
     
    It will also create more traffic headaches, admitted Mayor Don Iveson.
     
    "I feel for the commuters ... who've already been dealing with the delays and that's only going to get worse ... for the foreseeable future while the road remains closed," he said.
     
    But Iveson also said he isn't worried about the safety of Edmonton's bridges in general.
     
    "Everything is very regularly inspected and bridges are the ... highest priority pieces of infrastructure we have for safety and maintenance, so I have no reason to be concerned about any other structures.
     
    "I don't know what went wrong here, but at least we caught it — whatever it is — at the construction stage.

    MORE National ARTICLES

    Vancouver Woman Mumtaz Ladha Sues Feds, B.C. After Acquittal Of Human Trafficking Charges

    Vancouver Woman Mumtaz Ladha Sues Feds, B.C. After Acquittal Of Human Trafficking Charges
    Mumtaz Ladha is suing the RCMP and B.C.'s director of civil forfeiture, saying her reputation and finances have suffered as a result of what she says was a wrongful criminal prosecution.

    Vancouver Woman Mumtaz Ladha Sues Feds, B.C. After Acquittal Of Human Trafficking Charges

    Vancouver Police Find Wanted Sex Offender Jason Bresnahan Who Failed To Return To Halfway House

    Vancouver Police Find Wanted Sex Offender Jason Bresnahan Who Failed To Return To Halfway House
    Vancouver police have located a high-risk sex offender who failed to return to his halfway house. Thirty-nine-year-old Jason Bresnahan was wanted on a Canada-wide warrant for being unlawfully at large.

    Vancouver Police Find Wanted Sex Offender Jason Bresnahan Who Failed To Return To Halfway House

    Four B.C. Patients Challenge Medical Marijuana Regime In Federal Court

    Four B.C. Patients Challenge Medical Marijuana Regime In Federal Court
    VANCOUVER — A lawyer representing four patients has told a Federal Court judge that Canada's new rules governing medical marijuana are forcing them to choose between their health and their liberty.

    Four B.C. Patients Challenge Medical Marijuana Regime In Federal Court

    Man Stable After Being Abducted, Shot Multiple Times Near Dawson Creek: RCMP

    Man Stable After Being Abducted, Shot Multiple Times Near Dawson Creek: RCMP
    DAWSON CREEK, B.C. — A man who RCMP say was abducted then shot several times at a rural property near Dawson Creek, B.C., before dragging himself to safety is in stable condition.

    Man Stable After Being Abducted, Shot Multiple Times Near Dawson Creek: RCMP

    HSBC Bank Canada Reports Q4 Profit Lower Due To Low Interest Rates

    HSBC Bank Canada Reports Q4 Profit Lower Due To Low Interest Rates
    VANCOUVER — HSBC's Canadian subsidiary says its fourth-quarter profit was lower last year than in 2013 because of less income from consumer lending, higher operating expenses and a smaller share of profit from associated companies.

    HSBC Bank Canada Reports Q4 Profit Lower Due To Low Interest Rates

    Psychiatrist recommends man who beheaded bus passenger go to Winnipeg group home

    Psychiatrist recommends man who beheaded bus passenger go to Winnipeg group home
    WINNIPEG — The psychiatrist of a man who beheaded a fellow passenger aboard a Greyhound bus is recommending Vince Li be moved from a mental hospital to a community group home in Winnipeg.

    Psychiatrist recommends man who beheaded bus passenger go to Winnipeg group home