Regulator lifts Trans Mountain stop-work order

Darpan News Desk The Canadian Press, 22 Jun, 2021 03:28 PM
  • Regulator lifts Trans Mountain stop-work order

A federal regulator has lifted a stop-work order on tree cutting and grass mowing along the Trans Mountain pipeline expansion project route.

Trans Mountain has now submitted a satisfactory plan to correct deficiencies in the oversight of its contractors that could pose threats to nesting birds, the Canada Energy Regulator said Tuesday in a statement.

The regulator, which enforces safety and environmental guidelines for pipeline projects, issued a stop-work order on June 3 following investigations of tree-clearing work in the suburban Vancouver area that could have impacted nesting birds.

The regulator's website outlines four incidents along the pipeline route in the Burnaby and Coquitlam areas and near Agassiz in the Fraser Valley that date back to early April when a member of the public complained about bird nest destruction and improper buffer zones.

It also investigated tree-felling work near Agassiz that destroyed a robin's nest despite the area being marked by flags as a no-cutting zone.

The regulator says the stop-work order was issued after Trans Mountain reported to it on June 2 that one of its contractor crews cleared trees and shrubs in Burnaby without company authority.

No damaged or destroyed bird nests were reported in the June 2 incident, says the regulator.

"The order requires Trans Mountain to investigate and find the root cause for why there were two incidents related to contractor oversight issues in May," the regulator said in its order.

"Trans Mountain must also be able to prove that work is being done in a way that protects the environment, and more specifically, that workers are following Trans Mountain's own procedures and mitigation practices to protect the environment and migratory birds."

The regulator says Trans Mountain's plans now include improving field procedures to protect nesting birds and increasing direct supervision of its contractors.

Trans Mountain said in a statement on Tuesday the plan it filed to the regulator includes implementing enhanced communication, supervision and training measures before restarting pipeline clearing work.

The $12.6-billion expansion project between Burnaby, B.C., and north of Edmonton will triple existing pipeline capacity to about 890,000 barrels per day of oil products, including diluted bitumen, lighter crude and refined fuel.

 

MORE National ARTICLES

Canada alone in vaccine vagueness as G7 begins

Canada alone in vaccine vagueness as G7 begins
British Prime Minister Boris Johnson is hosting the G7 leaders for a three-day summit, taking place in the southwest village of Carbis Bay — bustling with police and summit officials — where the focus is on ending the health crisis, now in its second year.

Canada alone in vaccine vagueness as G7 begins

Victoria scraps Canada Day broadcast

Victoria scraps Canada Day broadcast
City councillors in Victoria have voted unanimously to cancel a planned Canada Day broadcast in order to permit a "thoughtful reflection" of what it means to be Canadian.

Victoria scraps Canada Day broadcast

Father of alleged London attacker expresses sorrow

Father of alleged London attacker expresses sorrow
The deadly attack against a Muslim family in southwestern Ontario was "a senseless act," the father of the man accused in what police believe was a deliberate hate crime said Thursday.

Father of alleged London attacker expresses sorrow

Search for potential GG candidates finished

Search for potential GG candidates finished
Intergovernmental Affairs Minister Dominic LeBlanc says a short list of potential candidates to become Canada's next governor general will be in Prime Minister Justin Trudeau's hands in "the next few days."

Search for potential GG candidates finished

Alberta says Keystone loss 'calculated decision'

Alberta says Keystone loss 'calculated decision'
Alberta’s finance minister says the province's $1.3-billion investment of taxpayers’ money in the now-defunct Keystone XL oil pipeline project was a prudent gamble given the potential payoff in profits and jobs.

Alberta says Keystone loss 'calculated decision'

Double murder probe in B.C. leads to another body

Double murder probe in B.C. leads to another body
RCMP say in a release that officers went to the home of a woman in Naramata on Wednesday in relation to the deaths of Erick and Carlos Fryer, whose bodies were found in a remote location near the town last month.

Double murder probe in B.C. leads to another body