Saskatchewan's Boundary dam carbon capture project underperforms, report says

Darpan News Desk The Canadian Press, 02 May, 2024 01:13 PM
  • Saskatchewan's Boundary dam carbon capture project underperforms, report says

"We don't think carbon capture works as well as industry and promoters claim," said David Schissel, an analyst who wrote the report for the Institute for Energy Economics and Financial Analysis, an international non-profit agency.

"We don't think it's a good use of money to keep coal-fired power plants running."

Schissel looked at data from Sask Power's Boundary Dam project, a coal-fired power plant in southeast Saskatchewan that began capturing carbon dioxide emissions in the fall of 2014. 

Proponents originally said the plant would capture up to 90 per cent of the plant's carbon emissions. That would amount to about a million tonnes of climate-changing carbon dioxide a year — the rough equivalent of emissions from 200,000 cars.   

That goal has never been reached, said Schissel. 

When all the plant's emissions are factored in, including flue gas that is simply vented, the average capture rate is 57 per cent, he said.

A 2022 report delivered to an international conference on carbon capture backs up the findings. 

"(The project) has not sustained the design rate beyond a dedicated capacity demonstration completed in 2015," says the report from the International CCS Knowledge Centre in Regina. 

The report says capture is limited by both technical issues and the demand for carbon dioxide from the energy industry, which uses the gas to extract more oil from depleting reserves. 

The plant's capture rate has improved, although it's still short of the million-tonne mark.  

Knowledge Centre spokesman Grady Semmens said Schissel's analysis is "generally correct."

He said the plant has managed to keep nearly six million tonnes of carbon dioxide out of the atmosphere. As well, he said almost all the CO2 from the emissions that are sent through the capture facility is separated out.

"For a variety of technical and economic reasons ... the (Boundary Dam) facility has not been run at full capacity, which has impacted the overall volume of CO2 captured over the last 10 years," Semmens wrote in an email. "This does not mean the project has not been successful.

"It has provided valuable experience and lessons that we are now actively applying to the next generation of CCS projects."

SaskPower spokesman Scott McGregor said the facility continues to improve. He said the equipment was online for almost the entire first three months of 2024 — its best performance yet.

"The knowledge we’ve gained at our (carbon capture) facility has also made SaskPower a resource for development of (such) projects in a wide range of industries outside of power generation, such as cement manufacturing, oil and gas production and chemical processing," he said in an email.

But Schissel said to live up to advocates' promises, carbon capture has to work nearly perfectly all the time. 

"If you're going to try to reduce greenhouse gas emissions by capturing CO2, you've got to capture almost all the emissions and you've got to do it year in and year out for decades."

"Carbon capture hasn't done what its proponents claimed it would do."

Other carbon capture projects have yet to reach their stated goals.

Since 2015, Shell's Quest project near Edmonton has stored nine million tonnes of CO2 at a lower-than-anticipated cost. But its capture rate of 77 per cent remains below the 90 per cent originally announced.

On Wednesday, Capital Power CEO Avik Dey said the company would no longer pursue its $2.4-billion carbon capture project at its Genesee power plant.

"Fundamentally, the economics just don't work," he told analysts in a conference call. "Hopefully, the technology will improve, and we can revisit this when the economics improve.

"What it really is, is the technology improving so the costs come down. How do you actually build the kit so you have higher efficacy and capture rates while bringing down the capture costs?"

Alberta's oilsands producers have estimated the cost of the first phase of carbon capture for the industry at $16 billion. 

Schissel said carbon capture can be worthwhile in some circumstances, especially at a smaller scale. He said it remains questionable if the technology can work at the level proponents suggest and asks whether it's the most cost-effective way to reduce emissions at large operations.

"We may find out in 20 years that we didn't capture as much CO2 as we needed to and we wasted a lot of money that could have been better spent."

MORE National ARTICLES

When the sun goes down, a swarm of rats emerges in downtown Vancouver

When the sun goes down, a swarm of rats emerges in downtown Vancouver
When the sun goes down, the rats of Vancouver's Burrard Skytrain Station emerge, in a scurrying blur of fur and whipping tails. Dozens of them, large and small, scamper around a park in front of the downtown station, running up and down the stairs among the legs of commuters and a wary reporter. Some appear to be feasting on birdseed scattered on the ground.

When the sun goes down, a swarm of rats emerges in downtown Vancouver

PM hints at tougher penalties for car thieves as feds seek ideas at national summit

PM hints at tougher penalties for car thieves as feds seek ideas at national summit
The Liberal government will consider tougher criminal penalties for people who steal vehicles, Prime Minister Justin Trudeau said Thursday as he kicked off a daylong summit aimed at confronting the scourge of auto theft.

PM hints at tougher penalties for car thieves as feds seek ideas at national summit

Former RCMP intelligence official sentenced to 14 years for breaking secrets law

Former RCMP intelligence official sentenced to 14 years for breaking secrets law
A former RCMP intelligence official has been sentenced to 14 years in prison for breaching Canada's secrets law in what the judge called a case without precedent. Ontario Superior Court Justice Robert Maranger handed the sentence Wednesday to Cameron Jay Ortis, who was found guilty in November of violating the Security of Information Act.  

Former RCMP intelligence official sentenced to 14 years for breaking secrets law

Sex offender missing from halfway house

Sex offender missing from halfway house
Vancouver police say  a man considered a high risk and violent sex offender is missing after he failed to check in to his halfway house yesterday. They say 36-year-old Johnny Walkus is wanted Canada-wide.

Sex offender missing from halfway house

Liberals' proposed AI law too vague

Liberals' proposed AI law too vague
Representatives from Big Tech companies say a Liberal government bill that would begin regulating some artificial intelligence systems is too vague.  Amazon and Microsoft executives told MPs at a House of Commons industry committee meeting Wednesday that Bill C-27 doesn't differentiate enough between high- and low-risk AI systems.

Liberals' proposed AI law too vague

Liberals devote $28M to beef up fight against stolen car exports on eve of summit

Liberals devote $28M to beef up fight against stolen car exports on eve of summit
The federal government is earmarking $28 million in new money to help fight the export of stolen vehicles. The Liberal government said Wednesday the money will give the Canada Border Services Agency more capacity to detect and search containers with pilfered autos.

Liberals devote $28M to beef up fight against stolen car exports on eve of summit