Scientist Calls $12.8B Rebuild Of Ontario Nuke Plant Costly Make-work Project

Darpan News Desk The Canadian Press, 27 Jan, 2016 12:47 PM
    TORONTO — The proposed $12.8-billion refurbishment of four nuclear reactors at the Darlington generating station is an ill-advised make-work project that will end up soaking taxpayers, a retired nuclear scientist says.
     
    In a letter to Ontario's energy minister, obtained by The Canadian Press, Frank Greening warns of the formidable technical hazards he says will undermine rosy projections for the project.
     
    "I am quite mystified that you would consider the refurbishment of Darlington to be some sort of solution to Ontario's economic woes, when in fact the premature failures of (nuclear reactors) are a major cause of Ontario's economic problems," writes Greening, a frequent critic of the industry.
     
    "Spending billions of dollars trying to patch up Darlington's four dilapidated reactors will simply continue the bleeding."
     
    Earlier this month, the province's publicly owned generating giant, Ontario Power Generation, announced plans to start refurbishing Darlington — situated east of Toronto on Lake Ontario — this fall. The project aims to extend the life of the CANDU reactors, scheduled for permanent shutdown in 2020, by 30 years.
     
    The government projects the rebuild will create up to 11,800 jobs a year at the height of construction and generate $14.9 billion in economic and spinoff benefits.
     
    Greening argues the units are in need of rebuilding prematurely because their pressure tubes and feeder pipes will soon fail fitness tests. He also warns the reactors' massive steam generators, which are not part of the proposed project, have had a less than stellar track record and will more than likely need replacement.
     
    "Replacing these steam generators is fraught with very serious problems, both technical and economic, that could prevent the continued operation of Darlington beyond 2030," says Greening, a senior scientist with OPG until he retired in 2000.
     
    "The decision to proceed with the refurbishment of Darlington could prove to be a disastrous mistake if it is discovered that steam generator replacement is in fact needed in the next 10 to 15 years."
     
    Environmental groups also argue such projects always run massively over budget and have cost taxpayers untold billions in the past and refurbishment is simply not worth the potential radiation risk to public safety.
     
    The Ontario cabinet has so far given the green light to refurbish one of Darlington's reactors. OPG would need separate approvals for each of the other three units. The government said that process would allow it to call off the project at each stage if things are going awry.
     
    Energy Minister Bob Chiarelli, who argues the province needs Darlington's power, referred questions about Greening's criticism to Ontario Power Generation.
     
    OPG spokesman Bill McKinlay said Wednesday the federal nuclear regulator noted Greening's concerns before giving the project its stamp of approval.
     
    "We've been preparing since 2009 and we're ready to deliver the job safely, on time and on budget,'' McKinlay said. "We expect it will provide 30-plus years of clean, reliable base-load power at a cost lower than other alternatives."
     
    Greening, however, argues the project is an attempt to put a "dying industry on life support" at the taxpayer's expense.
     
    "The inconvenient truth is that, after less than 25 years of operation, Darlington NGS is a mess," he says.
     
    "Its feeder pipes are falling apart and its pressure tubes are ready to crack. Darlington is another failed CANDU station desperately in need of a fix."
     
    The performance of four other refurbished CANDUs in Ontario, he argues, has fallen well short of what a new reactor typically delivers.
     
    "This reveals the uncomfortable truth: A refurbished CANDU reactor is no substitute for a new one."

    MORE National ARTICLES

    Shooting, Wild Chase Through Surrey Ends With Crash, Three Arrests In Delta

    Shooting, Wild Chase Through Surrey Ends With Crash, Three Arrests In Delta
    Mounties say a gun was seized from the car, the trio is known to them and charges are expected, but an investigation continues

    Shooting, Wild Chase Through Surrey Ends With Crash, Three Arrests In Delta

    Advisers Urge Justin Trudeau To Be Innovative In Era Of Dramatic Change

    OTTAWA — Federal advisers have told Justin Trudeau he must adopt more innovative approaches to successfully govern in the modern era.

    Advisers Urge Justin Trudeau To Be Innovative In Era Of Dramatic Change

    The Tie That Binds: Mother Of Missing Manitoba Man Starts Awareness Campaign

    The Tie That Binds: Mother Of Missing Manitoba Man Starts Awareness Campaign
    Colten Pratt, who is 26, has been missing since November 2014 and Lydia Daniels has spent the last year trying to find him.

    The Tie That Binds: Mother Of Missing Manitoba Man Starts Awareness Campaign

    Ice Jams Prompt Flooding Concerns For Homeowners Near Smithers, B.C.

    Ice Jams Prompt Flooding Concerns For Homeowners Near Smithers, B.C.
    Regional District of Bulkley-Nechako chairman Bill Miller says ice has backed up along the Bulkley River, causing water to rise and seep into basements and crawl spaces of some nearby homes.

    Ice Jams Prompt Flooding Concerns For Homeowners Near Smithers, B.C.

    B.C. Seniors Urged To Learn If They Qualify For Medical Services Plan Subsidy

    B.C. Seniors Urged To Learn If They Qualify For Medical Services Plan Subsidy
    Isobel Mackenzie says seniors could be eligible for full or partial payments but most are unaware of the available help.

    B.C. Seniors Urged To Learn If They Qualify For Medical Services Plan Subsidy

    Slumping Loonie Could Add $3.5 Billion To Cost Of Windsor-Detroit Bridge, Trudeau Told

    Slumping Loonie Could Add $3.5 Billion To Cost Of Windsor-Detroit Bridge, Trudeau Told
    OTTAWA — The federal Liberal government will need to find $3.5 billion more to pay for a new bridge at the bustling border crossing between Canada and the United States.

    Slumping Loonie Could Add $3.5 Billion To Cost Of Windsor-Detroit Bridge, Trudeau Told