Study questions benefits of Kinder Morgan's proposed Trans Mountain expansion

Darpan News Desk The Canadian Press, 10 Nov, 2014 10:37 AM

    CALGARY — A new report says Kinder Morgan is overplaying the economic benefits, and downplaying the costs of its proposed Trans Mountain pipeline expansion.

    Simon Fraser University's Centre for Public Policy Research teamed with The Goodman Group Ltd., a California-based consulting firm, to examine the estimated impacts of the project.

    The authors dispute Kinder Morgan's claim that 36,000 person-years of employment would be created in British Columbia during the project's development.

    More like 12,000, tops, they say — which is less than 0.2 per cent of total provincial employment.

    "We correctly anticipated that the benefits from the pipeline would be small in the context of the overall B.C. economy and mostly short-term," said Ian Goodman, president of the Goodman Group.

    "But we were very surprised that the company has exaggerated the short-term jobs associated with building the pipeline by a factor of three."

    The long-term jobs are also overstated, according to the report.

    Kinder Morgan has projected 50 direct full-time jobs once the pipeline is up and running, with 2,000 resulting from the project's spinoff benefits. The report pegs the spinoff jobs at closer to 800.

    The report's authors say B.C. government coffers will get a "tiny" benefit from the Trans Mountain expansion, with Alberta and oilsands producers the main beneficiaries. Property tax benefits for B.C. communities along the route would average less than one per cent of current total municipal revenues.

    On the cost side, the report also takes issue with Kinder Morgan's numbers. The company's most expensive spill scenario puts the cost at $100 million to $300 million. Goodman and Simon Fraser figure it would be in the "multibillion-dollar range" if oil spills in a populated area.

    "KM has vastly underestimated the worst-case costs for a catastrophic pipeline rupture. Contrary to KM's findings, damage and cleanup costs for major accidents are highly correlated with population density," said Brigid Rowan, Senior Energy Economist at The Goodman Group, Ltd and co-author of the report.

    "So a worst-case scenario for TMX would involve a major accident in a more densely populated area (such as Metro Vancouver) damaging and disrupting key infrastructure, and possibly resulting in a spill to water and losses of human life."

    Doug McArthur, director of the graduate school of public policy at SFU, said the project is "highly questionable from a public policy point of view."

    "These findings, along with the increasing evidence from interveners in the NEB pipeline hearings that Kinder Morgan is not providing accurate and complete data and information about the pipeline, make it difficult to see how the NEB can approve this pipeline while fulfilling its obligation to uphold the public interest."

    The Trans Mountain pipeline currently ships 300,000 barrels of petroleum products per day from the Edmonton area to the West Coast. The $5.4-billion expansion would nearly triple its capacity to 890,000 barrels a day.

    Past research by The Goodman Group has taken aim at other projects' stated economic benefits, such as Enbridge Inc.'s (TSX:ENB) Line 9 reversal between southern Ontario and Montreal and TransCanada Corp.'s (TSX:TRP) Keystone XL pipeline to the U.S.

    MORE National ARTICLES

    Court Deadline Passes But Tents Remain Up At Homeless Camp In Vancouver Park

    Court Deadline Passes But Tents Remain Up At Homeless Camp In Vancouver Park
    VANCOUVER - Tents remained up in a homeless camp on Vancouver's Downtown Eastside early Thursday, following an emotional day that saw a coroner remove a man's body and a court-imposed deadline to vacate the park pass.

    Court Deadline Passes But Tents Remain Up At Homeless Camp In Vancouver Park

    Union, seniors, disabled plan legal challenge over end of home mail delivery

    Union, seniors, disabled plan legal challenge over end of home mail delivery
    OTTAWA - Seniors' groups and organizations for people with disabilities are joining the Canadian Union of Postal Workers in a planned legal challenge to preserve home mail delivery.

    Union, seniors, disabled plan legal challenge over end of home mail delivery

    B.C. Can't Get Away With Voiding Contract Clauses: Teachers' Union Lawyer

    B.C. Can't Get Away With Voiding Contract Clauses: Teachers' Union Lawyer
    VANCOUVER - A litany of consequences arise if the British Columbia government is allowed to get away with rubbing out hundreds of clauses from the teachers' union's collective agreement, warns a lawyer for the B.C. Teachers' Federation.

    B.C. Can't Get Away With Voiding Contract Clauses: Teachers' Union Lawyer

    Body Removed From Tent In Vancouver's Homeless Camp As Injunction Looms

    Body Removed From Tent In Vancouver's Homeless Camp As Injunction Looms
    A coroner wheeled a body out of a homeless camp on Vancouver's Downtown Eastside just hours before police were expected to enforce an injunction ejecting occupants from the tent city.

    Body Removed From Tent In Vancouver's Homeless Camp As Injunction Looms

    Slocan: Friends of Fugitive Gunman Shot By B.C. Police Say He Was Harmless

    Slocan: Friends of Fugitive Gunman Shot By B.C. Police Say He Was Harmless
    SLOCAN, B.C. - Friends of a fugitive gunman shot to death by police near the village of Slocan, B.C., are expressing their grief and anger over what they consider a tragic end to the man's life.

    Slocan: Friends of Fugitive Gunman Shot By B.C. Police Say He Was Harmless

    Cabinet Decision On Site C Project Should Come By End Of Year: Minister

    Cabinet Decision On Site C Project Should Come By End Of Year: Minister
    VICTORIA - British Columbia's growing economy will need plenty of power for both business and population growth, but provincial Energy Minister Bill Bennett says the Site C dam on the Peace River still is not a certainty.

    Cabinet Decision On Site C Project Should Come By End Of Year: Minister