NEB rules in favour of Kinder Morgan over Burnaby Mountain access

Dene Moore, Canadian Press, 20 Aug, 2014 11:35 AM
    The National Energy Board has sided with Kinder Morgan in a dispute with the City of Burnaby over access to Burnaby Mountain.
     
    The company can proceed with necessary studies of its preferred pipeline route through the mountain without the city's consent.
     
    In a decision released Tuesday, the National Energy Board confirmed that under federal legislation the company doesn't need permission to access the land that is home to Simon Fraser University and a vast nature preserve.
     
    "It would not be logical that the Board be required to recommend approval or denial of a project without all necessary information before it," the board said in a decision posted online. "This would not be in the public interest."
     
    Kinder Morgan would prefer to bore its pipeline through the mountain, rather than follow the current pipeline route through residential and business areas.
     
    The federal National Energy Board Act stipulates that a company may enter into the land of any person that lies on the intended route to survey or otherwise ascertain whether the land is suitable, the board found.
     
    The company does not require an order from the national regulator for temporary access, it said.
     
    "There is no requirement ... for companies to reach agreement with landowners, the Crown, or otherwise, before exercising the right to access land," the board said.
     
    It does note that the company could have made a formal request to the city sooner than it did.
     
    "Throughout its submissions ... Burnaby mischaracterizes the nature of Trans Mountains' request," the board found.
     
    The dispute has already caused a seven-month delay in the regulatory process.
     
    The board panel will not have its final report to cabinet until Jan. 25, 2016. Under the original schedule, the report was due July 2, 2015.
     
    The $5.4-billion expansion project would almost triple the current capacity, from 300,000 barrels of oil a day to almost 900,000. The City of Burnaby opposes the expansion.
     
    In documents filed to the board, the city said "the 'engagement' that Trans Mountain is requesting appears in some cases to constitute support or pre-approval by Burnaby.''
     
    In other cases it's akin to city staff helping the company to meet its obligations to the National Energy Board, it said.
     
    Project leader Carey Johannesson said the company tried for more than a year to come to some agreement with the Metro Vancouver city.
     
    Initial studies can begin within days, he said.
     
    "For us, it gives us the ability to be able to do the survey work — the engineering, environmental and archeological survey work — that we need to be able to do to satisfy the NEB," said Johannesson.
     
    "The first thing we need to do is see whether that's technically feasible."
     
    Johannesson was circumspect about the dispute.
     
    "We respect that they've got a perspective and an position," he said. "We're still going to be reaching out and trying to work with them."
     

    MORE National ARTICLES

    John Baird Supports U.S. Air Strikes In Iraq; Says Canada Not Asked For Military Help

    John Baird Supports U.S. Air Strikes In Iraq; Says Canada Not Asked For Military Help
    OTTAWA - Foreign Affairs Minister John Baird says Canada fully supports U.S. airstrikes against Islamic extremists in northern Iraq and has received no request for military assistance in the volatile region.

    John Baird Supports U.S. Air Strikes In Iraq; Says Canada Not Asked For Military Help

    Quebec Woman Who Stopped For Ducks To Have Sentencing Hearing On Sept. 19

    Quebec Woman Who Stopped For Ducks To Have Sentencing Hearing On Sept. 19
    MONTREAL - A sentencing hearing has been postponed for a Quebec woman found guilty in the deaths of two motorcyclists who colliided with her car after she stopped for ducks on a Montreal-area highway.

    Quebec Woman Who Stopped For Ducks To Have Sentencing Hearing On Sept. 19

    MH 17: Remains of 24-year-old Canadian on doomed Malaysia flight identified

    MH 17: Remains of 24-year-old Canadian on doomed Malaysia flight identified
    AMSTERDAM - A Dutch-led forensic team says it has identified the remains of 23 victims aboard Malaysia Airlines Flight 17, including a 24-year-old medical student from Ontario.

    MH 17: Remains of 24-year-old Canadian on doomed Malaysia flight identified

    50 Soldiers to run five-province relay to retrace First World War route

    50 Soldiers to run five-province relay to retrace First World War route
    EDMONTON - About 50 soldiers are set to run a relay across five provinces to retrace a route used by troops before the First World War.

    50 Soldiers to run five-province relay to retrace First World War route

    Supreme Court of Canada won't hear from Quebec construction magnate over corruption inquiry testimon

    Supreme Court of Canada won't hear from Quebec construction magnate over corruption inquiry testimon
    MONTREAL - The Supreme Court of Canada says it won't hear a former Quebec construction magnate who is trying to get out of testifying at the province's corruption inquiry.

    Supreme Court of Canada won't hear from Quebec construction magnate over corruption inquiry testimon

    Princely-paid B.C. chief says he's regained support of most First Nation members

    Princely-paid B.C. chief says he's regained support of most First Nation members
    Members of a tiny Metro Vancouver-area First Nation went public with messages of support for their chief on Thursday, a week after he was lambasted for quietly accepting an $800,000 bonus connected with successful development contracts.

    Princely-paid B.C. chief says he's regained support of most First Nation members