What delayed Alberta carbon capture project: analysts

Darpan News Desk The Canadian Press, 03 May, 2024 10:45 AM
  • What delayed Alberta carbon capture project: analysts

 

Capital Power's decision not to pursue its $2.4-billion Genesee project is unlikely to be the first of other such cancellations, said Scott MacDougall of the Pembina Institute, a clean energy think tank.

"I think (Genesee) is different enough that I wouldn't extrapolate too much," MacDougall said.

But Sara Hastings-Simon, who studies energy transition at the University of Calgary, said the backtracking underlines that, unlike some decarbonization strategies, carbon capture adds cost.

"When some people say this is going to be a big part of our decarbonization solution, the question is who's going to pay for it." 

And Thomas Timmins, head of energy practice for the law firm Gowling WLG, called Capital Power's decision a reminder that carbon capture technology is still new.

"It is not where the proponents of the technology might wish it were," Timmins said.

Carbon capture separates climate-changing gases such as carbon dioxide from exhaust and sequesters it deep underground. Industries from cement manufacture to the oilsands consider it one of the most promising ways to reduce their carbon emissions.  

Capital Power announced Wednesday it would no longer pursue carbon capture at its Genesee power plant near Edmonton because the economics no longer work. 

The decision removed Canada's largest such project from the books. Genesee would have stored three million tonnes of carbon dioxide a year -- about three times the storage rate of Shell's Quest project. 

In a conference call with analysts Wednesday, Capital Power CEO Avik Dey said the technology has a future. 

"I do feel strongly that carbon capture and sequestration works," he said.

But several factors convinced the company to pull the plug -- the uncertainty over how much Capital Power could earn from the carbon credits the project would generate, the amount of carbon price it would avoid and the cost per tonne of the captured carbon.

"I wouldn't say it's any one thing," he said. "We need all of it to work.

"What will unlock carbon capture and storage for natural gas is the (cost per unit of carbon) coming down such that we can work within whatever regulatory framework exists. We're just early."

Capital Power would have been the first natural gas plant to use the technology. That creates risks and adds costs, MacDougall said. 

"There would be some extra costs relative to the second or third project. Costs will come down for future deployments."

The process is better understood in other applications, he said.

"(Carbon capture) on gas turbines is quite different than (carbon capture) on gas boilers."

Another risk is that other carbon capture projects planned for Alberta could flood the market for the credits carbon capture would generate, lowering their value. 

Hastings-Simon said Alberta could address that risk by tightening up its industrial carbon emissions program. 

Making credits harder to earn would ensure their continuing value, she said. So would increasing the market by lowering emissions caps for other industries. 

"If you're willing to do that as a government, you can pretty much control that risk."

Governments can also guarantee companies an adequate floor price for the carbon credits they generate. 

But failing a groundbreaking technological innovation, Timmins said carbon capture will continue to need public support for projects to go ahead.

"It hasn't reached the level where it's commercially viable, yet," Timmins said. 

"What's needed? Either a breakthrough or government money."

 

MORE National ARTICLES

2 in hospital after Cloverdale collision

2 in hospital after Cloverdale collision
One man is in custody following a collision that sent two pedestrians to hospital yesterday afternoon. The pedestrians, a 24-year-old man and a 24-year old woman, were transported to hospital with serious injuries. A suspect was arrested in the area shortly after the collision.

2 in hospital after Cloverdale collision

Defence minister insists $1B spending reduction is not a budget cut

Defence minister insists $1B spending reduction is not a budget cut
The country's top soldier and outside experts say that finding almost $1 billion in savings in the Department of National Defence budget will affect the Armed Forces' capabilities, although the defence minister insisted Friday the budget is not being cut.

Defence minister insists $1B spending reduction is not a budget cut

European Union heads to visit Canada amid talks for access to EU science grants

European Union heads to visit Canada amid talks for access to EU science grants
The top heads of the European Union are expected to visit Canada this year, as officials discuss the possibility of Ottawa joining a major research-funding pact.  "We are expecting the summit still to take place this year," the EU's ambassador to Canada, Melita Gabric, said Friday.

European Union heads to visit Canada amid talks for access to EU science grants

6 coyote attacks in Prince George

6 coyote attacks in Prince George
Prince George Conservation and RCMP officers are “actively investigating” six separate coyote attacks within a week in the city. RCMP say in a statement they have issued a warning to the public after receiving separate complaints of the attacks.

6 coyote attacks in Prince George

BC leg Fall session starts tomorrow

BC leg Fall session starts tomorrow
The fall session of the legislature begins on Tuesday and the B-C government says homes, clean energy and public safety will top the agenda. House Leader and Minister of Housing, Ravi Kahlon says several pieces of legislation will be introduced during the seven week session, including plans to resolve zoning and permitting challenges and boost the supply of middle-income housing.

BC leg Fall session starts tomorrow

Orange Shirt Day march at UBC

Orange Shirt Day march at UBC
A march will be held on the University of B-C's Point Grey campus tomorrow in honour of Canada's third Truth and Reconciliation Day. The march also honours those who suffered at -- or did not come home from -- Indian residential schools in B-C and across the country.  

Orange Shirt Day march at UBC