    HALIFAX — The claimants were the bride and groom.
     
     
    The defendant was the rental company, set to supply three tents, tables, chairs, linens, dishes, cutlery, a dance floor and other items to a rural property an hour outside of Halifax.  
     
     
    The contract was for about $10,000.
     
     
    "This is a case of wedding plans gone seriously wrong," says Nova Scotia small claims court adjudicator Michael O'Hara.
     
     
    In a written decision released Tuesday, he ordered MacFarlands Limited to pay the newlyweds $5,419.
     
     
    Although the 17-page decision reads like a suspense thriller for anyone who has ever planned their own wedding, the adjudicator said that "at its core" it's a contract case.
     
     
    O'Hara said the contract called for delivery and set-up of the rental items to take place on a Wednesday last September, yet it was not completed until Friday evening.
     
     
    "That is not what the contract called for," he said.
     
     
    "It seems to me that however one views this, MacFarlands has breached the terms of its contract."
     
     
    Ryan and Kristen Johnstone began planning their nuptials nearly a year in advance, with the bride seeking quotes from MacFarlands for a number of wedding accoutrements to accommodate roughly 200 guests.
     
     
    Delivery of the rental items was initially set for the day before the wedding on Saturday, Sept. 9, 2017.
     
     
    A month before getting hitched, the bride called and requested to change the delivery date to Thursday — two days before the wedding.
     
     
    The delivery date was changed again to Wednesday after a storm was forecasted — perhaps a foreshadowing of things to come.
     
     
    While MacFarlands delivered and set up some items on the Wednesday, the company did not complete setting up until late Friday — leaving the couple's 20 or so friends and family who had volunteered to help set up scrambling late into the night to finish up.
     
     
    The bride and groom alleged that the company "was late in delivering and completing the setup of the tents and this caused the timing of the wedding preparations to be significantly delayed the day before the wedding, virtual cancellation of the rehearsal dinner, and many of the guests, close friends, and relations of the couple to have to stay up late and into the morning of Saturday," the decision said.
     
     
    "This significantly affected the enjoyment of the wedding and the post-wedding reception which if not ruined, was significantly altered in a negative fashion."
     
     
    In the end, the groom indicated his bride-to-be got two hours of sleep the night before their marriage and "there were a lot of tired and stressed out people," the decision said.
     
     
    The groom's parents organized a post-rehearsal lobster party for Friday night, but the father said guests were too busy setting up to attend.
     
     
    "We read the riot act and made them come up and eat," he told the court.
     
     
    A witness for the claimants — the bride's best friend and co-maid of honour — told the court that "it was a mess."
     
     
    She described the rehearsal dinner as a "go get it and high-tail it back" type of affair, as wedding guests worked well into the night.
     
     
    Another witness — the groom's brother-in-law, who referred to what he did as "muscle" more than anything else — said the dance floor was not serviceable and required a sub-floor to be constructed.
     
     
    However, Michael Thompson, general manager for MacFarlands, said the issue with the dance floor was due to the claimants choosing a poor location with a slope.
     
     
    He indicated that most of the three tents were set up on Wednesday, with only some walls left to go up, and the tables delivered on Thursday.
     
     
    However, it was unclear who would set up the tables, or whether the tables could be set up before the tent walls were in place.
     
     
    The bride and groom said their volunteers were unable to set up the tables because the side walls to the main tent were not in place — something MacFarlands disputed.
     
     
    The company suggested the wedding party should have started setting up the venue much earlier and that they misjudged how much work was involved.
     
     
    "The picture that is painted is not one of the volunteers blithely standing around with their hands in their pockets waiting for something to do," O'Hara said in the decision.
     
     
    "I do not think that is a reasonable inference to make in these circumstances."
     
     
    However, the adjudicator also dismissed one of the groom's main complaints, which was the lack of a project co-ordinator for on site issues.
     
     
    O'Hara pointed out that MacFarlands is a rental company — not a wedding planner.
     
     
    Still, he added that the terms and conditions of MacFarlands' contract "are neither comprehensive nor accurate."
     
     
    "A clearly itemized list of who is responsible for what would go a long way to ensuring what happened here does not happen again."

    MORE National ARTICLES

    New Allegations Surface Against Nova Scotia-Based Buddhist Leader Sakyong Mipham Rinpoche

    New Allegations Surface Against Nova Scotia-Based Buddhist Leader Sakyong Mipham Rinpoche
    HALIFAX — The spiritual leader of one of the largest Buddhist organizations in the western world is facing fresh sexual misconduct allegations as a Halifax law firm prepares to launch an independent investigation into claims against him.

    New Allegations Surface Against Nova Scotia-Based Buddhist Leader Sakyong Mipham Rinpoche

    Toronto Police Seek First-Degree Murder Suspect In Downtown Shooting Of Two Men

    Toronto police have issued a warrant for the arrest of a 22-year-old man in the fatal shooting of two men associated with the local rap scene.

    Toronto Police Seek First-Degree Murder Suspect In Downtown Shooting Of Two Men

    Surge In Demand For Paper, Glass Straws A Boon For Plastic Alternatives Firms

    Surge In Demand For Paper, Glass Straws A Boon For Plastic Alternatives Firms
    Phillip Jacobsen started selling compostable cutlery in 2011 and about six months later expanded Greenmunch's product line to include paper straws.

    Surge In Demand For Paper, Glass Straws A Boon For Plastic Alternatives Firms

    B.C. Signs Agreements With Licensed Producers To Supply Legal Marijuana

    B.C. Signs Agreements With Licensed Producers To Supply Legal Marijuana
    British Columbia has announced the companies that will supply recreational marijuana after legalization this fall, boasting its stash will feature an "exclusive and competitive" assortment of products.

    B.C. Signs Agreements With Licensed Producers To Supply Legal Marijuana

    B.C. To Fast Track Applications For Intercity Bus Service After Greyhound Exit

    B.C. To Fast Track Applications For Intercity Bus Service After Greyhound Exit
    British Columbia says it will fast track applications from operators who want to serve parts of the province that will be left without intercity bus service after Greyhound's exit from Western Canada at the end of October.

    B.C. To Fast Track Applications For Intercity Bus Service After Greyhound Exit

    Indigenous Pipeline Protesters Take Over B.C. Park, Displace Campers, Erect 'Tiny Homes'

    Indigenous Pipeline Protesters Take Over B.C. Park, Displace Campers, Erect 'Tiny Homes'
    An Indigenous group calling itself the Tiny House Warriors has moved into the North Thompson River Provincial Park near Clearwater, B.C., in an effort to block the Trans Mountain pipeline expansion.

    Indigenous Pipeline Protesters Take Over B.C. Park, Displace Campers, Erect 'Tiny Homes'