Stalling Site C More Costly Than Cancelling Or Proceeding: Utilities Commission

The Canadian Press, 01 Nov, 2017 12:02 PM
  • Stalling Site C More Costly Than Cancelling Or Proceeding: Utilities Commission
VICTORIA — The British Columbia Utilities Commission has completed its review of the controversial Site C dam, concluding that delaying the megaproject would be the most risky and costly option.
 
The commission doesn't make a recommendation on whether the province should proceed with or cancel the dam, but it says terminating the project would cost $1.8 billion while completing it could cost more than $10 billion.
 
The province's fledgling NDP government asked the commission to examine the economic viability of the megaproject, which was a signature initiative of former Liberal premier Christy Clark.
 
The government has the final say on the fate of the project and Energy Minister Michelle Mungall is expected to respond to the report today.
 
The report says the project is not within the proposed budget of $8.3 billion and could end up costing 20 to 50 per cent more, while other energy sources including wind could provide similar benefits with lower costs.
 
The dam is two years into construction on the Peace River in northeast B.C. and work has continued while the review is underway.

MORE National ARTICLES

Witness Describes Man In Alleged Getaway Vehicle After B.C. Gang Leader Jonathan Bacon Murdered

Witness Describes Man In Alleged Getaway Vehicle After B.C. Gang Leader Jonathan Bacon Murdered
KELOWNA, B.C. — The driver of an SUV speeding from the scene of a gang murder tried to shield his face from witnesses but a woman who was leaving a coffee shop has described the man in B.C. Supreme Court.

Witness Describes Man In Alleged Getaway Vehicle After B.C. Gang Leader Jonathan Bacon Murdered

Premier Warns NDP, Greens That Delaying Site C Dam In B.C. Could Cost $600M

Premier Warns NDP, Greens That Delaying Site C Dam In B.C. Could Cost $600M
VANCOUVER — British Columbia's political leaders exchanged duelling letters over the future of the Site C dam project on Tuesday, with Premier Christy Clark arguing that delays will cost hundreds of millions of dollars.

Premier Warns NDP, Greens That Delaying Site C Dam In B.C. Could Cost $600M

Flood Risk Downgraded On Some B.C. Rivers, But Kelowna Residents Still Watchful

Flood Risk Downgraded On Some B.C. Rivers, But Kelowna Residents Still Watchful
VANCOUVER — A flood watch is in effect for the South Thompson and Shuswap rivers in B.C.'s southern Interior, but the River Forecast Centre has downgraded the risk on the North Thompson River and on the Thompson River through Kamloops.

Flood Risk Downgraded On Some B.C. Rivers, But Kelowna Residents Still Watchful

New Brunswick Boxer David Whittom Remains In Induced Coma After Post-Bout Brain Hemorrhage

New Brunswick Boxer David Whittom Remains In Induced Coma After Post-Bout Brain Hemorrhage
Thirty-eight-year-old David Whittom is listed in stable condition at Saint John Regional Hospital.

New Brunswick Boxer David Whittom Remains In Induced Coma After Post-Bout Brain Hemorrhage

Autopsy Report Shows Canadian Killed Fighting ISIL Died From Head Injury: Mother

Autopsy Report Shows Canadian Killed Fighting ISIL Died From Head Injury: Mother
Tassone was killed on Dec. 21 in the city of Raqqa while fighting militants associated with the Islamic State of Iraq and the Levant, known as ISIS or ISIL.

Autopsy Report Shows Canadian Killed Fighting ISIL Died From Head Injury: Mother

Parking Enforcement Officer 'Powerless' As 3 Toronto Cops Had Sex With Her

The woman, who cannot be identified due to a standard publication ban, is testifying at the trial of Joshua Cabero, Leslie Nyznik, and Sameer Kara, who have all pleaded not guilty to sexual assault in connection with the alleged incident.

Parking Enforcement Officer 'Powerless' As 3 Toronto Cops Had Sex With Her