Auditor general finds F-35 costs soar amid project delays, pilot shortages

Darpan News Desk The Canadian Press, 10 Jun, 2025 11:44 AM
  • Auditor general finds F-35 costs soar amid project delays, pilot shortages

The estimated cost of Canada’s incoming fleet of advanced stealth fighters exploded by nearly 50 per cent in just a few years, auditor general Karen Hogan said Tuesday in a new report.

The fighter jet audit was one of eight tabled in the House of Commons by Hogan and environment commissioner Jerry DeMarco. The reports flag problematic procurement contracts, a backlog in applications for First Nations status and a delay in reducing the amount of federal office space.

An investigation by the auditor general concluded that costs associated with the F-35 advanced fighter jet program are running $8.7 billion higher than the original estimates.

And it warns the program is being plagued by delays and critical shortfalls — including a lack of qualified pilots.

The report lands in the middle of an active review ordered by Prime Minister Mark Carney to examine possible alternatives to the F-35. He ordered the review in response to U.S. President Donald Trump’s trade war with Canada.

National Defence said in 2022 the base price for the F-35s would be $19 billion. Just two years later, the number has climbed to $27.7 billion. That estimate does not include figures for infrastructure upgrades or weapons.

The report says the department’s 2022 estimates relied on outdated data from 2019 — despite the availability of better estimates showing “that costs of the aircraft had already increased substantially.”

The audit says issues associated with the global pandemic — such as runaway inflation, rising costs for facilities and munitions and volatile foreign exchange rates — pushed the price tag sky high.

Defence Minister David McGuinty's office sent out a written statement to media that blamed the increased costs on "external economic conditions driven by the COVID-19 pandemic, including global supply chain disruptions, workforce shortages, and increased inflation and foreign exchange rates."

"In combination with increased global tensions and related impacts on the availability and demand for materials, we would not have been able to deliver the full scope of this project under our previous budget," he said in the statement.

But Hogan also warned Tuesday that the program faces “significant risks that could jeopardize the timely introduction of the new fleet.”

She said the department successfully identified the risks but has not planned appropriately to mitigate them.

Construction of two new fighter squadron facilities — in Cold Lake, Alta., and Bagotville, Que. — is running three years behind schedule. The report says the facilities will not be ready until at least 2031 because the department needs to “redo important elements” of their design.

The department started planning the new facilities in 2020 before the government had settled on the F-35. The aircraft comes with significant infrastructure security requirements.

Costs to develop an interim solution to support the new jets will further increase infrastructure expenses,” the report warned.

It said the department produced a contingency plan to operate the aircraft from temporary facilities but the plan fell short because it was incomplete and offered “no proposed actions nor a cost estimate.”

Canada is also still short of qualified pilots to fly the advanced aircraft — despite being warned about this in 2018.

The report said the F-35 program lacks measures to minimize potential risks and the department failed to produce robust contingency plans. It notes that the department identified cost overruns from inflation and currency fluctuations as potential risks to monitor, but plans to track those risks were never approved by officials.

The Liberal government announced in 2017 it planned to purchase 88 new fighter jets. It signed a contract with Lockheed Martin for the F-35s in 2023.

The modern jets are needed to replace Canada’s aging CF-18 fleet, which is nearing the end of its service life.

The fighter jets are expected to be delivered between 2026 and 2032. Over the next two years, the initial eight will be sent to a U.S. air force base in Arizona, where Canadian pilots will be trained to fly them. The rest will be delivered to Canada starting in 2028.

The report said the Joint Strike Fighter Program Office conducted various assessments that uncovered “significant issues,” such as “insufficient departmental engineering personnel to service support equipment for both the CF-18 Hornet and CF-35A during the transition.”

The audit said that at the end of the last fiscal year in March, National Defence earmarked $935 million for the U.S. government for the first four jets and related items needed to produce another eight aircraft. It says about $197 million has been paid out already.

On top of that, National Defence spent another $516 million on the project, including $270 million in infrastructure costs.

Picture Courtesy: AP Photo/Aijaz Rahi, File

MORE National ARTICLES

Court orders B.C. to pass law giving French school board expropriation powers

Court orders B.C. to pass law giving French school board expropriation powers
The B.C. Supreme Court has ordered the provincial government to pass a law within six months providing the Francophone School Board with powers to expropriate private property to build new French-language schools.

Court orders B.C. to pass law giving French school board expropriation powers

Canadian doctors group challenging constitutionality of Alberta transgender law

Canadian doctors group challenging constitutionality of Alberta transgender law
A group representing Canada's doctors is challenging the constitutionality of Alberta's legislation limiting access to medical treatment for transgender youth, arguing it violates their Charter right to freedom of conscience.

Canadian doctors group challenging constitutionality of Alberta transgender law

Human smuggler sentenced to 6 1/2 years in case of frozen family

Human smuggler sentenced to 6 1/2 years in case of frozen family
A judge in Minnesota has sentenced Steve Shand to 6 1/2 years for his role in a human smuggling operation that saw a family freeze to death in southern Manitoba near the Canada-U.S. border.

Human smuggler sentenced to 6 1/2 years in case of frozen family

Edmonton school trustees, advocates want province to allow undocumented kids to enrol

Edmonton school trustees, advocates want province to allow undocumented kids to enrol
Edmonton public school trustees have voted to push Alberta's government to make legislative changes to allow undocumented kids to enrol in school.

Edmonton school trustees, advocates want province to allow undocumented kids to enrol

Canada Post puts forward ‘final offers’ to union as overtime ban continues

Canada Post puts forward ‘final offers’ to union as overtime ban continues
Canada Post on Wednesday laid out its "final offers" to the union representing 55,000 workers after negotiations resumed Wednesday morning, as tensions run high over the future of the beleaguered institution.

Canada Post puts forward ‘final offers’ to union as overtime ban continues

Never going to happen': Ministers push back as Trump revives talk of annexing Canada

Never going to happen': Ministers push back as Trump revives talk of annexing Canada
Canada's sovereignty was front and centre as federal ministers and Liberal MPs fielded questions about U.S. President Donald Trump's latest talk of annexation ahead of the first post-election question period in the House of Commons.

Never going to happen': Ministers push back as Trump revives talk of annexing Canada