What delayed Alberta carbon capture project: analysts

Darpan News Desk The Canadian Press, 03 May, 2024 10:45 AM
  • What delayed Alberta carbon capture project: analysts

 

Capital Power's decision not to pursue its $2.4-billion Genesee project is unlikely to be the first of other such cancellations, said Scott MacDougall of the Pembina Institute, a clean energy think tank.

"I think (Genesee) is different enough that I wouldn't extrapolate too much," MacDougall said.

But Sara Hastings-Simon, who studies energy transition at the University of Calgary, said the backtracking underlines that, unlike some decarbonization strategies, carbon capture adds cost.

"When some people say this is going to be a big part of our decarbonization solution, the question is who's going to pay for it." 

And Thomas Timmins, head of energy practice for the law firm Gowling WLG, called Capital Power's decision a reminder that carbon capture technology is still new.

"It is not where the proponents of the technology might wish it were," Timmins said.

Carbon capture separates climate-changing gases such as carbon dioxide from exhaust and sequesters it deep underground. Industries from cement manufacture to the oilsands consider it one of the most promising ways to reduce their carbon emissions.  

Capital Power announced Wednesday it would no longer pursue carbon capture at its Genesee power plant near Edmonton because the economics no longer work. 

The decision removed Canada's largest such project from the books. Genesee would have stored three million tonnes of carbon dioxide a year -- about three times the storage rate of Shell's Quest project. 

In a conference call with analysts Wednesday, Capital Power CEO Avik Dey said the technology has a future. 

"I do feel strongly that carbon capture and sequestration works," he said.

But several factors convinced the company to pull the plug -- the uncertainty over how much Capital Power could earn from the carbon credits the project would generate, the amount of carbon price it would avoid and the cost per tonne of the captured carbon.

"I wouldn't say it's any one thing," he said. "We need all of it to work.

"What will unlock carbon capture and storage for natural gas is the (cost per unit of carbon) coming down such that we can work within whatever regulatory framework exists. We're just early."

Capital Power would have been the first natural gas plant to use the technology. That creates risks and adds costs, MacDougall said. 

"There would be some extra costs relative to the second or third project. Costs will come down for future deployments."

The process is better understood in other applications, he said.

"(Carbon capture) on gas turbines is quite different than (carbon capture) on gas boilers."

Another risk is that other carbon capture projects planned for Alberta could flood the market for the credits carbon capture would generate, lowering their value. 

Hastings-Simon said Alberta could address that risk by tightening up its industrial carbon emissions program. 

Making credits harder to earn would ensure their continuing value, she said. So would increasing the market by lowering emissions caps for other industries. 

"If you're willing to do that as a government, you can pretty much control that risk."

Governments can also guarantee companies an adequate floor price for the carbon credits they generate. 

But failing a groundbreaking technological innovation, Timmins said carbon capture will continue to need public support for projects to go ahead.

"It hasn't reached the level where it's commercially viable, yet," Timmins said. 

"What's needed? Either a breakthrough or government money."

 

MORE National ARTICLES

Staff at lodge for LNG workers in Kitimat, B.C., win 40% pay bump, averting strike

Staff at lodge for LNG workers in Kitimat, B.C., win 40% pay bump, averting strike
Employees at a lodge housing workers for LNG Canada's under-construction facility in Kitimat, B.C., have won wage increases of up to 40 per cent, averting a strike. The workers' union, Unite Here Local 40, says in a statement the new deal was reached after mediation with the employer at the BC Labour Board.  

Staff at lodge for LNG workers in Kitimat, B.C., win 40% pay bump, averting strike

Cooler weather sees B.C. wildfire numbers dip, but drought still poses concern

Cooler weather sees B.C. wildfire numbers dip, but drought still poses concern
The number of active wildfires in British Columbia has dipped below 450 as cooler weather and recent rain has cut the fire risk, although another hot spell could wipe out those gains as large sections of the province wilt under severe drought.

Cooler weather sees B.C. wildfire numbers dip, but drought still poses concern

Trudeau names new cabinet, shifting focus to economy, housing ahead of next election

Trudeau names new cabinet, shifting focus to economy, housing ahead of next election
Two-thirds of cabinet portfolios have switched hands, with seven rookie ministers coming in to replace the seven ministers who are leaving. Five of the new ministers represent constituencies in Ontario, one is from British Columbia and one from Quebec.  

Trudeau names new cabinet, shifting focus to economy, housing ahead of next election

2 new mass-timber courses to start at BCIT

2 new mass-timber courses to start at BCIT
Two new mass-timber courses are slated to begin in the fall at the British Columbia Institute of Technology. In addition, the province is providing 3.3-million-dollars to the school for the creation of a mass-timber training hub at B-C-I-T's Burnaby campus.

2 new mass-timber courses to start at BCIT

Prince George RCMP shooting leaves one injured

Prince George RCMP shooting leaves one injured
Mounties say it happened on Sunday morning at a home on Lalonde Road and that it was a targeted incident. They say surveillance footage shows a dark-coloured, extended cab pickup leaving the home at the time of the shooting.  

Prince George RCMP shooting leaves one injured

Surrey Council approves contract to build new Strawberry Hill Community Hall

Surrey Council approves contract to build new Strawberry Hill Community Hall
During the Regular Council Meeting on Monday, Surrey Council voted in favour of a $2.53M contract to build a new Strawberry Hill Community Hall. In 2021, a fire destroyed the historic Strawberry Hill Hall that was currently under construction as part of a $1.2M rehabilitation project that would have seen areas built for childcare and community rentals. 

Surrey Council approves contract to build new Strawberry Hill Community Hall