Wednesday, April 8, 2026
ADVT 
National

Regulator lifts Trans Mountain stop-work order

Darpan News Desk The Canadian Press, 22 Jun, 2021 03:28 PM
  • Regulator lifts Trans Mountain stop-work order

A federal regulator has lifted a stop-work order on tree cutting and grass mowing along the Trans Mountain pipeline expansion project route.

Trans Mountain has now submitted a satisfactory plan to correct deficiencies in the oversight of its contractors that could pose threats to nesting birds, the Canada Energy Regulator said Tuesday in a statement.

The regulator, which enforces safety and environmental guidelines for pipeline projects, issued a stop-work order on June 3 following investigations of tree-clearing work in the suburban Vancouver area that could have impacted nesting birds.

The regulator's website outlines four incidents along the pipeline route in the Burnaby and Coquitlam areas and near Agassiz in the Fraser Valley that date back to early April when a member of the public complained about bird nest destruction and improper buffer zones.

It also investigated tree-felling work near Agassiz that destroyed a robin's nest despite the area being marked by flags as a no-cutting zone.

The regulator says the stop-work order was issued after Trans Mountain reported to it on June 2 that one of its contractor crews cleared trees and shrubs in Burnaby without company authority.

No damaged or destroyed bird nests were reported in the June 2 incident, says the regulator.

"The order requires Trans Mountain to investigate and find the root cause for why there were two incidents related to contractor oversight issues in May," the regulator said in its order.

"Trans Mountain must also be able to prove that work is being done in a way that protects the environment, and more specifically, that workers are following Trans Mountain's own procedures and mitigation practices to protect the environment and migratory birds."

The regulator says Trans Mountain's plans now include improving field procedures to protect nesting birds and increasing direct supervision of its contractors.

Trans Mountain said in a statement on Tuesday the plan it filed to the regulator includes implementing enhanced communication, supervision and training measures before restarting pipeline clearing work.

The $12.6-billion expansion project between Burnaby, B.C., and north of Edmonton will triple existing pipeline capacity to about 890,000 barrels per day of oil products, including diluted bitumen, lighter crude and refined fuel.

 

MORE National ARTICLES

740 COVID cases for Friday

740 COVID cases for Friday
Of the active cases, 511 individuals are currently hospitalized with COVID-19, 174 of whom are in intensive care. The remaining people are recovering at home in self-isolation.

740 COVID cases for Friday

MPs split over freedom of expression in Bill C-10

MPs split over freedom of expression in Bill C-10
Harder said there's widespread fear the CRTC could undermine individual freedom of expression by regulating how internet platforms distribute content generated by ordinary users.    

MPs split over freedom of expression in Bill C-10

Vancouver's PNE at risk due to COVID-19 impacts

Vancouver's PNE at risk due to COVID-19 impacts
The exhibition's management says it would take more than 15 years to eliminate the forecasted deficit, jeopardizing the PNE's ability to organize events.

Vancouver's PNE at risk due to COVID-19 impacts

Family in India awaits man's remains from B.C.

Family in India awaits man's remains from B.C.
Bimaljeet Kaur Kaler said her cousin's body was taken to the airport for an early morning flight on April 23 to New Delhi and then on to Punjab. The  government should have given people a few days to get their affairs in order. 

Family in India awaits man's remains from B.C.

Most campers at Vancouver park now inside: city

Most campers at Vancouver park now inside: city
A statement from the city says officials have worked with BC Housing to move 184 people into indoor accommodations, including some shelter spaces and private rooms in hotels purchased by the province.

Most campers at Vancouver park now inside: city

Vancouver Coastal Health declares COVID-19 outbreak at Lions Gate Hospital

Vancouver Coastal Health declares COVID-19 outbreak at Lions Gate Hospital
The unit is closed to new admissions and transfers at this time. 

Vancouver Coastal Health declares COVID-19 outbreak at Lions Gate Hospital