What delayed Alberta carbon capture project: analysts

Darpan News Desk The Canadian Press, 03 May, 2024 10:45 AM
  • What delayed Alberta carbon capture project: analysts

 

Capital Power's decision not to pursue its $2.4-billion Genesee project is unlikely to be the first of other such cancellations, said Scott MacDougall of the Pembina Institute, a clean energy think tank.

"I think (Genesee) is different enough that I wouldn't extrapolate too much," MacDougall said.

But Sara Hastings-Simon, who studies energy transition at the University of Calgary, said the backtracking underlines that, unlike some decarbonization strategies, carbon capture adds cost.

"When some people say this is going to be a big part of our decarbonization solution, the question is who's going to pay for it." 

And Thomas Timmins, head of energy practice for the law firm Gowling WLG, called Capital Power's decision a reminder that carbon capture technology is still new.

"It is not where the proponents of the technology might wish it were," Timmins said.

Carbon capture separates climate-changing gases such as carbon dioxide from exhaust and sequesters it deep underground. Industries from cement manufacture to the oilsands consider it one of the most promising ways to reduce their carbon emissions.  

Capital Power announced Wednesday it would no longer pursue carbon capture at its Genesee power plant near Edmonton because the economics no longer work. 

The decision removed Canada's largest such project from the books. Genesee would have stored three million tonnes of carbon dioxide a year -- about three times the storage rate of Shell's Quest project. 

In a conference call with analysts Wednesday, Capital Power CEO Avik Dey said the technology has a future. 

"I do feel strongly that carbon capture and sequestration works," he said.

But several factors convinced the company to pull the plug -- the uncertainty over how much Capital Power could earn from the carbon credits the project would generate, the amount of carbon price it would avoid and the cost per tonne of the captured carbon.

"I wouldn't say it's any one thing," he said. "We need all of it to work.

"What will unlock carbon capture and storage for natural gas is the (cost per unit of carbon) coming down such that we can work within whatever regulatory framework exists. We're just early."

Capital Power would have been the first natural gas plant to use the technology. That creates risks and adds costs, MacDougall said. 

"There would be some extra costs relative to the second or third project. Costs will come down for future deployments."

The process is better understood in other applications, he said.

"(Carbon capture) on gas turbines is quite different than (carbon capture) on gas boilers."

Another risk is that other carbon capture projects planned for Alberta could flood the market for the credits carbon capture would generate, lowering their value. 

Hastings-Simon said Alberta could address that risk by tightening up its industrial carbon emissions program. 

Making credits harder to earn would ensure their continuing value, she said. So would increasing the market by lowering emissions caps for other industries. 

"If you're willing to do that as a government, you can pretty much control that risk."

Governments can also guarantee companies an adequate floor price for the carbon credits they generate. 

But failing a groundbreaking technological innovation, Timmins said carbon capture will continue to need public support for projects to go ahead.

"It hasn't reached the level where it's commercially viable, yet," Timmins said. 

"What's needed? Either a breakthrough or government money."

 

MORE National ARTICLES

RCMP says Lytton wildfire probe still active, two years after village's destruction

RCMP says Lytton wildfire probe still active, two years after village's destruction
The Village of Lytton and the Thompson-Nicola Regional District are suing Canadian National and Canadian Pacific railways and Transport Canada, alleging they were negligent to let trains pass through the town during the heat dome. The district says the claim was brought on its behalf by its insurer, the Municipal Insurance Association of B.C.

RCMP says Lytton wildfire probe still active, two years after village's destruction

Series of trailer and skid-steer thefts result in over $150K

Series of trailer and skid-steer thefts result in over $150K
Between May and June 2023, a suspect male has attended various Home Depot locations in Langley, Vancouver, Burnaby, Coquitlam and Port Coquitlam to steal Bobcat510 wheeled skid-steers and trailers. In all five incidents, the suspect rented the skid-steers using a false name, removed the GPS trackers and never returned them.  

Series of trailer and skid-steer thefts result in over $150K

Lack of B.C. transplant surgeons means donated kidneys are sent elsewhere: doctors

Lack of B.C. transplant surgeons means donated kidneys are sent elsewhere: doctors
Dr. David Harriman, a kidney transplant surgeon at Vancouver General Hospital, said between eight and 10 surgeons are needed in B.C. so residents waiting for a kidney can benefit from the organs that were donated in the province. The B.C. Health Ministry said the province had six kidney transplant surgeons in 2018. 

Lack of B.C. transplant surgeons means donated kidneys are sent elsewhere: doctors

New Chinese Canadian Museum opens its doors in historic Vancouver Chinatown building

New Chinese Canadian Museum opens its doors in historic Vancouver Chinatown building
The museum opens its permanent location in Chinatown's historic Wing Sang Building after more than six years of planning, starting with then-premier John Horgan mandating the province's Tourism, Arts and Culture Ministry to establish the institution.  

New Chinese Canadian Museum opens its doors in historic Vancouver Chinatown building

Family appeals to public on one-year anniversary of Port Coquitlam shooting

Family appeals to public on one-year anniversary of Port Coquitlam shooting
Around 1 A-M on June 30th last year, police responded to reports of gunshots. Officers arrived to find 37-year old Mehdi “Damian” Eslahian suffering from gunshot wounds outside a home in Port Coquitlam, and he died at the scene.

Family appeals to public on one-year anniversary of Port Coquitlam shooting

B.C. must urgently change forest strategies or face more wildfire disasters: report

B.C. must urgently change forest strategies or face more wildfire disasters: report
British Columbia's independent forests watchdog is calling for the provincial government to make critical changes to how it manages forests to reduce the risk of catastrophic wildfires. It comes as the largest wildfire in the province's history, the Donnie Creek wildfire, continues to burn out of control in the remote northeast.  

B.C. must urgently change forest strategies or face more wildfire disasters: report