What delayed Alberta carbon capture project: analysts

Darpan News Desk The Canadian Press, 03 May, 2024 10:45 AM
  • What delayed Alberta carbon capture project: analysts

 

Capital Power's decision not to pursue its $2.4-billion Genesee project is unlikely to be the first of other such cancellations, said Scott MacDougall of the Pembina Institute, a clean energy think tank.

"I think (Genesee) is different enough that I wouldn't extrapolate too much," MacDougall said.

But Sara Hastings-Simon, who studies energy transition at the University of Calgary, said the backtracking underlines that, unlike some decarbonization strategies, carbon capture adds cost.

"When some people say this is going to be a big part of our decarbonization solution, the question is who's going to pay for it." 

And Thomas Timmins, head of energy practice for the law firm Gowling WLG, called Capital Power's decision a reminder that carbon capture technology is still new.

"It is not where the proponents of the technology might wish it were," Timmins said.

Carbon capture separates climate-changing gases such as carbon dioxide from exhaust and sequesters it deep underground. Industries from cement manufacture to the oilsands consider it one of the most promising ways to reduce their carbon emissions.  

Capital Power announced Wednesday it would no longer pursue carbon capture at its Genesee power plant near Edmonton because the economics no longer work. 

The decision removed Canada's largest such project from the books. Genesee would have stored three million tonnes of carbon dioxide a year -- about three times the storage rate of Shell's Quest project. 

In a conference call with analysts Wednesday, Capital Power CEO Avik Dey said the technology has a future. 

"I do feel strongly that carbon capture and sequestration works," he said.

But several factors convinced the company to pull the plug -- the uncertainty over how much Capital Power could earn from the carbon credits the project would generate, the amount of carbon price it would avoid and the cost per tonne of the captured carbon.

"I wouldn't say it's any one thing," he said. "We need all of it to work.

"What will unlock carbon capture and storage for natural gas is the (cost per unit of carbon) coming down such that we can work within whatever regulatory framework exists. We're just early."

Capital Power would have been the first natural gas plant to use the technology. That creates risks and adds costs, MacDougall said. 

"There would be some extra costs relative to the second or third project. Costs will come down for future deployments."

The process is better understood in other applications, he said.

"(Carbon capture) on gas turbines is quite different than (carbon capture) on gas boilers."

Another risk is that other carbon capture projects planned for Alberta could flood the market for the credits carbon capture would generate, lowering their value. 

Hastings-Simon said Alberta could address that risk by tightening up its industrial carbon emissions program. 

Making credits harder to earn would ensure their continuing value, she said. So would increasing the market by lowering emissions caps for other industries. 

"If you're willing to do that as a government, you can pretty much control that risk."

Governments can also guarantee companies an adequate floor price for the carbon credits they generate. 

But failing a groundbreaking technological innovation, Timmins said carbon capture will continue to need public support for projects to go ahead.

"It hasn't reached the level where it's commercially viable, yet," Timmins said. 

"What's needed? Either a breakthrough or government money."

 

MORE National ARTICLES

Third child under 10 dies of complications linked to influenza in B.C.

Third child under 10 dies of complications linked to influenza in B.C.
The latest update from the B.C. Centre for Disease Control says it received three reports of influenza-related deaths in children aged under 10 during the final week of 2023. It says that means influenza was a contributing factor but not necessarily the primary cause of death in the children.

Third child under 10 dies of complications linked to influenza in B.C.

Witnesses need to come forward in shooting, plea from Coquitlam RCMP

Witnesses need to come forward in shooting, plea from Coquitlam RCMP
Mounties in Coquitlam say they're looking for witnesses and video footage of a shooting Thursday afternoon. Coquitlam R-C-M-P say nobody was injured in the shooting, which happened before 3 p-m around Johnson Street and Glen Drive.

Witnesses need to come forward in shooting, plea from Coquitlam RCMP

Snowfall warning triggers travel advisories for two B.C. highways

Snowfall warning triggers travel advisories for two B.C. highways
Environment Canada has also issued snowfall warnings for a number of areas in B.C. as a low pressure system from the Pacific Ocean approaches after an unusually warm December. The weather agency says the area around Whistler and the Howe Sound can expect accumulation at elevations above 400 metres, with the ski resort community getting as much as 15 centimetres.

Snowfall warning triggers travel advisories for two B.C. highways

Surrey RCMP need public's help in locating missing male Narinder Sandhu

Surrey RCMP need public's help in locating missing male Narinder Sandhu
Narinder Sandhu is described as a 69 year old South Asian Male. He is 5"7 with a slim build with white facial hair. He is believed to be riding a white Infinity mountain bike. Anyone with information on the whereabouts of Narinder Sandhu is asked to contact the Surrey RCMP at 604 599 0502. 

Surrey RCMP need public's help in locating missing male Narinder Sandhu

Abbotsford Police handed out close to 300 tickets in project joyride

Abbotsford Police handed out close to 300 tickets in project joyride
Police in Abbotsford say they handed out close to 300 traffic tickets and impounded more than 100 vehicles in what it called "project joyride." The department’s traffic enforcement unit spent numerous shifts in October and November focusing on high-risk driving behaviours such as speeding and street racing.

Abbotsford Police handed out close to 300 tickets in project joyride

Trucking group's B.C. firm suspended for overpass strike, but still runs Alberta arm

Trucking group's B.C. firm suspended for overpass strike, but still runs Alberta arm
B.C.'s Transport Ministry says in a statement it has reached out to counterparts in Alberta about the suspension of the safety certificate for Chohan Freight Forwarders' 65-truck fleet. The statement came after social media users shared photographs they said were taken in B.C. this week that showed trucks branded "Chohan Group" and "Edmonton." A truck operated by Langley, B.C., based Chohan Freight Forwarders was involved in the Dec. 28 crash that lodged a steel girder in an overpass over Highway 99 in Delta.

Trucking group's B.C. firm suspended for overpass strike, but still runs Alberta arm