Saskatchewan's Boundary dam carbon capture project underperforms, report says

Darpan News Desk The Canadian Press, 02 May, 2024 01:13 PM
  • Saskatchewan's Boundary dam carbon capture project underperforms, report says

"We don't think carbon capture works as well as industry and promoters claim," said David Schissel, an analyst who wrote the report for the Institute for Energy Economics and Financial Analysis, an international non-profit agency.

"We don't think it's a good use of money to keep coal-fired power plants running."

Schissel looked at data from Sask Power's Boundary Dam project, a coal-fired power plant in southeast Saskatchewan that began capturing carbon dioxide emissions in the fall of 2014. 

Proponents originally said the plant would capture up to 90 per cent of the plant's carbon emissions. That would amount to about a million tonnes of climate-changing carbon dioxide a year — the rough equivalent of emissions from 200,000 cars.   

That goal has never been reached, said Schissel. 

When all the plant's emissions are factored in, including flue gas that is simply vented, the average capture rate is 57 per cent, he said.

A 2022 report delivered to an international conference on carbon capture backs up the findings. 

"(The project) has not sustained the design rate beyond a dedicated capacity demonstration completed in 2015," says the report from the International CCS Knowledge Centre in Regina. 

The report says capture is limited by both technical issues and the demand for carbon dioxide from the energy industry, which uses the gas to extract more oil from depleting reserves. 

The plant's capture rate has improved, although it's still short of the million-tonne mark.  

Knowledge Centre spokesman Grady Semmens said Schissel's analysis is "generally correct."

He said the plant has managed to keep nearly six million tonnes of carbon dioxide out of the atmosphere. As well, he said almost all the CO2 from the emissions that are sent through the capture facility is separated out.

"For a variety of technical and economic reasons ... the (Boundary Dam) facility has not been run at full capacity, which has impacted the overall volume of CO2 captured over the last 10 years," Semmens wrote in an email. "This does not mean the project has not been successful.

"It has provided valuable experience and lessons that we are now actively applying to the next generation of CCS projects."

SaskPower spokesman Scott McGregor said the facility continues to improve. He said the equipment was online for almost the entire first three months of 2024 — its best performance yet.

"The knowledge we’ve gained at our (carbon capture) facility has also made SaskPower a resource for development of (such) projects in a wide range of industries outside of power generation, such as cement manufacturing, oil and gas production and chemical processing," he said in an email.

But Schissel said to live up to advocates' promises, carbon capture has to work nearly perfectly all the time. 

"If you're going to try to reduce greenhouse gas emissions by capturing CO2, you've got to capture almost all the emissions and you've got to do it year in and year out for decades."

"Carbon capture hasn't done what its proponents claimed it would do."

Other carbon capture projects have yet to reach their stated goals.

Since 2015, Shell's Quest project near Edmonton has stored nine million tonnes of CO2 at a lower-than-anticipated cost. But its capture rate of 77 per cent remains below the 90 per cent originally announced.

On Wednesday, Capital Power CEO Avik Dey said the company would no longer pursue its $2.4-billion carbon capture project at its Genesee power plant.

"Fundamentally, the economics just don't work," he told analysts in a conference call. "Hopefully, the technology will improve, and we can revisit this when the economics improve.

"What it really is, is the technology improving so the costs come down. How do you actually build the kit so you have higher efficacy and capture rates while bringing down the capture costs?"

Alberta's oilsands producers have estimated the cost of the first phase of carbon capture for the industry at $16 billion. 

Schissel said carbon capture can be worthwhile in some circumstances, especially at a smaller scale. He said it remains questionable if the technology can work at the level proponents suggest and asks whether it's the most cost-effective way to reduce emissions at large operations.

"We may find out in 20 years that we didn't capture as much CO2 as we needed to and we wasted a lot of money that could have been better spent."

MORE National ARTICLES

Surrey, B.C., municipal police force calls for clarity over future

Surrey, B.C., municipal police force calls for clarity over future
An open letter from the Surrey Police Service says the ongoing debate over whether the city transitions to using a municipal force or returns to the RCMP means employees are increasingly distracted by worries about their futures. The letter calls for "a clear and safe path forward for policing in Surrey."

Surrey, B.C., municipal police force calls for clarity over future

Driver strikes a pole in 152nd Street area of Surrey, road closures in effect

Driver strikes a pole in 152nd Street area of Surrey, road closures in effect
Surrey RCMP is investigating a single vehicle collision in the area of 152nd street and 62a Avenue. A vehicle was travelling north bound on 152 street when the driver lost control and struck a power pole, severely damaging it.

Driver strikes a pole in 152nd Street area of Surrey, road closures in effect

Surrey RCMP need the public's help in locating missing man Parmjit Dhillon

Surrey RCMP need the public's help in locating missing man Parmjit Dhillon
Parmjit was driving a 2007 white Honda Civic bearing British Columbia, license plate “595GMV”.  Parmjit is described as a South Asian male, 5’7”, 146 lbs, short white hair, brown eyes; wearing a black jacket.   

Surrey RCMP need the public's help in locating missing man Parmjit Dhillon

Cyclist struck in Maple Ridge

Cyclist struck in Maple Ridge
Ridge Meadows RCMP frontline members were first on scene and with support from BC Emergency Health Services (BCEHS) assessed that the cyclist suffered serious but non-life-threatening injuries. The cyclist was transported to hospital.

Cyclist struck in Maple Ridge

Johnston advises against inquiry, but aims to hold hearings on foreign interference

Johnston advises against inquiry, but aims to hold hearings on foreign interference
The former governor general said an inquiry cannot be undertaken in public because of the sensitivity of the intelligence involved, and there would be considerable overlap with the work that he has already been doing to investigate the issue of alleged foreign meddling in the last two federal elections. 

Johnston advises against inquiry, but aims to hold hearings on foreign interference

Federal government pledges $5M to Chinese Canadian Museum in Vancouver

Federal government pledges $5M to Chinese Canadian Museum in Vancouver
The museum will feature an exhibition titled "The Paper Trail to the 1923 Chinese Exclusion Act," with the July 1 opening date coinciding with the centennial of the passing of the act which effectively halted all immigration from China.

Federal government pledges $5M to Chinese Canadian Museum in Vancouver