BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Environment Canada heat warnings remain in effect from Ontario to Newfoundland

Environment Canada heat warnings remain in effect from Ontario to Newfoundland
Some areas in southern Ontario, including Windsor and Toronto, were also under a heat warning but the weather agency had lifted it as of Thursday morning. 

Environment Canada heat warnings remain in effect from Ontario to Newfoundland

Man charged with impersonating North Vancouver Mountie

Man charged with impersonating North Vancouver Mountie
They say the man was driving a Ford F-150 with lights that resembled emergency vehicle lights.

Man charged with impersonating North Vancouver Mountie

Woman arrested in Langley, B.C., for assault causing severe burns

Woman arrested in Langley, B.C., for assault causing severe burns
They previously said officers responded to a report of a woman in distress along a stretch of the Fraser Highway lined with businesses near the city's downtown area at about 6:35 p.m. on Saturday.

Woman arrested in Langley, B.C., for assault causing severe burns

B.C. Premier David Eby reshuffles cabinet to boost economy and jobs

B.C. Premier David Eby reshuffles cabinet to boost economy and jobs
Former housing minister Ravi Kahlon takes over as minister responsible for jobs from Diana Gibson, who moves into the citizens' services role previously held by George Chow. 

B.C. Premier David Eby reshuffles cabinet to boost economy and jobs

Former commercial pilot charged with hijacking and terrorism over Vancouver flight

Former commercial pilot charged with hijacking and terrorism over Vancouver flight
But authorities elsewhere were hurrying to send planes to the scene — fighter jets tasked with intercepting the rogue flight.

Former commercial pilot charged with hijacking and terrorism over Vancouver flight

Unionized Canada Post workers to vote on deal starting July 21

Unionized Canada Post workers to vote on deal starting July 21
The Canada Industrial Relations Board will run the vote between July 21 and Aug. 1.

Unionized Canada Post workers to vote on deal starting July 21