BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

B.C. police watchdog calls hearing into officers' 'racist, sexist' WhatsApp group

B.C. police watchdog calls hearing into officers' 'racist, sexist' WhatsApp group
Prabhu Rajan says the allegations "go to the heart of public trust in policing" and the public hearing will also delve into a constitutional challenge filed in court last year by five of the subject officers. 

B.C. police watchdog calls hearing into officers' 'racist, sexist' WhatsApp group

Trump 'terminating' trade talks with Canada, threatens tariffs over Ottawa's digital services tax

Trump 'terminating' trade talks with Canada, threatens tariffs over Ottawa's digital services tax
Trump made the comments in a post on his social media account this afternoon.

Trump 'terminating' trade talks with Canada, threatens tariffs over Ottawa's digital services tax

Statistics Canada says real GDP down 0.1 per cent in April as manufacturing slowed

TD economist Marc Ercolao said the downside risks to Canada's economic growth are beginning to manifest, especially in tariff-exposed sectors. 

Statistics Canada says real GDP down 0.1 per cent in April as manufacturing slowed

Federal minister plans to hold consultations this summer on immigration intake

Federal minister plans to hold consultations this summer on immigration intake
An Immigration, Refugees and Citizenship Canada spokeswoman says the government expects schools to only accept students they can "reasonably support" by providing housing and other services.

Federal minister plans to hold consultations this summer on immigration intake

Canadian tourist found dead in Dominican Republic, officials say

Canadian tourist found dead in Dominican Republic, officials say
The country’s civil defence agency says 33-year-old Dorian Christian MacDonald was found dead in the water on a beach in the Puerto Plata resort town of Maimon Bay last Friday.

Canadian tourist found dead in Dominican Republic, officials say

Western Canada glaciers melting twice as fast as in previous decade, research says

Western Canada glaciers melting twice as fast as in previous decade, research says
The research led by University of Northern British Columbia professor Brian Menounos says low snow accumulation over winter, early-season heat waves, and prolonged warm and dry spells were contributing factors.

Western Canada glaciers melting twice as fast as in previous decade, research says