B.C. adds conditions for Trans Mountain expansion

Darpan News Desk The Canadian Press, 08 Mar, 2022 01:02 PM
  • B.C. adds conditions for Trans Mountain expansion

VANCOUVER - British Columbia has amended the conditions of its environmental assessment certificate for the Trans Mountain pipeline expansionand told the federal government it still has concerns about its response to potential marine oil spills.

The changes announced in late February focus on the impacts of marine shipping and potential oil spills from ships related to the pipeline project.

The expansion is set to nearly triple the capacity of the existing 1,150-kilometre pipeline that carries 300,000 barrels per day of petroleum products from Alberta to B.C., which will significantly increase the number of tankers carrying oil for export.

In a letter relaying B.C.'s updated conditions, Environment Minister George Heyman and Energy Minister Bruce Ralston urged federal Natural Resources Minister Jonathan Wilkinson to adopt a series of recommendations that would address the province's concernsafter it consulted with Indigenous nations, municipalities, government agencies and the public.

Those concerns would be most effectively addressed by Ottawa as part of the regulations and measures that fall under federal jurisdiction, Heyman and Ralston wrote in the letter, dated Feb. 24.

B.C. has made changes that are under its jurisdiction and sought to avoid duplicating existing federal regulations, the province said in a news release.

One of B.C.'s recommendations encourages Transport Canada to "expand the scope of its oversight" to include work done by the Western Canada Marine Response Corp., which responds to spills. In particular, it says Transport Canada's oversight should include shoreline cleanup, planning for sunken and submerged oil, co-ordinating volunteers, and managing wildlife and waste in the event of a spill.

"We strongly urge you to carefully consider these important recommendations, and to take action on them ... as soon as possible, so that the (Trans Mountain expansion) is operated in as safe a manner as possible," the ministers wrote.

Among B.C.'s new conditions is a requirement that Trans Mountain, a federal Crown corporation, provide a report on health risks in the event of a marine oil spill. It must identify measures to reduce human exposure and negative health effects and outline which authorities would be responsible.

Another condition requires Trans Mountain to provide a report with baseline data on B.C.'s shoreline in areas that could be affected by an oil spill, including Vancouver's English Bay and the Strait of Georgia. The report should include information on land use, infrastructure, flora and fauna, the order says.

The province has also amended a condition to require updates every five years on research Trans Mountain is involved with related to diluted bitumen and how the heavier, unrefined oil product could be cleaned up if spilled in water.

A Trans Mountain spokesperson said it is reviewing the changes to determine next steps.

Neither Wilkinson nor anyone from his Department of Natural Resources was available to comment on the provincial government's request.

Andrew Radzik, an energy campaigner with the Georgia Strait Alliance, said the province's changes are welcome, but gaps remain.

"If a spill happens, we've got better baseline data. So that's great, that's important. That's information that will inform spill response plans," he said in an interview.

"But they're not requiring shoreline spill response plans of a particular standard."

Instead, the province is relying on federal regulations on marine shipping and spill response that it has criticized for being too vague, Radzik said.

Transport Canada requires certified marine response organizations to treat 500 metres of shoreline per day and the Western Canada Marine Response Corp. has indicated it's working to increase its capacity to 3,000 metres.

But the existing regulations and emergency plans for the pipeline expansion lack some key detail, Radzik said, like what exactly it means to fully "treat" a shoreline.

The province shares jurisdiction along its shoreline and it could have amended the project's certificate to require more specific information or standards, he said.

On human health risks, Radzik said it's a step forwardfor B.C. to require an outline of the roles and responsibilities of different levels of government and the pipeline operator in reducing exposure after a potential spill.

However, it's not clear who would foot the bill for those health measures and what portion the province would have to pay, he said.

Asked why B.C.'s new conditions didn't include more specific requirements for marine spill preparedness and response, the Environment Ministry said the changes reflect certain criteria it had to follow in its review.

The opportunity for B.C. to change its environmental assessment certificate stemmed from a 2018 decision by the Federal Court of Appeal.It found the National Energy Board, since renamed the Canada Energy Regulator, had incorrectly excluded marine shipping from its assessment.

The regulator reconsidered the potential impacts, and the federal government used the subsequent report in 2019 to approve the pipeline expansion for a second time.

The B.C. Court of Appeal later decided that because the provincial ministers who issued the environmental assessment certificate had relied on the regulator's original assessment, they should have the opportunity to consider the later report and make changes, provided the issues related to differences between the two reports and fell under provincial jurisdiction.

MORE National ARTICLES

Boeing told fighter bid did not meet requirements

Boeing told fighter bid did not meet requirements
Three sources from industry and government say the message was delivered Wednesday as the other two companies competing for the $19-billion contract — U.S. defence giant Lockheed Martin and Swedish firm Saab — were told they met the government’s requirements.    

Boeing told fighter bid did not meet requirements

B.C. opens major highway section in Fraser Valley

B.C. opens major highway section in Fraser Valley
The provincial government says the section of Highway 1 between Chilliwack and Abbotsford has been cleared to reopen and that will connect the Lower Mainland to Highway 3 as major road routes continue to be rebuilt from last week's floods.

B.C. opens major highway section in Fraser Valley

People on B.C. Highway 8 facing long-term disaster

People on B.C. Highway 8 facing long-term disaster
The Nicola River, which runs along flood-damaged Highway 8, has changed course and left some farms underwater, Rice says. A subsequent mudslide wiped out the highway and destroyed or damaged dozens of properties in the area.    

People on B.C. Highway 8 facing long-term disaster

RCMP say B.C. shooting suspect in custody

RCMP say B.C. shooting suspect in custody
Police say a suspect is in custody after officers responded to reports of a shooter at an RCMP detachment in northern British Columbia Cpl. Madonna Saunderson says there are no reported injuries at this time.

RCMP say B.C. shooting suspect in custody

Man shot in driveway in South Surrey

Man shot in driveway in South Surrey
On November 25, 2021,  at approximately 12:00 p.m., Surrey RCMP responded the report of a shooting in the 2900-block of 160 Street. One man was shot in the driveway of a residence. The victim was taken to local hospital with what is believed to be non-life threatening injuries.

Man shot in driveway in South Surrey

Canada's homicide rate jumped in 2020: StatCan

Canada's homicide rate jumped in 2020: StatCan
The new survey says 743 homicides were reported by Canadian police in 2020 — a figure that was the most since 1991 and includes the 22 victims of a gunman's rampage that began in Portapique, N.S., in April of last year.

Canada's homicide rate jumped in 2020: StatCan