Saskatchewan's Boundary dam carbon capture project underperforms, report says

Darpan News Desk The Canadian Press, 02 May, 2024 01:13 PM
  • Saskatchewan's Boundary dam carbon capture project underperforms, report says

"We don't think carbon capture works as well as industry and promoters claim," said David Schissel, an analyst who wrote the report for the Institute for Energy Economics and Financial Analysis, an international non-profit agency.

"We don't think it's a good use of money to keep coal-fired power plants running."

Schissel looked at data from Sask Power's Boundary Dam project, a coal-fired power plant in southeast Saskatchewan that began capturing carbon dioxide emissions in the fall of 2014. 

Proponents originally said the plant would capture up to 90 per cent of the plant's carbon emissions. That would amount to about a million tonnes of climate-changing carbon dioxide a year — the rough equivalent of emissions from 200,000 cars.   

That goal has never been reached, said Schissel. 

When all the plant's emissions are factored in, including flue gas that is simply vented, the average capture rate is 57 per cent, he said.

A 2022 report delivered to an international conference on carbon capture backs up the findings. 

"(The project) has not sustained the design rate beyond a dedicated capacity demonstration completed in 2015," says the report from the International CCS Knowledge Centre in Regina. 

The report says capture is limited by both technical issues and the demand for carbon dioxide from the energy industry, which uses the gas to extract more oil from depleting reserves. 

The plant's capture rate has improved, although it's still short of the million-tonne mark.  

Knowledge Centre spokesman Grady Semmens said Schissel's analysis is "generally correct."

He said the plant has managed to keep nearly six million tonnes of carbon dioxide out of the atmosphere. As well, he said almost all the CO2 from the emissions that are sent through the capture facility is separated out.

"For a variety of technical and economic reasons ... the (Boundary Dam) facility has not been run at full capacity, which has impacted the overall volume of CO2 captured over the last 10 years," Semmens wrote in an email. "This does not mean the project has not been successful.

"It has provided valuable experience and lessons that we are now actively applying to the next generation of CCS projects."

SaskPower spokesman Scott McGregor said the facility continues to improve. He said the equipment was online for almost the entire first three months of 2024 — its best performance yet.

"The knowledge we’ve gained at our (carbon capture) facility has also made SaskPower a resource for development of (such) projects in a wide range of industries outside of power generation, such as cement manufacturing, oil and gas production and chemical processing," he said in an email.

But Schissel said to live up to advocates' promises, carbon capture has to work nearly perfectly all the time. 

"If you're going to try to reduce greenhouse gas emissions by capturing CO2, you've got to capture almost all the emissions and you've got to do it year in and year out for decades."

"Carbon capture hasn't done what its proponents claimed it would do."

Other carbon capture projects have yet to reach their stated goals.

Since 2015, Shell's Quest project near Edmonton has stored nine million tonnes of CO2 at a lower-than-anticipated cost. But its capture rate of 77 per cent remains below the 90 per cent originally announced.

On Wednesday, Capital Power CEO Avik Dey said the company would no longer pursue its $2.4-billion carbon capture project at its Genesee power plant.

"Fundamentally, the economics just don't work," he told analysts in a conference call. "Hopefully, the technology will improve, and we can revisit this when the economics improve.

"What it really is, is the technology improving so the costs come down. How do you actually build the kit so you have higher efficacy and capture rates while bringing down the capture costs?"

Alberta's oilsands producers have estimated the cost of the first phase of carbon capture for the industry at $16 billion. 

Schissel said carbon capture can be worthwhile in some circumstances, especially at a smaller scale. He said it remains questionable if the technology can work at the level proponents suggest and asks whether it's the most cost-effective way to reduce emissions at large operations.

"We may find out in 20 years that we didn't capture as much CO2 as we needed to and we wasted a lot of money that could have been better spent."

MORE National ARTICLES

Boy nearly drowns in Port Moody lake

Boy nearly drowns in Port Moody lake
Police in Port Moody say a 14-year-old boy is in hospital in critical condition after he nearly drowned in a Metro Vancouver lake. They say that around 4 p-m on Saturday, first responders were called to Sasamat Lake for a report of a possible drowning.

Boy nearly drowns in Port Moody lake

Man arrested for fatal stabbing in Toronto

Man arrested for fatal stabbing in Toronto
A man was arrested in Surrey, B-C, for his role in a fatal stabbing that happened in downtown Toronto in March. Toronto Police say an altercation between a 55-year-old and four other men resulted in the stabbing and while the man was transported to hospital, he died soon after.  

Man arrested for fatal stabbing in Toronto

Shooting in Oliver

Shooting in Oliver
Mounties in the southern Interior of British Columbia are asking for the public's help after the body of a 29-year-old man was found. This comes after officers were called to a vineyard on the road Wednesday, where they confirmed a man was shot and killed. Police say the suspect left the scene but was found later that day at his home, where he was then arrested.    

Shooting in Oliver

Man flees from U.S. police, crashes in B.C. after speeding across border

Man flees from U.S. police, crashes in B.C. after speeding across border
Mounties in Surrey, B.C., say a driver who fled from authorities in the U.S., sped through the Peace Arch border crossing and crashed in British Columbia is now in custody.  They say RCMP responded to a report that a suspected stolen vehicle had crossed the border from Washington State around 8 p.m. Saturday.

Man flees from U.S. police, crashes in B.C. after speeding across border

Surrey RCMP need the public's help in locating missing man Kewal Singh

Surrey RCMP need the public's help in locating missing man Kewal Singh
Kewal Singh was last seen at approximately 4:00pm on July 23, 2023 in the 8500 block of 151A Street in Surrey. He has not been seen or heard from since. It is unusual for Singh to not be in contact with his family Police and family are concerned for his health and well-being.

Surrey RCMP need the public's help in locating missing man Kewal Singh

B.C. port union to recommend settlement agreement to its members

B.C. port union to recommend settlement agreement to its members
The BC Maritime Employers Association said Friday the agreement to be presented to workers is the same one the union's caucus rejected just days ago. In a statement, the association said the deal is the proposal reached with a federal mediator and was originally agreed to by both sides on July 13.

B.C. port union to recommend settlement agreement to its members