Auditor general finds F-35 costs soar amid project delays, pilot shortages

Darpan News Desk The Canadian Press, 10 Jun, 2025 11:44 AM
  • Auditor general finds F-35 costs soar amid project delays, pilot shortages

The estimated cost of Canada’s incoming fleet of advanced stealth fighters exploded by nearly 50 per cent in just a few years, auditor general Karen Hogan said Tuesday in a new report.

The fighter jet audit was one of eight tabled in the House of Commons by Hogan and environment commissioner Jerry DeMarco. The reports flag problematic procurement contracts, a backlog in applications for First Nations status and a delay in reducing the amount of federal office space.

An investigation by the auditor general concluded that costs associated with the F-35 advanced fighter jet program are running $8.7 billion higher than the original estimates.

And it warns the program is being plagued by delays and critical shortfalls — including a lack of qualified pilots.

The report lands in the middle of an active review ordered by Prime Minister Mark Carney to examine possible alternatives to the F-35. He ordered the review in response to U.S. President Donald Trump’s trade war with Canada.

National Defence said in 2022 the base price for the F-35s would be $19 billion. Just two years later, the number has climbed to $27.7 billion. That estimate does not include figures for infrastructure upgrades or weapons.

The report says the department’s 2022 estimates relied on outdated data from 2019 — despite the availability of better estimates showing “that costs of the aircraft had already increased substantially.”

The audit says issues associated with the global pandemic — such as runaway inflation, rising costs for facilities and munitions and volatile foreign exchange rates — pushed the price tag sky high.

Defence Minister David McGuinty's office sent out a written statement to media that blamed the increased costs on "external economic conditions driven by the COVID-19 pandemic, including global supply chain disruptions, workforce shortages, and increased inflation and foreign exchange rates."

"In combination with increased global tensions and related impacts on the availability and demand for materials, we would not have been able to deliver the full scope of this project under our previous budget," he said in the statement.

But Hogan also warned Tuesday that the program faces “significant risks that could jeopardize the timely introduction of the new fleet.”

She said the department successfully identified the risks but has not planned appropriately to mitigate them.

Construction of two new fighter squadron facilities — in Cold Lake, Alta., and Bagotville, Que. — is running three years behind schedule. The report says the facilities will not be ready until at least 2031 because the department needs to “redo important elements” of their design.

The department started planning the new facilities in 2020 before the government had settled on the F-35. The aircraft comes with significant infrastructure security requirements.

Costs to develop an interim solution to support the new jets will further increase infrastructure expenses,” the report warned.

It said the department produced a contingency plan to operate the aircraft from temporary facilities but the plan fell short because it was incomplete and offered “no proposed actions nor a cost estimate.”

Canada is also still short of qualified pilots to fly the advanced aircraft — despite being warned about this in 2018.

The report said the F-35 program lacks measures to minimize potential risks and the department failed to produce robust contingency plans. It notes that the department identified cost overruns from inflation and currency fluctuations as potential risks to monitor, but plans to track those risks were never approved by officials.

The Liberal government announced in 2017 it planned to purchase 88 new fighter jets. It signed a contract with Lockheed Martin for the F-35s in 2023.

The modern jets are needed to replace Canada’s aging CF-18 fleet, which is nearing the end of its service life.

The fighter jets are expected to be delivered between 2026 and 2032. Over the next two years, the initial eight will be sent to a U.S. air force base in Arizona, where Canadian pilots will be trained to fly them. The rest will be delivered to Canada starting in 2028.

The report said the Joint Strike Fighter Program Office conducted various assessments that uncovered “significant issues,” such as “insufficient departmental engineering personnel to service support equipment for both the CF-18 Hornet and CF-35A during the transition.”

The audit said that at the end of the last fiscal year in March, National Defence earmarked $935 million for the U.S. government for the first four jets and related items needed to produce another eight aircraft. It says about $197 million has been paid out already.

On top of that, National Defence spent another $516 million on the project, including $270 million in infrastructure costs.

Picture Courtesy: AP Photo/Aijaz Rahi, File

MORE National ARTICLES

King Charles, Queen Camilla delight Ottawa crowds with 'momentous' royal visit

King Charles, Queen Camilla delight Ottawa crowds with 'momentous' royal visit
Thousands of royal watchers gathered on a sunny Monday afternoon in Ottawa to give King Charles and Queen Camilla a taste of Canadian hospitality during their short but highly symbolic trip.

King Charles, Queen Camilla delight Ottawa crowds with 'momentous' royal visit

Canada faces 'massive challenge' as NATO eyes new 5% spending target: expert

Canada faces 'massive challenge' as NATO eyes new 5% spending target: expert
When representatives of NATO nations meet in The Hague late next month, they're expected to dramatically hike the alliance's defence spending target for members — the one Canada is failing to hit already

Canada faces 'massive challenge' as NATO eyes new 5% spending target: expert

B.C. orders Hobo Hot Spring restored, as new fence blocks off public use

B.C. orders Hobo Hot Spring restored, as new fence blocks off public use
The British Columbia government has ordered the restoration of free natural hot spring pools that were mysteriously filled with dirt and boulders last fall.

B.C. orders Hobo Hot Spring restored, as new fence blocks off public use

Hockey players' sexual assault trial watches Michael McLeod's police interview

Hockey players' sexual assault trial watches Michael McLeod's police interview
The sexual assault trial of five former members of Canada's world junior hockey team is watching a video of an interview one of the accused gave to police months after the alleged incident.

Hockey players' sexual assault trial watches Michael McLeod's police interview

Residents across the Prairies flee, others on edge due to wildfire threats

Residents across the Prairies flee, others on edge due to wildfire threats
In remote locations from Alberta to Manitoba, wildfires forced residents from their homes Tuesday while others remained on edge as flames inched closer to their communities.

Residents across the Prairies flee, others on edge due to wildfire threats

Minister's bid to soothe concerns over B.C. fast-track bill is rejected

Minister's bid to soothe concerns over B.C. fast-track bill is rejected
Contentious British Columbia legislation to speed up infrastructure projects is heading toward passage unchanged after a government amendment to improve consultation with First Nations failed. 

Minister's bid to soothe concerns over B.C. fast-track bill is rejected