'Several critical safety failures' behind B.C. workers death, WorkSafeBC says

Darpan News Desk The Canadian Press, 12 Mar, 2025 03:58 PM
  • 'Several critical safety failures' behind B.C. workers death, WorkSafeBC says

WorkSafeBC says a worker killed in Vancouver last year when a mould used for concrete fell 26 storeys should never have been able to stand where she was.

The report released by the province's worker safety agency says "several critical safety failures" are to blame for the death of the woman at the Oakridge Park development site in February of 2024. 

It says CCTV footage revealed "no effective controls in place" and safety protocols not followed, with workers often under suspended loads and entering areas that should have been off-limit "ground control zones." 

The agency says there was a lack of clarity about which contractor was responsible for the control zones and that ambiguity "contributed significantly," as no single employer took responsibility.

The primary contractor, EllisDon, did not immediately respond to a request for comment, although a lawyer for another contractor, Newway, says in a statement that it has already implemented changes to how it carries out inspections and operates control zones.

The report says on the day of the death, several workers were pushing the mould as it was rigged to a crane when it "suddenly accelerated out of the side of the building" falling on the female worker. 

The report says EllisDon, as the prime contractor, did not ensure that the hazards were identified or that the safety measures for critical lifts and overhead work were co-ordinated, exposing workers to serious risks. 

"EllisDon failed to ensure that there was adequate planning, co-ordination, hazard identification, risk assessment, training, and supervision for the critical lift and overhead work on the day of the incident," the report says.

It says the company also failed to review policies and procedures, including those for spotters and ground control zones during the hoisting and repositioning of the mould, also called a flytable, "leading to the development of unsafe conditions."

"The inadequate fulfilment of prime contractor responsibilities was a key contributing factor in the incident," the report says.

 

MORE National ARTICLES

B.C. investigates 'significant' opioid diversion, including international trafficking

B.C. investigates 'significant' opioid diversion, including international trafficking
A "significant portion" of opioids prescribed by doctors and pharmacists in British Columbia are being diverted, and prescribed alternatives are being trafficked provincially, nationally and internationally, a Ministry of Health investigative unit says.

B.C. investigates 'significant' opioid diversion, including international trafficking

MPs reject Trump's idea of clearing out Gaza as Israeli minister points to Canada

MPs reject Trump's idea of clearing out Gaza as Israeli minister points to Canada
Canadian politicians are pushing back on the idea of clearing Palestinians out of the Gaza Strip as an Israeli minister suggests some of them could be sent to Canada. The previous day, U.S. President Donald Trump stunned leaders across the Middle East and beyond when he suggested that the territory be cleared out and made into a U.S.-owned resort destination.

MPs reject Trump's idea of clearing out Gaza as Israeli minister points to Canada

Ottawa, provinces should discuss possibility of west-east oil pipeline: Wilkinson

Ottawa, provinces should discuss possibility of west-east oil pipeline: Wilkinson
Federal Energy Minister Jonathan Wilkinson says Ottawa and the provinces should discuss the possibility of an oil pipeline to Eastern Canada to improve energy security and diversify trade. Wilkinson said Thursday that United States President Donald Trump's tariff threats have exposed "vulnerabilities" in the Canadian economy, including in the energy sector. 

Ottawa, provinces should discuss possibility of west-east oil pipeline: Wilkinson

Federal government commits more than $160 million to Jasper recovery

Federal government commits more than $160 million to Jasper recovery
The fire-ravaged town of Jasper, Alta., has received two pieces of critical funding from the federal and provincial governments as it attempts to stabilize in the wake of last summer's devastating wildfire. The federal government announced on Thursday it's committing $162 million to the recovery in Jasper, Alta. — a portion of which is being dedicated to interim and long-term housing.

Federal government commits more than $160 million to Jasper recovery

Fast-track approval no guarantee of success for B.C. mines, researcher suggests

Fast-track approval no guarantee of success for B.C. mines, researcher suggests
The mining industry is applauding the British Columbia government's decision to fast-track permits for several projects amid the ongoing U.S. tariff threat, but research suggests economic factors have been behind long delays for many other proposals. Simon Fraser University associate professor Rosemary Collard says research shows that regulatory fast-tracking of mining projects is no guarantee that they will all materialize.

Fast-track approval no guarantee of success for B.C. mines, researcher suggests

Former human rights chief commissioner sues for defamation

Former human rights chief commissioner sues for defamation
At a press conference Thursday, Birju Dattani spoke about lawsuits he has filed against Conservative deputy leader Melissa Lantsman, media personality Ezra Levant and the Jewish advocacy group Centre for Israel and Jewish Affairs over statements made about him on social media last year. One of the defendants has called Dattani's claims "baseless."

Former human rights chief commissioner sues for defamation