BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

PM Carney cabinet to meet amid Palestine statehood talk, U.S. trade discussions

PM Carney cabinet to meet amid Palestine statehood talk, U.S. trade discussions
The meeting, set for 2 p.m. ET., comes as trade talks escalate and as Canada's closest peers move toward recognizing a Palestinian state.

PM Carney cabinet to meet amid Palestine statehood talk, U.S. trade discussions

Bank of Canada holds key rate at 2.75% as economy shows resilience to tariffs

Bank of Canada holds key rate at 2.75% as economy shows resilience to tariffs
The central bank’s policy rate remains at 2.75 per cent after a third consecutive hold.

Bank of Canada holds key rate at 2.75% as economy shows resilience to tariffs

Two Canadians and previous winner Kiran Desai on the Booker Prize long list

Two Canadians and previous winner Kiran Desai on the Booker Prize long list
“The Loneliness of Sonia and Sunny,” the 677-page tale of two young Indians making their way in the United States, is one of 13 books announced Tuesday as semifinalists for the prestigious 50,000-pound ($67,000) prize. The contenders include authors from nine countries on four continents.

Two Canadians and previous winner Kiran Desai on the Booker Prize long list

Wildfire near Lytton, B.C., larger than initial estimate after aerial mapping

Wildfire near Lytton, B.C., larger than initial estimate after aerial mapping
The service's latest update on the Cantilever Bar wildfire says it is now measured at 4.6 square kilometres, up from the 1.5 square kilometres reported earlier this week.

Wildfire near Lytton, B.C., larger than initial estimate after aerial mapping

'Don't see it coming:' minister pushes for preparedness after B.C. tsunami scare

'Don't see it coming:' minister pushes for preparedness after B.C. tsunami scare
But the province's emergency management minister says it's a reminder that B.C. has to always be prepared for the possibility of a quake closer to home.

'Don't see it coming:' minister pushes for preparedness after B.C. tsunami scare

Tax data suggests lethal Canadian arms still being exported to Israel

Tax data suggests lethal Canadian arms still being exported to Israel
"Canadian military products are deeply embedded in Israel's military infrastructure, despite our government's attempts to placate us," said Rachel Small of the group World Beyond War.

Tax data suggests lethal Canadian arms still being exported to Israel