What delayed Alberta carbon capture project: analysts

Darpan News Desk The Canadian Press, 03 May, 2024 10:45 AM
  • What delayed Alberta carbon capture project: analysts

 

Capital Power's decision not to pursue its $2.4-billion Genesee project is unlikely to be the first of other such cancellations, said Scott MacDougall of the Pembina Institute, a clean energy think tank.

"I think (Genesee) is different enough that I wouldn't extrapolate too much," MacDougall said.

But Sara Hastings-Simon, who studies energy transition at the University of Calgary, said the backtracking underlines that, unlike some decarbonization strategies, carbon capture adds cost.

"When some people say this is going to be a big part of our decarbonization solution, the question is who's going to pay for it." 

And Thomas Timmins, head of energy practice for the law firm Gowling WLG, called Capital Power's decision a reminder that carbon capture technology is still new.

"It is not where the proponents of the technology might wish it were," Timmins said.

Carbon capture separates climate-changing gases such as carbon dioxide from exhaust and sequesters it deep underground. Industries from cement manufacture to the oilsands consider it one of the most promising ways to reduce their carbon emissions.  

Capital Power announced Wednesday it would no longer pursue carbon capture at its Genesee power plant near Edmonton because the economics no longer work. 

The decision removed Canada's largest such project from the books. Genesee would have stored three million tonnes of carbon dioxide a year -- about three times the storage rate of Shell's Quest project. 

In a conference call with analysts Wednesday, Capital Power CEO Avik Dey said the technology has a future. 

"I do feel strongly that carbon capture and sequestration works," he said.

But several factors convinced the company to pull the plug -- the uncertainty over how much Capital Power could earn from the carbon credits the project would generate, the amount of carbon price it would avoid and the cost per tonne of the captured carbon.

"I wouldn't say it's any one thing," he said. "We need all of it to work.

"What will unlock carbon capture and storage for natural gas is the (cost per unit of carbon) coming down such that we can work within whatever regulatory framework exists. We're just early."

Capital Power would have been the first natural gas plant to use the technology. That creates risks and adds costs, MacDougall said. 

"There would be some extra costs relative to the second or third project. Costs will come down for future deployments."

The process is better understood in other applications, he said.

"(Carbon capture) on gas turbines is quite different than (carbon capture) on gas boilers."

Another risk is that other carbon capture projects planned for Alberta could flood the market for the credits carbon capture would generate, lowering their value. 

Hastings-Simon said Alberta could address that risk by tightening up its industrial carbon emissions program. 

Making credits harder to earn would ensure their continuing value, she said. So would increasing the market by lowering emissions caps for other industries. 

"If you're willing to do that as a government, you can pretty much control that risk."

Governments can also guarantee companies an adequate floor price for the carbon credits they generate. 

But failing a groundbreaking technological innovation, Timmins said carbon capture will continue to need public support for projects to go ahead.

"It hasn't reached the level where it's commercially viable, yet," Timmins said. 

"What's needed? Either a breakthrough or government money."

 

MORE National ARTICLES

Ongoing cases of online sexual extortions in North Vancouver

Ongoing cases of online sexual extortions in North Vancouver
Police in North Vancouver are warning residents of ongoing cases of online sexual extortions targeting youth in the area. Mounties say scammers are targeting males by creating fake female online profiles, luring the victims into performing sexual acts on camera.

Ongoing cases of online sexual extortions in North Vancouver

Critical health violations found in kitchen used by daycares after E. coli outbreak

Critical health violations found in kitchen used by daycares after E. coli outbreak
There have been 264 lab-confirmed cases of the bacterial infection since the outbreak at 11 daycares was declared on Sept. 4. Twenty-five patients are in hospital, 22 of whom have hemolytic uremic syndrome, a complication affecting the blood and kidneys. Six patients are on dialysis at Alberta Children's Hospital.

Critical health violations found in kitchen used by daycares after E. coli outbreak

Illicit drug "superlab" bust in Lumby

Illicit drug
R-C-M-P say they have wrapped up a case that shutdown an illicit drug "superlab" producing huge quantities of methamphetamine and fentanyl in the north Okanagan community of Lumby. In all, six people were convicted of running the lab which Seyed says was capable of producing millions of doses of potentially lethal fentanyl.  

Illicit drug "superlab" bust in Lumby

No charges for Vancouver cop: IIO

No charges for Vancouver cop: IIO
A Vancouver police officer will not be charged for subduing a man who was vandalizing cars, threatening people and damaging property in the city's West End in July 2021. The man suffered cuts to his face and head as well as a broken arm when he was confronted by two officers after numerous people called 9-1-1 to report a person was waving a tree branch and using it to damage cars and threaten other pedestrians.

No charges for Vancouver cop: IIO

House peppered with bullets: Richmond RCMP

House peppered with bullets: Richmond RCMP
Mounties in Richmond are investigating separate, late-night shootings that have left a house, vehicle and garage peppered with bullets. A statement from R-C-M-P says the first shooting in the 6300 block of Chelmsford Street happened more than two weeks ago, on August 27th, and the second occurred on August 29th.

House peppered with bullets: Richmond RCMP

B.C. premier breaks ground on second hospital, cancer centre at cost of $2.88 billion

B.C. premier breaks ground on second hospital, cancer centre at cost of $2.88 billion
A long-awaited and often promised second hospital for the City of Surrey marked a milestone today with a groundbreaking ceremony promising the opening of the new facility by 2029. Premier David Eby says the start of construction on the new $2.88 billion hospital and cancer treatment centre is an anticipated and needed health-care expansion in one of British Columbia's fastest growing communities.  

B.C. premier breaks ground on second hospital, cancer centre at cost of $2.88 billion