Auditor general finds F-35 costs soar amid project delays, pilot shortages

Darpan News Desk The Canadian Press, 10 Jun, 2025 11:44 AM
  • Auditor general finds F-35 costs soar amid project delays, pilot shortages

The estimated cost of Canada’s incoming fleet of advanced stealth fighters exploded by nearly 50 per cent in just a few years, auditor general Karen Hogan said Tuesday in a new report.

The fighter jet audit was one of eight tabled in the House of Commons by Hogan and environment commissioner Jerry DeMarco. The reports flag problematic procurement contracts, a backlog in applications for First Nations status and a delay in reducing the amount of federal office space.

An investigation by the auditor general concluded that costs associated with the F-35 advanced fighter jet program are running $8.7 billion higher than the original estimates.

And it warns the program is being plagued by delays and critical shortfalls — including a lack of qualified pilots.

The report lands in the middle of an active review ordered by Prime Minister Mark Carney to examine possible alternatives to the F-35. He ordered the review in response to U.S. President Donald Trump’s trade war with Canada.

National Defence said in 2022 the base price for the F-35s would be $19 billion. Just two years later, the number has climbed to $27.7 billion. That estimate does not include figures for infrastructure upgrades or weapons.

The report says the department’s 2022 estimates relied on outdated data from 2019 — despite the availability of better estimates showing “that costs of the aircraft had already increased substantially.”

The audit says issues associated with the global pandemic — such as runaway inflation, rising costs for facilities and munitions and volatile foreign exchange rates — pushed the price tag sky high.

Defence Minister David McGuinty's office sent out a written statement to media that blamed the increased costs on "external economic conditions driven by the COVID-19 pandemic, including global supply chain disruptions, workforce shortages, and increased inflation and foreign exchange rates."

"In combination with increased global tensions and related impacts on the availability and demand for materials, we would not have been able to deliver the full scope of this project under our previous budget," he said in the statement.

But Hogan also warned Tuesday that the program faces “significant risks that could jeopardize the timely introduction of the new fleet.”

She said the department successfully identified the risks but has not planned appropriately to mitigate them.

Construction of two new fighter squadron facilities — in Cold Lake, Alta., and Bagotville, Que. — is running three years behind schedule. The report says the facilities will not be ready until at least 2031 because the department needs to “redo important elements” of their design.

The department started planning the new facilities in 2020 before the government had settled on the F-35. The aircraft comes with significant infrastructure security requirements.

Costs to develop an interim solution to support the new jets will further increase infrastructure expenses,” the report warned.

It said the department produced a contingency plan to operate the aircraft from temporary facilities but the plan fell short because it was incomplete and offered “no proposed actions nor a cost estimate.”

Canada is also still short of qualified pilots to fly the advanced aircraft — despite being warned about this in 2018.

The report said the F-35 program lacks measures to minimize potential risks and the department failed to produce robust contingency plans. It notes that the department identified cost overruns from inflation and currency fluctuations as potential risks to monitor, but plans to track those risks were never approved by officials.

The Liberal government announced in 2017 it planned to purchase 88 new fighter jets. It signed a contract with Lockheed Martin for the F-35s in 2023.

The modern jets are needed to replace Canada’s aging CF-18 fleet, which is nearing the end of its service life.

The fighter jets are expected to be delivered between 2026 and 2032. Over the next two years, the initial eight will be sent to a U.S. air force base in Arizona, where Canadian pilots will be trained to fly them. The rest will be delivered to Canada starting in 2028.

The report said the Joint Strike Fighter Program Office conducted various assessments that uncovered “significant issues,” such as “insufficient departmental engineering personnel to service support equipment for both the CF-18 Hornet and CF-35A during the transition.”

The audit said that at the end of the last fiscal year in March, National Defence earmarked $935 million for the U.S. government for the first four jets and related items needed to produce another eight aircraft. It says about $197 million has been paid out already.

On top of that, National Defence spent another $516 million on the project, including $270 million in infrastructure costs.

Picture Courtesy: AP Photo/Aijaz Rahi, File

MORE National ARTICLES

Trump vs. Harvard: Canadian university athlete Ocean Ma caught in the crossfire

Trump vs. Harvard: Canadian university athlete Ocean Ma caught in the crossfire
Highlighted by an Ivy League title and a divisional crown at the national college playdowns, Canada's Ocean Ma enjoyed a memorable first season on Harvard's squash team. 

Trump vs. Harvard: Canadian university athlete Ocean Ma caught in the crossfire

King Charles, Queen Camilla arrive in Canada ahead of throne speech

King Charles, Queen Camilla arrive in Canada ahead of throne speech
King Charles arrived in Canada Monday afternoon for a short visit that will include reading the speech from the throne in Parliament.

King Charles, Queen Camilla arrive in Canada ahead of throne speech

Experts say linking Yukon, B.C. power grids a 'game-changer' but will take time

Experts say linking Yukon, B.C. power grids a 'game-changer' but will take time
Experts say the potential linking of British Columbia's power grid with Yukon would be a game-changer for the territory's quality of life and economy, but realization would likely take more than a decade.

Experts say linking Yukon, B.C. power grids a 'game-changer' but will take time

CRA cutting up to 280 permanent jobs in response to fiscal constraints

CRA cutting up to 280 permanent jobs in response to fiscal constraints
The Canada Revenue Agency is cutting up to 280 permanent employees in response to fiscal constraints.

CRA cutting up to 280 permanent jobs in response to fiscal constraints

Vancouver dismantles and consolidates festival memorials, advocates say it's too soon

Vancouver dismantles and consolidates festival memorials, advocates say it's too soon
For almost four weeks, the tributes to victims of the Lapu Lapu Day festival attack have grown -- piles of teddy bears, flowers, candles and cards stretching down Fraser Street from East 41st Avenue, then round the corner on East 43rd where the attack took place.

Vancouver dismantles and consolidates festival memorials, advocates say it's too soon

Steve Rai appointed Vancouver's new police chief after filling job in interim role

Steve Rai appointed Vancouver's new police chief after filling job in interim role
Newly minted Vancouver police chief Steve Rai says the city's diversity means its police department must be "accessible to everyone from all cultures," as he takes the helm at the department after the exit of former chief Adam Palmer. 

Steve Rai appointed Vancouver's new police chief after filling job in interim role