Small Claims Court Rules In Case Of 'Wedding Plans Gone Seriously Wrong'

Darpan News Desk The Canadian Press, 02 Oct, 2018 07:33 PM
    HALIFAX — The claimants were the bride and groom.
     
     
    The defendant was the rental company, set to supply three tents, tables, chairs, linens, dishes, cutlery, a dance floor and other items to a rural property an hour outside of Halifax.  
     
     
    The contract was for about $10,000.
     
     
    "This is a case of wedding plans gone seriously wrong," says Nova Scotia small claims court adjudicator Michael O'Hara.
     
     
    In a written decision released Tuesday, he ordered MacFarlands Limited to pay the newlyweds $5,419.
     
     
    Although the 17-page decision reads like a suspense thriller for anyone who has ever planned their own wedding, the adjudicator said that "at its core" it's a contract case.
     
     
    O'Hara said the contract called for delivery and set-up of the rental items to take place on a Wednesday last September, yet it was not completed until Friday evening.
     
     
    "That is not what the contract called for," he said.
     
     
    "It seems to me that however one views this, MacFarlands has breached the terms of its contract."
     
     
    Ryan and Kristen Johnstone began planning their nuptials nearly a year in advance, with the bride seeking quotes from MacFarlands for a number of wedding accoutrements to accommodate roughly 200 guests.
     
     
    Delivery of the rental items was initially set for the day before the wedding on Saturday, Sept. 9, 2017.
     
     
    A month before getting hitched, the bride called and requested to change the delivery date to Thursday — two days before the wedding.
     
     
    The delivery date was changed again to Wednesday after a storm was forecasted — perhaps a foreshadowing of things to come.
     
     
    While MacFarlands delivered and set up some items on the Wednesday, the company did not complete setting up until late Friday — leaving the couple's 20 or so friends and family who had volunteered to help set up scrambling late into the night to finish up.
     
     
    The bride and groom alleged that the company "was late in delivering and completing the setup of the tents and this caused the timing of the wedding preparations to be significantly delayed the day before the wedding, virtual cancellation of the rehearsal dinner, and many of the guests, close friends, and relations of the couple to have to stay up late and into the morning of Saturday," the decision said.
     
     
    "This significantly affected the enjoyment of the wedding and the post-wedding reception which if not ruined, was significantly altered in a negative fashion."
     
     
    In the end, the groom indicated his bride-to-be got two hours of sleep the night before their marriage and "there were a lot of tired and stressed out people," the decision said.
     
     
    The groom's parents organized a post-rehearsal lobster party for Friday night, but the father said guests were too busy setting up to attend.
     
     
    "We read the riot act and made them come up and eat," he told the court.
     
     
    A witness for the claimants — the bride's best friend and co-maid of honour — told the court that "it was a mess."
     
     
    She described the rehearsal dinner as a "go get it and high-tail it back" type of affair, as wedding guests worked well into the night.
     
     
    Another witness — the groom's brother-in-law, who referred to what he did as "muscle" more than anything else — said the dance floor was not serviceable and required a sub-floor to be constructed.
     
     
    However, Michael Thompson, general manager for MacFarlands, said the issue with the dance floor was due to the claimants choosing a poor location with a slope.
     
     
    He indicated that most of the three tents were set up on Wednesday, with only some walls left to go up, and the tables delivered on Thursday.
     
     
    However, it was unclear who would set up the tables, or whether the tables could be set up before the tent walls were in place.
     
     
    The bride and groom said their volunteers were unable to set up the tables because the side walls to the main tent were not in place — something MacFarlands disputed.
     
     
    The company suggested the wedding party should have started setting up the venue much earlier and that they misjudged how much work was involved.
     
     
    "The picture that is painted is not one of the volunteers blithely standing around with their hands in their pockets waiting for something to do," O'Hara said in the decision.
     
     
    "I do not think that is a reasonable inference to make in these circumstances."
     
     
    However, the adjudicator also dismissed one of the groom's main complaints, which was the lack of a project co-ordinator for on site issues.
     
     
    O'Hara pointed out that MacFarlands is a rental company — not a wedding planner.
     
     
    Still, he added that the terms and conditions of MacFarlands' contract "are neither comprehensive nor accurate."
     
     
    "A clearly itemized list of who is responsible for what would go a long way to ensuring what happened here does not happen again."

    MORE National ARTICLES

    City Of Burnaby Going To Court To Help Remove Pipeline Protest Camp

    BURNABY, B.C. — The City of Burnaby is going to B.C. Supreme Court asking for help in enforcing an eviction order on a pipeline protest camp that has grown to include two-storey structures, a shower and a sacred fire.

    City Of Burnaby Going To Court To Help Remove Pipeline Protest Camp

    WATCH: Vancouver-Born Comedian, Actor Seth Rogen Is The New Voice Of Vancouver Transit

    WATCH: Vancouver-Born Comedian, Actor Seth Rogen Is The New Voice Of Vancouver Transit
    Vancouver commuters will soon hear the voice of a familiar funnyman on public transit telling them to keep their bags and dirty shoes off the seats.

    WATCH: Vancouver-Born Comedian, Actor Seth Rogen Is The New Voice Of Vancouver Transit

    Coming Out Of Its Shell: 11-Kg Tortoise Found Roaming The Streets Of Edmonton

    Coming Out Of Its Shell: 11-Kg Tortoise Found Roaming The Streets Of Edmonton
    There's no sign of a hare but an 11-kilogram tortoise has been found roaming free in Edmonton.

    Coming Out Of Its Shell: 11-Kg Tortoise Found Roaming The Streets Of Edmonton

    Lawyer For Hedley Frontman Jacob Hoggard To Address Sex Charges In Court Today

    Lawyer For Hedley Frontman Jacob Hoggard To Address Sex Charges In Court Today
    A lawyer for the frontman of the band Hedley is scheduled to appear in a Toronto courtroom today, as the rock star faces three sex-related charges.

    Lawyer For Hedley Frontman Jacob Hoggard To Address Sex Charges In Court Today

    Man Arrested After Alleged Sexual Assaults At Victoria Care Facility

    Man Arrested After Alleged Sexual Assaults At Victoria Care Facility
    A 39-year-old man is facing several charges after an investigation into alleged sexual assaults at a residential care facility in Victoria.

    Man Arrested After Alleged Sexual Assaults At Victoria Care Facility

    Delta Police Recover Man's Body From Fraser River

    Delta Police Recover Man's Body From Fraser River
    Delta Police have recovered the body of a male from the Fraser River this morning, July 26, at the 8200 block of River Road, near Bridgeview Marine.

    Delta Police Recover Man's Body From Fraser River